StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Welcome To The Brave New World of Unreliable Renewables

5/28/2021

1 Comment

 
Picture
The North American Electric Reliability Corporation recently released its 2021 Summer Reliability Assessment.

Two words:  Buy candles.

NERC sees possible problems ahead in California and Texas.  Coincidentally, these regions have built a lot of renewables, which causes "more expensive" fossil fuel generators to close.

About California:
WECC-California is at risk of energy emergencies during periods of normal peak summer demand and high risk when above-normal demand is widespread in the west. Prior to summer, the planning reserve margin (which is based on existing and firm capacity) for the California-Mexico assessment area was below the 18.4% Reference Margin Level that WECC calculates is needed for maintaining loss-of-load risk below a 1-day-in-10-year benchmark (a 400 MW shortfall at peak demand). Probabilistic studies indicate 10,185 MWh of energy in the area is expected to go unserved this summer. Over 3 GW of additional resources are expected for this summer with most coming in the form of new solar photovoltaic (PV) generation. These generation plants can provide energy to support peak demand; however, solar PV output falls off rapidly in late afternoon while high demand often remains.
More electric use (homes, cars) combined with unreliable, variable renewables equals disaster.  How might California avoid it?
Imports to the area are needed to maintain reliability when demand peaks in the afternoon and to ramp up even further for several hours as internal resources draw down. California will have 675 MW of new battery energy storage systems on-line at the start of the summer that can continue to supply stored energy for periods when needed. Reliance on non-firm imports to cover high demand or low resource output conditions heightens the risk that operators will need to use energy emergency alerts (EEA)—and trigger the shedding of firm load in above-normal heat conditions—to maintain a stable BPS at times. Planned resource additions of 1,300 MW over the summer, including 825 MW of new battery storage, are expected to help mitigate late-summer risks.
California plans to suck energy out of neighboring regions.  California depends on other states to supply its energy.  Why?  It's not that California cannot build baseload generation that runs when called, like natural gas, it simply chooses not to.  Gotta meet those renewable energy goals, ya know.... at least on paper.  But are they really effective when the "dirty" energy is produced in other regions?  This is not realistic, and Californians may pay the price this summer with increased blackouts.

In addition, there's the risk that a weather event, such as a wide area heat wave for instance, can make less energy from other regions available as they deal with their own needs.  Imports are unreliable.

There's also:
Additionally, transmission networks can become stressed when events such as wildfires or wide-area heatwaves cause network congestion. The growing reliance on transfers within the Western Interconnection and falling resource capacity in many adjacent areas increases the risk that extreme events will lead to load interruption.

Operation of the BPS can be impacted in areas where wildfires are active as well as areas where there is heightened risk of wildfire ignition due to weather and ground conditions. Wildfire prevention planning in California and other areas include power shut-off programs in high fire-risk areas. When conditions warrant implementing these plans, power lines (including transmission-level lines) may be preemptively de-energized in high fire-risk areas to prevent wildfire ignitions.
So, even if other regions can supply the power California needs to meet its own need, it often can't happen during wildfire season because transmission is shut off so it doesn't start a fire.  Hey... don't you think BURYING transmission might allow it to continue to operate during wildfire season?  Overhead transmission and investor owned utility neglect caused by greed creates disaster.  Again, California's energy policies are insufficient to meet demand.  This isn't an aberration.  This is the new normal of a "clean" energy future.

About Texas:
Variable energy resources from wind and solar are critical to meeting peak electricity demand in ERCOT. Periods of low wind generation or higher-than expected thermal outages create a reliability risk during peak load hours. ERCOT appears to be in a weather cycle that may increase the risk of intensifying drought conditions and higher than normal summer temperatures. These weather factors could result in actual summer peak demand exceeding the forecast, which already anticipates record peak demand levels. Thermal outages may increase during severe and prolonged drought conditions due to cooling water supply and temperature issues.

Highest risk for unserved energy at peak demand hour, late afternoon (Risk can
extend for 1–2 hours after peak as solar PV output diminishes. Periods of low-wind, which usually occur 1–2 hours before peak demand, can also result in extended shortfall risk
.)
Again, reliance on variable, undependable renewables causes shortages.  Texas has a lot of wind and solar.  Blackouts are the result.

This is scary news.  However, the mainstream media chooses not to report reality (surprise!  surprise!).  Instead, the media chooses to focus on climate change being responsible for the shortages.  They also like to talk about other things that don't really matter, like the Colonial Pipeline hack.  Anything but the fact that electric systems dependent upon renewables are not dependable. 

Just look at the capacity factors for wind and solar in the table at the end of the NERC report. The lowest wind capacity factor is listed as 7%, with the majority of them hovering somewhere between 10 and 20%.  This means that those generators can only be expected to reliability produce 7% of their potential.  Do you know how much overbuilding these poor capacity figures require?  Does this even make sense?  We'd have to build way too many to get any kind of "reliability," and even then the "reliability" is only a percentage on paper... reality may differ. 

"But this turbine produces energy reliably 7% of the time!"  However, today is a 0% day." Off go the lights.

Speaking of plans that only work on paper... building enormous amounts of new overhead transmission in order to hook all these poorly performing renewables together to produce a 7% chance of getting energy is so much fantasy.  If increased reliance on renewables requires imports from other regions, what happens when all regions have increased reliance on renewables?  Where does the energy come from then?

The warning is stark.  Nobody is paying attention because it's not what they want to hear.

NERC officials warned:
The full report identifies the extent of the possible deficiencies, and Robb told reporters of his own concerns about how the energy transition might be impacting reliability.

"In our hurry to develop a cleaner resource base, reliability and energy adequacy have to be taken into consideration," he said.

The latest reliability assessment is "quite concerning," John Moura, NERC's director of reliability assessment and performance analysis, told reporters.

Summer 2020 and winter 2021 were "difficult to say the least," Moura said, and the latest assessment signals "similar risks" lie ahead.

In the long-term, system operators must do extensive analysis to ensure the addition of variable resources will not negatively impact reliability, he added. "As we look forward, it really just looks more stressful," Moura said, "because of the different resources coming onto the system."

