Illinois Groups Ask FERC to Dismiss GBE's Request to Amend its Negotiated Rate Authority

12/29/2023

0 Comments

 
Picture
There's a new filing in the on-going saga of GBE's FERC Negotiated Rate Authority.  As I wrote earlier, here and here, Grain Belt Express recently asked FERC to approve an "amendment" to its existing negotiated rate authority.  Missouri Landowners Alliance filed a protest and asked FERC to consider all the changes to the project, including its change of ownership since the original Negotiated Rate Authority was issued.  Missouri Landowners Alliance questioned whether GBE needed approval for the sale of its project to Invenergy under Sec. 203 of the Federal Power Act.  Invenergy responded saying that it didn't need permission.  But is that really true?

Yesterday, a coalition of Illinois groups filed a Motion for Summary Disposition, asking that FERC deny GBE's request for amendment to the existing negotiated rate authority.  The Illinois groups contend that when the project was sold, the negotiated rate authority issued to Clean Line expired because GBE did not get FERC approval for the sale.
In GBX’s view, the Commission has no jurisdiction over GBX’s activities until GBX hammers iron into the ground (GBX Limited Answer, pgs. 2-3); until that time, GBX is free to transfer that negotiated rate authority like a collectable baseball card. GBX’s logic makes a mockery of both the process by which the Commission determines whether an applicant should be granted negotiated rate authority and the Commission’s authority to review and approve sales, mergers and other transactions under FPA Section 203. 
20231228-5092_motion_for_summary_disposition_final_public.pdf
File Size: 8859 kb
File Type: pdf
Download File

And that pretty much describes ALL of the regulatory activity on GBE since Invenergy bought the project.  GBE has treated all its approvals as collectible baseball cards.  Invenergy did not buy a transmission project, it bought a set of state and federal approvals, and then methodically set about changing the actual project that was permitted without the regulator actually examining the new project.  It simply transferred the permits to a new project without proper examination.

The Illinois groups make the case why GBE should have to get the sale of its project approved, not simply "amend" its existing authority without proper examination of changed circumstances.

When GBE filed for its NRA "amendment" in early October, it expected to sail through a mere rubber stamping of its request so it could have new authority granted by December 5.  December 5 came, and December 5 went.  FERC doesn't seem to be in any particular hurry to ink up its stamp, and now that there is considerable controversy in this case, FERC must spend more time figuring things out.  GBE cannot advertise its capacity for sale, nor sign contracts to sell it, until it has FERC approval.

This must be extremely frustrating to Invenergy CEO Michael Polsky.  In a recent interview on Bloomberg, Polsky lamented that "we don't hear much" from FERC on a number of open dockets.  Isn't that a shame?  FERC isn't dancing to Polsky's serenade.  Also in this interview Polsky says that he thinks "the government" should pay for new transmission.  Well, that would make things rather simple for GBE, wouldn't it?  Then the merchant transmission project wouldn't need customers to fund it before it is built.  In Polsky's world, anyone who wants to build a transmission project would simply shake the taxpayer piggy bank until enough money falls out. Perhaps that's the way things work in Ukraine, but that's not where Polsky is operating.  He chose to come to this country and he must abide by our laws.

And while we're thinking about the elite Mr. Polsky, perhaps this article can also shed some light on how he makes money controlling energy policy?

Meanwhile, FERC continues to do "not much" on Invenergy's numerous open dockets, and Invenergy keeps filing stuff, like this recent complaint.  It must be really frustrating not to have a federal regulatory agency under your super rich thumb.

P.S.  Nice jacket!  Where does he find them?  Nightclub yard sale?
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.