StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

GBE Project Delayed Another 3 Years

12/12/2023

1 Comment

 
Grain Belt Express is complaining again.  Last week it filed a complaint with the Federal Energy Regulatory Commission against MISO, the Midcontinent Independent System Operator.  This makes the second complaint Invenergy filed against MISO regarding GBE.  The first complaint GBE filed is still languishing more than a year later.  This one will probably suffer a worse fate.

The problem is that MISO recently notified GBE that it was changing the date for connecting GBE to the MISO transmission system from December 1, 2027 to December 1, 2030 based on MISO's determination that some of the Network Upgrades that are required by MISO for Grain Belt's interconnection may not be ready by 2027.   GBE says it will have its project built in 2028 and wants MISO to allow it to connect some smaller portion of its capacity that does not rely on the Network Upgrades at that time.

MISO's rules do not allow for this kind of "limited operation," therefore MISO cannot grant it without changing its rules.  In order to change its rules, MISO must complete its stakeholder process, which can take years to talk about the rule changes, vote on the rule changes, get the rule changes approved by FERC, before they can become effective.  That's probably going to take longer than 2030 because MISO has a lot on its plate.

GBE tries to tell FERC that other system operators permit limited operation, therefore MISO should, too.  Too bad GBE never raised this issue and asked for this rule when the rules for merchant transmission were being made.  It is what it is... GBE cannot connect to MISO until 2030.  That's 7 years from now.

But what about those "Network Upgrades" that got delayed and required pushing GBE's interconnection out until 2030?  What are those upgrades?  According to GBE's complaint:
The Ameren upgrades involve two new 345 kV Montgomery-Burns transmission lines for which GBX will pay $126.5 million. The total cost of all upgrades that GBX is funding under the TCA is $217 million. In addition to permitting the two new Ameren transmission lines, Ameren mentioned some concerns about scheduling outages in connection with these lines and coordinating with AECI, which is an Affected System. 
Well, what do you know... two MORE 345kV transmission lines caused by GBE and that GBE needs to have built in order to connect its project.  First there was the GBE itself, then there was the 40-mile Tiger connector and now TWO 345kV lines connecting the new Burns substation in Callaway County to the existing Montgomery substation to the east.  Where is the Montgomery substation?
Picture
These 2 new 345kV transmission lines are the financial responsibility of GBE, but will be built by Ameren in its service territory.  Therefore, Ameren has to get them permitted by the PSC.  More landowners are going to be affected with new transmission only made necessary because of GBE.  But will these new landowners be entitled to 150% of fair market value?  What problems are going to crop up during permitting of these new lines?  Is it going to take them as long to get permitted as all the other GBE lines?  No wonder the connection date has been pushed out until 2030.

Grain Belt Express -- spreading the misery to thousands of landowners across Missouri for at least 20 years.  Will GBE even be relevant by then?
1 Comment
Do the math
12/13/2023 11:10:56 am

A 1 MW solar farm can be built for about $1 million.

How much has been spent on GBE so far? It is estimated Clean Line spent $200 million+ in the five years it owned the project. If Invenergy has spent the same in the five years they've owned it, it may be approaching $500 million.

Last I checked, only 250 MW of GBE has potential customers. For the same money that's already been spent, Clean Line and Invenergy could have satisfied all of these potential customers' want for renewable energy, maybe X2. No giant transmission lines needed. All paid for up front, no DOE loans or taxpayer money necessary.

Do the useful idiots who support this project really believe GBE cares about "saving the planet"? I think those folks need to volunteer their property and homes to host solar farms.

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.