Get used to it... electricity is going to become a "sometimes" commodity if we continue to spiral faster and faster towards the "zero carbon" fantasy.  Reliability will be sacrificed in the name of "climate change."  Didn't the "clean energy" folks tell us we'd have to make some hard choices?
1 Comment

PJM Plans Studies to Remove Transource IEC From its Plan

5/25/2021

1 Comment

 
Well, it seems that didn't take long.  PJM issued a statement yesterday according to trade press RTO Insider.
Officials at PJM said they were also reviewing the PUC’s decision and that it “appreciates the commission’s consideration.”

“PJM will commence the appropriate planning studies to determine next steps, including identifying any potential reliability issues due to removal of the project from the Regional Transmission Expansion Plan,” the RTO said in a statement.

So PJM is removing the IEC from its plan?  Is that some kind of Freudian slip or a sudden realization?

Dear Dr. Freud would probably also be verrrrry interrrrested in PJM's sudden interest in doing planning studies to identify any potential reliability issues due to removal of the project from its plan, since it refused to do these kinds of studies during the PUC case, insisting that some old data was good enough to determine there was a serious reliability issue that only IEC could solve. 

Was PJM lying then, or is it lying now?

I seem to remember PJM refusing to do these very same studies to support the project's "reliability" claims at the PUC.
The OCA also noted that Transource’s assertions regarding “reliability” as a basis for need refer to a single generation deliverability test performed by PJM in 2018.  Further, the OCA noted PJM neither, performed its full suite of reliability tests to confirm that these reliability violations will result in 2023, nor, performed another generation deliverability test since 2018 which may confirm or refute the results of the 2018 test.  
If PJM didn't do these studies during the PUC case, then it did not have to recognize that there is no reliability issue IEC must solve.  PJM's new studies may magically determine that the project isn't needed after all, and then PJM can remove it from the RTEP.  No fuss, no muss!

Hit it, Alanis...
1 Comment

Pennsylvania PUC Denies Transource IEC Project Application

5/24/2021

2 Comments

 
Picture
Late last week, the PA PUC voted on an Order denying the application of AEP affiliate Transource to build the Independence Energy Connection in Franklin and York Counties.  Today, the PUC issued the Order.

Denied, denied, denied, denied and denied!  The PUC also rescinded Transource's Certificate of Public Convenience and Necessity for the project, and ordered all related dockets closed.  As far as the PA PUC is concerned, the Transource nightmare is over and done.  Of course, Transource may (and probably will) ask the Commission to reconsider its decision.    After that, Transource may have certain rights to appeal the decision of the PUC.  However, chances of that being successful seem to be hovering between slim and none.

The Commission adopted the Recommended Decision of Judge Barnes, except as modified in the Order.  The modifications are few.  The Commission addressed all the exceptions to Judge Barnes' decision, and granted only one.  That one was the Judge's finding of fact regarding interference with GPS systems used in farming operations.  The Commission struck that finding, but it did not change the outcome.  The second bone of contention was Judge Barnes' recommendation that the Commission should issue a Rule to Show Cause why Transource's CPCN should not be rescinded.  The Commission simply skipped bothering with another proceeding and straight up rescinded Transource's CPCN in this Order.

The Commission reprimanded Transource over several of its exceptions.  One was its contention that ALL the findings of fact by Judge Barnes should be disregarded where they don't agree with Transource's contentions.  Transource forgot to mention WHY, or provide any facts whatsoever, to support this exception.  Exceptions must be specific, or the Commission cannot even consider them.  Denied!
In its Exception No. 8, Transource asserts that the ALJ’s recommendation to deny Project 9A is based on “faulty findings” without specifying any alleged factual or legal error.  In footnote to its Exception, Transource takes issue with certain specified findings by the ALJ and asserts, as a general matter, that all the ALJ’s findings of fact and conclusions of law should be disregarded to the extent the findings “are inconsistent with [Transource’s] Exceptions, Briefs and Testimony in this proceeding.”  Transource Exc. at 39, fn. 27 (emphasis added). 
 
We note that Transource’s Exception, as stated, fails to conform with Commission Regulations for stating exceptions, and lacks sufficient specificity to enable our review.  See 52 Pa. Code § 5.533 (pertaining to exceptions, requiring that the exceptions be stated with supporting reasons for each exception).  A general assertion that all the ALJ’s factual findings and legal conclusions should be disregarded to the extent they are “inconsistent” with a party’s filings does not state a supporting reason to disregard any of the findings and conclusions.  
Transource's team of crack lawyers (the best our money can buy!) should have known better.

They also should have known better regarding their crazy contention that the PA PUC has no authority (under federal law) to deny a project ordered by PJM.  Pennsylvania must evaluate the need for the project under statute.  Pennsylvania's statute is not satisfied by abdicating to PJM's findings of need.  I think this might be my favorite part:
... “need” from a PJM planning perspective may or may not be, as Transource asserts, “consistent with the standard for need under Pennsylvania law.”  It is for this Commission, not PJM, to decide whether the PJM planning perspective is, or is not, in line with the Pennsylvania standard for “need” under the Code, Commission Regulations and relevant caselaw.
BAM!  Read it and weep, Transource.  Of course, Transource must have known that this argument would lead nowhere, and possibly tick off the Commission.  But they went there anyhow.  Was it because Transource simply had nothing else?

Pennsylvania's Consumer Advocate deserves an MVP award for its work on this case.  The Consumer Advocate provided the experts and data that demonstrated how the transmission project would cause additional costs to ratepayers in Pennsylvania, and how PJM refused to consider these impacts.  PJM's claims simply were not true, no matter what lengths it went to in order to continue to push this project along towards approval.  It's refreshing to see all the PJM flim-flam stripped away, and for regulators to evaluate a transmission proposal based on its actual merits, instead of the glammed up package presented by a regional transmission organization.  The judge and the Commission are not buying PJM's story, and are not impressed in the least by PJM's self-importance or overly-complicated geek speak.  It is what it is, and IEC simply isn't needed.
Isn't it time for PJM to fall gracefully on its sword and cancel the project as it has done in the past for the PATH project, the MAPP project, the Monmouth County Reliability Project, and others, when the need for the project simply and magically evaporated?  C'mon, PJM, the time has come!

PJM's first foray into competitive market efficiency projects has been an overly expensive failure.  Transmission congestion is fleeting, and PJM's planning process simply takes too long.  The IEC was no longer needed by the time the PJM Board approved it.  But once PJM decides it wants a project, actual need no longer matters.  It's about the project, not the process.  The lengths PJM went to in order to continue to prop up this project are truly shameful.  It's time for PJM to come to terms with reality and fix its broken processes that allowed this travesty to play out over the last five years, including the changes it made to FERC-approved mechanisms that allow PJM to ignore cost increases to parts of the region caused by projects that lower costs for others, and to ignore new generation coming online on the other side of the transmission constraint.  It has now been proven that neither one of these policies will fool a state regulator on the question of "need."  When PJM does these things, it damages its credibility as a regional transmission planner.  How many times can PJM order and support projects that are not truly needed before they are simply unreliable and unbelievable?  PJM is not acting in the best interests of regional electric consumers when it orders unneeded projects.  It's acting in the financial interests of its utility members.  How many hundreds of millions of dollars have PJM electric consumers paid in their monthly electric bills for projects that were never built?  Transource's IEC, like other cancelled projects before it, will collect all its project costs through FERC-jurisdictional transmission rates even though the project was never built.  FERC transmission incentives allow the owner of a cancelled project to file to collect all its costs in the event of abandonment.  Transource gets made whole, and even earns a return (interest) on its investment until the project is finally paid off.  But what about the citizens, landowners, and communities who made a huge investment in legal fees in order to participate in the PUC case and uncover the truth?  What do they get?  Are they made whole?  No, they simply enjoy not being burdened by a new transmission line in their community, and the personal satisfaction of victory when speaking truth to power.

If it strikes your fancy, go ahead and tell PJM what you think about their actions, and urge them to cancel IEC before it costs you any more money.

Of course, this story would not be complete without recognizing the hundreds of concerned citizens who stepped up, organized, attended meetings and hearings, and participated in the regulatory process.  Ordinary people doing extraordinary things!  Their hard work and determination changed the course of history!  Despite PJM's original "constructability" analysis that the only impediments to this project sited on "vacant land" were bats and crossing state game land, the people have proven that there is no such thing as "vacant land" that nobody cares about.  People care deeply about their land and community, and they will do remarkable things to protect the places they call home.

Let's end with my favorite quote from cultural anthropologist Margaret Mead:
Never doubt that a small group of thoughtful, committed citizens can change the world; indeed, it's the only thing that ever has.
Congratulations, folks!  Let the parties begin!
2 Comments

Help Wanted!

5/21/2021

0 Comments

 
Now here's an interesting twist...  Dominion Virginia Energy wants the public's "advice" in siting its new transmission connection to its new offshore wind farm in the Virginia Beach area.
Dominion Energy Virginia is seeking public feedback and advice about linking its planned wind farm, 27 miles off the Virginia Beach shore, to the 500 kilovolt backbone of its statewide power grid at the Fentress substation on Centerville Turnpike in Chesapeake.
Bravo for taking suggestion, Dominion!  Communities burdened by new transmission will absolutely, positively rebel against a fait accompli transmission proposal.
Is there a "good" way to present a transmission line proposal to the public?  Not if you're approaching the communities with a fully-formed idea of what you're going to build and where you're going to put it.  The only good way to involve a community in a transmission proposal is to approach them with a need before making decisions about what to build and where.  Presenting a community with a problem to be solved and allowing meaningful input into the solution selected is the only way a transmission company can get community buy-in and support for the proposal.  Everything else is nothing more than a battle to push a bad idea the community doesn't want off onto someone else.
But Duh-minion only gets it half right... no,  maybe even less than that.  They simply use the *idea* that they are seeking community advice in an attempt to trick the community into thinking they are involved in solving a problem.  When all the window dressing is removed, this is nothing more than your routine transmission siting exercise. 

Dominion has already selected 6 routes.  The community gets to pick its favorite.  Are you kidding me?  That's not how it works and it's not going to fool anyone.  Dominion would have done better to ask for help connecting its offshore wind farm and left the siting options hidden for the time being.  Must be a control issue.  Dominion can't stand not having complete control.


The power company has part of the route nailed down: the 27 miles of underwater cable to a landing point at the state military reservation at Camp Pendleton. It also has proposed an underground route through the southernmost reaches of Naval Air Station Oceana, to comply with regulations restricting structures near airfields, which the Navy must still review.

Its research into what’s on the ground, in terms of neighborhoods, wetlands, wildlife and historic resources has led it to six options for the final roughly 15 miles to the Fentress station.

“We can look at maps and desktop it, but it’s not until we talk to people that we’ll really understand these alternatives,” said Kevin Curtis, Dominion’s vice president, electric transmission.

Guess what alternative they're going to get from the community?  Bury it.  All of it.  On existing rights of way.  Without that alternative, opposition begins.  Why?  Because burial is already an option for portions of the route, such as the path through the air station.  If Dominion can bury it under the ocean, and through the air station, then it can bury it the entire length.
One option for one of these routes would be to bury the lines for a stretch. That could create much more disruption during construction and mean they were costlier to install and repair than running lines overhead but would mean that portion of the lines would not be visible.
Oh, please!  These are transparent excuses that don't even make sense.  Too disruptive... as if having 3 separate overhead 230-kV lines in parallel isn't disruptive at all.  One time disruption to bury the project?  Or 50 years of disruption from an overhead line?  Installing a buried transmission line isn't really that disruptive.  They do it on streets all the time.  It's a shallow, narrow trench, not a whole lot different than fiber optic cable installation.  Costlier to install?  Maybe, but cheaper to maintain, especially in a coastal area subject to extreme weather.  Dominion's excuses are plainly excuses and completely illogical in the face of their plans to bury it at the air station and along a portion of one of the route alternatives.

With this kind of deceptive roll out, Dominion is doomed.  Why?
Five routes would run along the never-built Southeast Parkway, now an open space corridor through the most densely populated neighborhoods between Oceana and an area southwest of Princess Anne Road, between the Virginia Beach National Golf Course and the Princess Anne Athletic Complex.
Two words... densely populated.  It's over before it begins when Dominion ham-hands its rollout like this.

Help wanted?  Not hardly... unless the "help" Dominion is looking for consists of wildfire opposition leading to an entrenched battle.

Well, there goes that offshore wind idea.
0 Comments

Gag Me With A Spoon

5/21/2021

3 Comments

 
Picture
As if the 17-year locusts weren't enough for this spring, there's a more revolting creature crawling out of the ground lately.

Yesterday, Michael Skelly testified before a Congressional Committee in love with the Green New Deal.
He introduces himself like this:

My name is Michael Skelly and I am founder and CEO of Grid United, an early stage transmission development company. I have spent the last 25 years developing a wide variety of energy projects. I got involved in the US wind industry in the late 90’s, and helped put together thousands of megawatts of new wind projects. In 2009 I started a company called Clean Line Energy which focused on interstate power lines to move renewable energy around the country. We successfully permitted a three-state high voltage, direct current transmission line. We sold off our projects several years ago to other developers who are carrying them forward. Indeed, our Western Spirit project is now under construction in New Mexico.

What's an "early stage transmission development company?"  Is that what happens when you register a corporate name in Delaware, throw up a one-page website announcing you are "Coming Soon!", but you don't have any employees or funding, just another grandiose brain fart?  How soon is too soon to once again begin tilting at windmills after being kicked squarely in the mouth by spectacular, flaming failure?

The people have not forgotten.  Michael Skelly's reputation will precede him.  Who's going to give this guy another $200M to spend on crackpot transmission ideas?

Funny he doesn't mention his failure in his comments.  He says he "successfully permitted a three-state" transmission line.  Except there were no customers and the government cancelled its participation in the project, so there wasn't actually a permit after all.  The project (and the non-permit "permit") were cancelled.  That's not success.  The U.S. DOE never issued a "permit."  It issued a participation agreement based on certain conditions.  One condition was that the project had to have customers.  No customers, no project.  And furthermore, there is no developer who is "carrying forward" the Plains & Eastern Clean Line.  The project got chopped up and a portion bought up for an entirely different purpose.  That's not success, either.  Western Spirit?  You mean some other company did it better than Skelly?  That's also not success.  That's failure.

So, blah, blah, blah... you folks are just so nettlesome!
A decade ago, we as a country did not have such a fantastic opportunity set in front of us. However, in the ensuing years, both utilities and independent developers have been sorting through the nettlesome siting, permitting, cost allocation and grid connection challenges.
Nettlesome:  causing annoyance or difficulty. 

Michael Skelly wants you to stop annoying him.

Because "we as a country...".  Is that like last decade's "we as a society"?  Now Michael Skelly can speak for the whole country!  There ain't no "we" here.  Michael Skelly and his one-man band playing a nettlesome song for rural landowners.

Transmission plays a role in replacing the carbon and other pollution in these population centers with renewable sources of energy, thereby improving air quality for residents, and addressing long-standing environmental injustices.

Is that like the long-standing environmental and financial injustices Michael Skelly perpetrated upon Midwest landowners for a decade trying to build unneeded and unwanted transmission?  Oh, cry me a river of environmental injustice... then dam it up and generate electricity with it.  Make yourself useful.

Skelly tells the committee all about how transmission is paid for.  But he makes several critical errors.  On regionally-planned, cost-allocated projects with regulated cost-of-service rates:

While not a perfect policy tool, an Investment Tax Credit can make up for this deficiency in the planning process. The ITC would have the effect of lowering the denominator in the benefit to cost test. More lines would make it through the planning process, and we will end up with a lower carbon grid.

So, in other words, Skelly thinks that receiving a tax credit for 30% of the project's cost would lower the cost of the project at the regional planning level.  No, it would not.  The tax credit comes AFTER a project is put in service and is not guaranteed.  It cannot be fed into the RTO project cost estimate BEFORE is is planned.  Cart before horse.  The cost of the transmission project is the cost of the transmission project, sans tax credits.  Tax credits are completely separate things.  Utility ratemaking and taxes are complicated things.  Perhaps Skelly should ask someone who is an expert on these things before making crap up?  I was going to write a tutorial here, but then I figure why bother?  You don't care about the mechanics and I don't work for Michael Skelly.

Even worse is Skelly's take on merchant transmission rates:

The other type of transmission lines that get built are called “merchant” lines. These are typically built outside the conventional planning process, and their economics rely on generators paying the developers of merchant lines to deliver their power across long distances to get to market. An ITC will help reduce the cost of the transmission service, and therefore more lines would get built, and more renewable energy projects will follow.

Merchants assume all risk.  They also assume all costs.  The rate charged for a merchant project is negotiated between the customer and the transmission owner, not set by regulators.  A fair rate for merchant transmission service is set by market.  It's the highest cost a merchant can negotiate that is also attractive to the customer, a mutual agreement of the value of the project to the customer.  That value doesn't change because of tax credits.  Unless Skelly is proposing that rates are negotiated without the specter of tax credits, and then the value of the tax credit is subtracted from the agreed upon rate.  That's the only way the tax credit would reduce merchant transmission rates and pass through to ratepayers.

One last rate-geek thought here...  transmission is always, and I do mean always, paid for by the beneficiaries of the project.  If you don't benefit from transmission, you don't pay for it in your transmission bill.  The tax credit proposal completely upends this long-standing regulatory concept.  It replaces the beneficiary ratepayers with non-beneficiary taxpayers.  It's such a simple concept, even Michael Skelly might be able to understand it.  Just like we don't charge ratepayers in Alaska for a transmission line that serves Floridians, we don't charge taxpayers in Florida for a transmission line built in Alaska.

The transmission investment tax credit is a thoughtless, ignorant idea dreamed up by the greedy and stupid.  Its supporters keep digging a wider and wider hole.  There's no way out of this...  it simply doesn't work.

Maybe the most interesting thing about this is the fact that the "Macrogrid" disciples have hitched their star to Michael Skelly's Wagon of Failure.  That tells you all you need to know about the possibility of its success.

Gag me with a spoon!  A spoon?  Really?  I never understood the use of a spoon, but it makes me laugh nonetheless.  But who needs a spoon when you have Michael Skelly?
3 Comments

It depends upon what the meaning of the word 'is' is...

5/19/2021

1 Comment

 
Picture
Briefs have been filed in the Missouri Public Service Commission case alleging that Invenergy is building a materially different project than the one the PSC permitted.  If the "new" Grain Belt Express project that Invenergy announced last summer is being built, then Invenergy has effectively abandoned the project it had permitted.  No permit, no project.  Invenergy admits that the "new" project would require new approvals from the PSC, but says it alone will set the timetable for when it applies for new approvals.  Meanwhile, Invenergy wants to use its current permit to build a different project, and ask for approval after the fact.

What's the harm in this?  Two words -- eminent domain.  The currently permitted GBE was granted eminent domain authority.  The possibility of eminent domain can be used as a tool to coerce landowners to sign voluntary easements.  Without eminent domain, there is no coercion.  It's as simple as that.  However it remains to be seen if the threat of eminent domain is enough to acquire necessary easements.  How scared are landowners?  Do they believe they will get a better deal before condemnation?  Why should they?  The "fair market value" of their property will not change and will be debated  at any condemnation proceeding by a panel of their peers.  Would landowners believe that they can get more by signing a voluntary easement?  My experience with eminent domain had a different result.  Because I resisted and forced the condemning party to face a court hearing, my value suddenly went up.  It was worth a lot of money to them to avoid the court.  How much?  Six times the original offer, and double that offered before condemnation.  It's a straight up poker game... who's bluffing... and who is forced to show their hand?

Anyhow... back to the briefs.  Invenergy claimed the Missouri Landowners Alliance presented no evidence that it was building a different GBE.  The MLA brief pointed out the specific language Invenergy used in its press release and other documents  and examined the definitive nature of its statements.  It wasn't about maybe, or perhaps, it was a straight up declaration of a new plan.  For example,
Among other indications that Grain Belt now intends to materially change the original project are these additional, unequivocal statements from their press release:
● “Invenergy Transmission, the owner and developer of the Grain Belt Express transmission line project (‘Grain Belt’) today announced plans to increase local clean energy access and accelerate billions of dollars in economic investment in Kansas and Missouri.” The statement does not say Respondents “might” or “are considering” those plans. It says they are hereby announcing them.

● “Economic recovery and long-term economic competitiveness in Kansas and Missouri depend on new investment, more jobs, and tapping into low-cost, homegrown clean energy, which Grain Belt is moving full speed ahead to deliver, said Kris Zadlo, SVP [with Invenergy] .... Grain Belt is proud to increase our investment in Kansas and Missouri to rebuild the economy, deliver billions of dollars in energy cost savings, and meet growing renewable energy demand.” (emphasis added). No ambiguities there.

● “As the new owner of Grain Belt, Invenergy Transmission plans to increase the project’s delivery capacity to Kansas and Missouri to up to 2,500 megawatts of the line’s 4,000 megawatt capacity .... Previously, 500 megawatts of the transmission line’s capacity was slated for delivery to Missouri.” (emphasis added). Again, Respondents’ plan to increase delivery of power to these two states was expressed in unequivocal terms.

● ”Grain Belt will provide critical power infrastructure to the region benefiting residents for decades to come.”

● Governor Laura Kelly of Kansas is quoted in the press release as stating that “[t]his impressive project is the latest example of Kansas’ place as a wind energy leader in our region and beyond.”

● According to the Kansas Secretary of Commerce, “the unwavering commitment from Governor Kelly to further support renewable sources is paying off in many ways, including this tremendous step forward in the Grain Belt Express.” He is further quoted as saying that the revised project “will deliver a significant economic boost to our rural communities in particular. The news couldn’t come at a better time.”

Clearly, these statements from the two Kansas officials would have been authorized for inclusion in the press release only if those individuals had been convinced that Respondents actually plan to move forward with the changes announced in the press release. Had Respondents told them that the revised plans were merely under consideration, the reaction from the Kansas officials would no doubt have been different from what they are quoted as saying in the press release.

● A representative of Renew Missouri is quoted in the press release as saying that “the benefits of Grain Belt have only grown with billions of dollars of added savings ....” Again, this statement is nonsensical unless the speaker had been led to believe that Respondents are committed to moving forward with the changes announced in the press release.

● Perhaps the clearest commitment by Respondents to materially change the original project is the following statement from the press release: “With increased delivery to Missouri ... Grain Belt will double its overall economic investment in Missouri to $1 billion .... Grain Belt will now make available as much as half or more of the project’s total capacity for Missourians.”

The importance of this statement lies in how this additional $500 million is to be spent on the project. As Mr. Zadlo acknowledged, the additional $500 million announced in the press release represents the added cost of increasing the capacity of the Missouri converter station by five-fold: from the original 500 MW to 2,500 MW.35 One could hardly argue that this change is not material.
And Respondents did not state that they were merely “considering” or “contemplating” the additional $500 million investment, which was earmarked for quintupling the size of the Missouri converter station. Instead, the press release states unequivocally that the new plans for the project “would” double the investment in Missouri to $1 billion.
In addition to the press release, in a letter sent from Respondents to landowners just this past December, Respondents included the following statements, again made unequivocally and with no hint that the plans announced therein were anything short of a firm commitment:

● “As you may be aware from recent news, Grain Belt Express has announced a proposed plan to increase the project’s delivery capacity for Kansas and Missouri consumers.”
● “Under this plan, up to 2,500 megawatts of Grain Belt’s 4,000-megawatt capacity would be delivered to Kansas and Missouri consumers .... This requires expanding the already-approved converter station in northeast Missouri.” Again, Respondents do not equivocate. The new plan “requires” the expansion of the Missouri converter station. As it turns out, it requires a five-fold increase in the size of that converter station. ● “Grain Belt Express will be seeking regulatory approval for this plan.” Again, this is a firm commitment to proceed with the project as modified by the announced changes. If Respondents had not already committed to making these changes, there would be no need to state that they “will be seeking regulatory approval” for the changes. This statement also recognizes that the changes being made are “material” enough to require Commission approval under the terms of the CCN decision.

● The letter also states that Respondents will be seeking approval to begin construction of the line prior to obtaining approval for the Illinois segment of the project. This statement confirms the description of the new project in the press release as constituting a “phased construction plan.”

And as counsel for Respondents conceded, “if phasing was to occur so that the Missouri and Kansas portion of the line was built before the Illinois and Indiana portion of the line, then we would likely consider that a material change and be before the Commission.” So the newly announced phasing plan definitely constitutes a material change to the project.

● A series of emails shown at Exhibit 6 indicate that a woman named Kimberly, acting on behalf of Grain Belt, was soliciting comments from the Governor of Kansas to be used in the August 25 press release. In an email of August 6, she informed a number of Kansas officials that “The project is moving into its next phase and the company plans to announce this development.” (emphasis added). She did not tell the Kansas officials that the project might be moving into a new phase. Instead, she unequivocally assured them that the project “is” moving into the next phase.
● Finally, in
his response to Data Request No. 8, Mr. Zadlo simply answered “yes” to the following question:
Do Respondents presently plan to eventually seek regulatory approval from the Missouri Commission for the changes described in the press release attached as Exhibit 1 to the Complaint in this case, assuming no other significant changes are proposed to the project as originally approved?

This answer says, plainly and simply, that Respondents do in fact “presently” plan to seek Commission approval for the changes they announced in the press release. Mr. Zadlo did not say they might do so, or that they were considering that as an option. He said they will be seeking approval for those changes, which necessarily means they have already decided to make the revisions announced in the press release. It follows that Respondents have abandoned the project as approved in the CCN case.
The press release also mentions that Grain Belt will seek regulatory approvals “to the extent necessary” for the revised project. That of course is a given. Respondents have no choice but to seek regulatory approval for what amounts to a new transmission project. But that fact has no bearing on the question of whether they have already decided, as they have said, to move “full speed ahead” with the revised project. And again, the statement reinforces the fact that Respondents themselves consider the proposed changes to be “material” enough to require Commission approval.

In attempting to explain away their answer to Data Request No. 8, Respondents claim that the revisions announced in the press release are merely “contemplated changes.” But that explanation misses the point. As of today the specifics of the new plan may well be in the “contemplated” stage, with final details still to be determined.

However, that does not mean Respondents have not already committed to building the project in accordance with the announcements in the press release, as opposed to the project approved in the CCN case. In fact, they have as much as promised officials in Kansas that those changes will be forthcoming.
Perhaps at some point Respondents realized the potential consequences of their announced changes to the project. But taking them at their word up to that point, they have clearly stated they are already committed to making material changes to the project originally approved by the Commission. For Respondents to now dismiss the press release as nothing more than “a marketing exercise” simply demonstrates a complete lack of transparency and credibility.

The same holds true for their after-the-fact attempt to dismiss the press release as merely announcing the supposed benefits of the line and “an openness by Grain Belt to increase the converter station and dropoff in Missouri.” That document goes well beyond that characterization. In fact, the additional consumer benefits would materialize only if the chances announced in the press release were implemented.

The more credible statements from Respondents concerning this project are those made before the Complaint was filed here. Assuming Respondents were not deliberately misleading Missouri landowners, public officials, and the general public up to that point, those statements can only mean that they have already decided to materially alter the project approved by the Commission.
Based on the foregoing, the design and engineering of the project presently being pursued by Respondents is materially different from that approved in the CCN case.

... she unequivocally assured them that the project “is” moving into the next phase.

Is it, or is it not?  I guess that depends on what your definition of is is.  Famous words from a famous equivocator.

The language clearly stated that Grain Belt Express was being changed.  The claims about the vagueness of this new plan only came after GBE realized it had stepped in it.

Is the MO PSC going to allow Invenergy to dictate how it regulates by allowing the company to permit its new transmission project after the fact?  I think the PSC has a greater duty to the citizens of Missouri than it has to an out-of-state corporation who appears less than honest.

1 Comment

Calling all Hypocrites...

5/19/2021

2 Comments

 
When is hypocrisy not hypocrisy?  When it enables corporate profit and political goals!

The divide between using eminent domain for gas and oil pipelines and using it for renewable energy transmission lines is becoming an issue.  For years, environmental groups have raged against eminent domain to acquire right of way for fossil fuel projects.  However, they are being advised to think differently when it comes to electric transmission "for renewables."  For some reason, this use of eminent domain is okay.  Can we just admit that it never was about eminent domain in the first place?  It's about politics, and these politics are riddled with hypocrisy.

This article just goes too far.  Written by a law firm scrounging for clients who want to re-write eminent domain law, it proposes to change the definition of "public use."  Cue the Supreme Courts...

The 5th Amendment of the Constitution reads:
No person shall be held to answer for a capital, or otherwise infamous crime, unless on a presentment or indictment of a Grand Jury, except in cases arising in the land or naval forces, or in the Militia, when in actual service in time of War or public danger; nor shall any person be subject for the same offence to be twice put in jeopardy of life or limb; nor shall be compelled in any criminal case to be a witness against himself, nor be deprived of life, liberty, or property, without due process of law; nor shall private property be taken for public use, without just compensation.
Each state has its own version of this.  What is "public use?"  Your personal definition of it may differ, but we can all probably agree what it is not... it's not the confiscation of private property by others seeking to make a profit using it for their own purposes.  I cannot force my neighbor to sell me the use of his backyard so that I can plant a vegetable garden that will enable me to open a booth at the local farmer's market and make a profit selling produce.  So why should we allow a for-profit corporation to acquire my property to build a transmission line from which they will realize profit?  We did this in the past because the transmission line enabled others to have electricity.  The public was getting a benefit from having electricity.  We use it still when it enables the public to realize a benefit.  When a transmission line is needed for reliability, for instance.  However, we need to draw the line at using eminent domain to build transmission that may lower prices for a small segment of the population at the expense of another.  We need to draw the line at using eminent domain to build transmission for political reasons.  We need to draw the line at using eminent domain to build unneeded transmission designed for corporate profit.

This law firm proposes:
Soon enough, eminent domain policies will have to evolve to align with renewable energy policies in order for a complete overhaul of the grid system to be attainable. State and federal lawmakers will eventually have to address the issue by having to revise the definition of “public use” to account for transmission lines transporting renewable electricity.
We're going to have to re-define "public use" to suit your political goals and corporate profit? 

NO!

The last time the definition of "public use" arose was in the context of a high profile Supreme Court case, Kelo v. City of New London.  In that case, the Court narrowly decided that economic development (increasing the tax base) was a "public use."  The backlash was enormous.  Many states enacted new laws to thwart this ridiculous decision.   Any corporation can increase the tax base by turning residential property into commercial property, but are the tax benefits to the community a "public use?"

The same goes for taking private property to enable new generation choices.  Everyone who wants electricity has electricity.  Where's the public need?  It's nothing but politics, folks.

And here's something to consider that you may find surprising.  The liberal justices were the ones who supported eminent domain for economic development purposes.  Conservative justices dissented.  How might a new battle be decided?  And just how long might that take?  It would be much, much longer than renewable energy companies are willing to wait.

Can they quietly change the definition of "public use" written in the Constitution and in individual state law?  And if they did, how could they still use it to oppose eminent domain for fossil fuel use, but enable electric transmission "for renewables"?  The hypocrisy here is so thick you could cut it with a knife.
2 Comments

Grain Belt Express Seeks New $600 Million Taxpayer Handout

5/14/2021

4 Comments

 
Picture
At a recent ACORE webinar trying to sell a new transmission investment tax credit to a friendly, money-spewing administration, GBE owner Invenergy stated that it NEEDED the proposed tax credit to "enable" the Grain Belt Express.
Financing large-scale, interregional transmission can be particularly challenging for merchant developers, said Shashank Sane, senior vice president and head of transmission at Invenergy.  “The beneficiaries of these projects can be diverse, and so in order to monetize the value of those lines, we have to find the stakeholder who is willing to pay for a certain benefit and create those links,” Sane said. “That’s really not the right model.”

For example, he said, Invenergy’s Grain Belt Express project now under development is aimed at bringing wind power from Kansas across Missouri, Illinois and ultimately to Indiana, providing a connection to MISO and PJM.

“The ITC is the key tool that will enable [the project] because it addresses the cost allocation problem and paying for those multiple benefits a single beneficiary is not willing to pay for,” Sane said.

The ITC is a new tax credit that will allow the owner of new transmission to take a credit on their taxes of 30% of the project's cost.  If Grain Belt Express is supposed to cost $2B (latest estimate I could find), then it would receive $600M (that's 600 MILLION!) of federal tax credits paid for by U.S. taxpayers.  What's more, the ITC is proposed to be refundable, if the transmission owner does not pay enough taxes to offset the credit it earns.  If Invenergy only owes $50M of federal taxes in the year it puts GBE in service, under the new proposal it could pay no taxes at all that year and receive a $550M tax refund from the federal government.

As a supposed merchant transmission project, GBE is supposed to pay for its own project and collect all its costs from voluntary customers who negotiate rates for service on GBE.  GBE is supposed to shoulder all risk of its project.  If GBE fails, there are no captive ratepayers to cover its costs.  However, GBE is now proposing, indeed saying it NEEDS, a new handout from American taxpayers in the neighborhood of $600M in order to build its project.

Just yesterday, GBE "needed" eminent domain to take land from Missouri farmers cheaper than it could acquire the same land in the free market.  Keeping land costs low keeps Invenergy's costs low, and lower costs translate to higher profits.  Today, GBE "needs" a $600M taxpayer handout to further increase its profits.  GBE just keeps "needing," and taking, more and more from people.

Isn't it time to say enough?

Stop enabling Invenergy's profits!  Start supporting the citizens of Missouri who elected you.
4 Comments

Transmission Tax Credits Interfere With Negotiated Rate Authority

5/14/2021

1 Comment

 
Picture
Well, someone's been doing a little reading, haven't they?  Stick around, fellas, and maybe you'll learn enough about transmission rates to finally admit that your stupid ideas about building a useless and super expensive "macrogrid" just don't work.

The silly schemers behind the "22 shovel ready transmission projects" have finally recognized that there are two distinctly different types of transmission, traditional and merchant.  Can we get a hallelujah, boys and girls?  I'm guessing that they got a little worried that someone might recognize their lies, and that regulators certainly aren't going to fall for them.  So, they issued a new "report."  There's more "reports" in there than a 7th grade Social Studies class!  However, their "we meant to do that" ass-cover report does nothing but make excuses for their ignorance.  Do they really think regulators are going to buy this nonsense?

ACORE says that investment tax credits for transmission can be used by either type of transmission project.

Traditional:  The tax credits lower the cost of the transmission project and lower the amount captive ratepayers must pay for cost-of-service rates. *

Merchant:  The tax credits lower the amount of money the transmission owner needs to recover through rates, therefore the transmission owner can "offer" lower rates to voluntary customers it negotiates with, making the project more likely to find customers and be built.

Say what?  This is the biggest bunch of misleading propaganda I've read in a while.  Does ACORE really think regulators are going to buy that?
The tax credit would stimulate both of the main types of transmission projects—regulated rate- based projects and “merchant” lines whose costs are recovered through negotiated or market- based capacity reservations. In the case of regulated lines, a utility or Regional Transmission Organization (RTO) would allocate the costs through a state or federal (FERC) regulatory process across a set of wholesale or retail customers. In that case, the tax credit would reduce the costs paid by those customers and make the cost allocation and approval process easier so more projects can move forward. In the latter case of merchant projects, the transmission capacity reservation costs that developers need to recover from wholesale customers would be reduced by the tax credit. This would allow the transmission developer to offer a more attractive price to customers, increasing the odds of success.
A merchant project will have a set amount of capacity to offer through negotiation with willing buyers.  The project offers that capacity, and then negotiates the highest price it can get in the open market with voluntary customers.  Lowering the project's costs does not affect the market, or the negotiating power of the project.  The transmission owner will still negotiate individually with a voluntary pool of customers to contract the highest rates it can negotiate.  Paying less for the project because of a tax credit only increases the merchant transmission project's profit, it doesn't lower its rates.  Whoever came up with that idiotic idea needs to belly up to the bar and think of something else because this dog don't hunt.

And while you're scheming up your new scheme, don't lose sight of the fact that merchant transmission accepts all risk.  Any subsidization of merchant projects invalidates their merchant status and ability to fairly negotiate rates.  You can't give government or other handouts to merchant transmission and still call it merchant.  If you want to do that, we're going to have to regulate merchant transmission rates.  So, which is is going to be?

*The schemers have turned traditional transmission rates into Robin Hood Rates by replacing the current system of beneficiary pays with a new system where taxpayers fund the electric system based on income.  This upends the way utilities are paid for, and wrecks the regulatory system.
By reducing the cost of electricity, a transmission tax credit can significantly reduce the burden of electricity costs on lower-income Americans. Electricity costs are regressive in that they hit the lowest income Americans disproportionately hard. Electricity accounts for 3.7 percent of total household expenditures for lower-income Americans, versus only 1.4 percent for the highest-income Americans. This is because electricity is a necessity for many aspects of modern life, so the poorest Americans can only reduce their electricity consumption to a limited extent. Unlike other products, it is not possible to use a lower-cost substitute, as a kiloWatt-hour used by a lower-income family is the same and costs the same as one used by a higher-income family. In addition, lower-income Americans have less ability to invest in cost-saving energy efficiency upgrades. As a result, those in the highest 10 percent income bracket only spend twice as much on electricity as those in the lowest 10 percent bracket; for other goods, those in the top 10 percent spend nearly six times as much.In contrast, the federal taxes used to offset the cost of a transmission tax credit are much more progressive, with the top 10 percent of earners paying 60 percent of total federal taxes, and the bottom 30 percent paying negative tax rates due to policies like the earned income tax credit. As a result, a transmission tax credit that moves costs from utility bills to tax bills is very progressive.

It's also very illegal!!!  A public utility with an obligation to serve must charge the same rate to all similarly situated customers.  This means by customer class (residential, business, industrial) and not by individual customer income.  A public utility is prohibited from charging different rates to different customers based on their income.  A rich person pays the same for a kilowatt hour as a poor one because both use the same system at the same rate, and the sale of kilowatt hours is for the purpose of building and maintaining the system that produces and delivers that kilowatt hour.  Regulated utility rates are not about how much the consumer can or wants to pay, but about the consumer's share of how much the system costs to build and operate.

You cannot change regulated electric rates into some Robin Hood system based on income, race, or political affiliation by shifting the cost responsibility for electricity from ratepayers to taxpayers.  I think this idea might just be laughed out of regulatory venues.  Again, belly up to the bar... more ideas, more reports, more spinning your wheels doing dumb things.

The "macrogrid" just isn't going to happen.
1 Comment

Reliability Reality

5/13/2021

0 Comments

 
Picture
Seems like the idea of "reliability" is a big thing these days.  When applied to electricity, what does it mean?  It means that when you flip the switch on the wall at your home, the lights go on.  And that may be the extent of what the general public knows about the "reliability" of their electricity.   These folks are gullible patsies for  greedy, electric industry propaganda.  The best propaganda disseminates a self-serving idea that plays on public fear.

How many stories have you read lately about things that fail without warning:  bridges... pipelines... electricity.  Bingo!  You're being fed a bunch of lies about "the electric grid" and its "reliability."
Developers of the Grain Belt Express say the massive transmission line remains on track to open up by 2025, connecting wind power in western Kansas with voracious demand in the East.
The 800-mile project promises to add more reliability to the electric grid — all the more enticing since rolling blackouts in February left millions of Americans without power. While the $2 billion overhead transmission line aims at exporting wind energy from Kansas, it will also be capable of moving electricity both directions, which could have helped mitigate the electricity crisis that hit the United States earlier this year.

Zadlo understands the opposition to the project. But he said the benefits for people here and across the United States are immense. Just like railroad cars transport coal from mines to refineries, the Grain Belt will move a much-needed resource to customers, while also strengthening the electrical grid.

"Reliability benefits all people, right? Increasing the reliability of the grid is a good societal impact," he said. "Whether you're in the city or in rural areas, you will benefit from the increased reliability that Grain Belt will bring."

Well, gosh, you might think that we NEED GBE to make sure the lights go on when we flip the switch.  However, this is nothing but propaganda designed to make you think we're just sitting around watching the grid rot and waiting for some non-utility corporation to build enormously profitable new transmission that serves their generation portfolio.  That would just be stupid!

Reliability is maintained through transmission planning by several independent regional transmission system operators.  Reliability planning is their main purpose!    In addition, utilities must meet rigorous reliability standards set and enforced by NERC, a federal reliability enforcement organization.  We don't leave reliability to chance!!!  Therefore when some vapid media piece tells you that our grid is "outdated," "creaky," "aged," "unreliable" you can be assured that none of that is true!  Our grid is kept reliable through strict regulation, planning and operation.  These are the organizations that deserve all the credit for keeping your lights on.

The regional transmission system operators have a robust transmission planning process that looks years into the future to ensure that the grid remains reliable in any scenario.  If we need new transmission for reliability purposes, then the buck stops there.  All transmission that we actually NEED for reliability is planned by the grid operator, assigned to a regulated utility, and ordered to be built, with the costs of the project allocated across the electric ratepayers who receive the benefit.  It works!

However, GBE is not one of these needed reliability projects.  No grid operator has planned, ordered, or allocated the costs of GBE to ratepayers.  Instead, GBE is an outside actor that is attempting to build transmission for its own purposes.  It is building transmission because it wants to make money.  It is not building transmission to be a public service.  GBE owner Invenergy has no obligation to serve electric consumers and it doesn't give a rat's patootie whether or not your lights come on when you flip the switch.  Invenergy simply wants to see lots of money in its bank account.

So when merchant transmission projects like GBE tell you that they will provide some necessary "reliability," it's nothing but bogus propaganda.  Any "reliability" provided by GBE is reliability we don't need.  If we needed it to keep the lights on, GBE would be a regional system operator planned, ordered and cost allocated project.  But it's not.  It's a private corporate foray into transmission whose only obligation is to its own balance sheet.

The reality of reliability is that we have an extensive, federally sanctioned system that ensures reliability.

Grain Belt Express is not part of that system.  We don't "need" it to make sure the lights go on when we flip the switch on the wall.
0 Comments
<<Previous

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.