StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Learning from the Cascading Power Failures that Brought Down the Power Grid in India

8/6/2012

1 Comment

 
by Deb Severson

On Tuesday July 31, 2012, India’s interconnected power grids failed, leaving half the population without electricity.

Cascading failures occur in systems of interconnected parts. They usually begin when one part of the system fails. Nearby system parts must then compensate for the failed component, which can overload that part to trigger a vicious cycle as successive parts fail.

When Federal Energy Regulatory Commission (FERC) chairman Jon Wellinghoff was asked if power problems in the Northeast could spread all the way to California, he told ABC News, “It’s very, very unlikely that ultimately would happen.” Part of why the risk is low, the ABC story conveyed, is due to our nation’s grid being divided in the middle.

Unfortunately, this division still leaves hundreds of millions at risk for cascading failures, and increased investment in transmission is in NOT the answer.

A comprehensive, three-year DoD and Federal Emergency Management Agency study — Brittle Power: Energy Strategy for National Security — concluded that relying on massive, complex, and interconnected infrastructures that need to transmit and deliver power from centralized generation create unavoidable (and costly) vulnerabilities.

Cascading failures in “brittle” interconnected electrical systems can be induced by severe weather, human error, sabotage, or even the interference of small animals. Conversely, resilient infrastructure systems are less likely to collapse in the face of natural or manmade disruptions and will limit damage when disruptions occur.

A 2007 US Department of Energy (DOE) study, The Potential Benefits of Distributed Generation and Rate-Related Issues that May Impede Their Expansion, provides compelling evidence of how a distributed network of smaller sources was able to adjust to problems without causing major consequences. A decentralized system also reduced the magnitude and duration of failures.

The DoD study on “brittle power” further concluded that centralized energy facilities create tempting targets for terrorists because the terrorists would need to attack only a few, poorly guarded facilities to cause large, catastrophic power outages. In a complementary study, Energy Security in a Dangerous World, the International Energy Agency reaches the same conclusion.

Examples from nearly every area of critical infrastructure defined by the Department of Homeland Security verify distributed generation (DG) to be a viable means for reducing vulnerability to terrorism and improving the resilience of electrical infrastructure. This is based on actual cases where DG continued to provide power to critical facilities during times of large-scale power disruptions and outages, and is documented in the 2007 DOE study.

Richard Clarke, a former national security adviser and ABC News consultant also conveyed, during the ABC Nightly News coverage of Black Tuesday, that today’s biggest grid threat is cyber-attack. “The U.S. power grid is extremely vulnerable to cyber-attack,” Clarke said. “The government is aware of that. Recently the government held a White House level cyber exercise in which the scenario was a cyber-terrorist attack that took down the power grid.”

A July 17, 2012 webinar, New Approaches to Grid Security, featured three of the electric industry’s most knowledgeable and influential leaders in grid reliability -- Terry Jarrett, MPSC regulator and chair of NARUC committee on critical infrastructure, Terry Boston, president and CEO of PJM Interconnections, and Gerry Cauley, president and CEO of North American Electric Reliability Corp.

Each of these experts stressed the importance of resilience – the ability of the electrical infrastructure to quickly respond to cyber, terrorist and weather induced attack. Mr. Cauley also conveyed how the interconnected grid throughout the US and Canada created challenges to protecting the grid from cyber-attack due to issues related to information sharing and analysis.

Expert testimony from Dr. Benjamin Sovacool regarding a 500 kV transmission line in Virginia demonstrated how long-distance transmission reduces the stability of the electric grid. Dr. Sovacool concluded, “The proposed project should be rejected on grounds that it fails to provide substantial reliability and security as defined by (the utility) Dominion itself. Instead, the proposed line increases the vulnerability of Virginia and the National Capital Area to critical national security threats.”

Dominion -- one of the nation's largest producers and transporters of energy, which serves electrical needs for customers in Virginia, West Virginia, Ohio and North Carolina -- received permission to construct this project connecting Meadow Brook to Loudoun. The $243 million, 65-mile long overhead transmission line was placed in service in mid-2011. On June 29 2012, more than a million customers in DC, Virginia and Maryland suffered mass power outoutages due to “derecho” storms. The area’s electrical grid was slow to recover.

The August 14, 2003 rolling blackout of the East Coast was, at the time, the second most wide-spread blackout in history, affecting an estimated 45 million people in eight U.S. states and 10 million people n Ontario. In this disaster, a power surge affected the transmission grid, resulting in a cascading failure. The tools in place to analyze the “what ifs” didn’t do their job and the appropriate people didn’t understand the issue was theirs until their own lights went off. By then, an uncontrollable cascading failure was under way and it was too late for human intervention to save the grid.

In 2005, Congress put in place financial incentives to improve existing transmission to prevent future blackouts. Since then, most of the funding has been diverted to new transmission and, in 2011, the US experienced another significant black-out.

In reviewing the cause of the September 28, 2011 blackout, which affected up to 5 million people in California, Arizona and Mexico, NERC and FERC found “common underlying causes” to the 2003 East Coast black-out. The power loss should have been limited to the Yuma, Arizona, area but, according to the power company, Arizona Public Service, “…an employee was just switching out a piece of equipment that was problematic."

This clearly indicates that transmission incentives have not produced a corresponding increase in reliability that would prevent future blackouts, as Congress intended. Despite this, building more and more interconnected transmission is rampant. $170 billion in new transmission is planned nationally between now and 2020. In Wisconsin alone eight new high voltage lines planned that will greatly increase inter-connection from Maine to the Dakotas.

CapX2020, a controversial and contested high voltage transmission line, is planned to cross the Mississippi River at Alma, Wisconsin. Despite testimony of inherent grid instability, the Wisconsin Public Service Commission (PSC) approved CapX2020 on May 30, 2012.

The next interconnected segment of this line, known as Badger Coulee, would connect to Madison.

This type of transmission expansion is planned all over the country, making further interconnection of the nation’s grid imminent and immense.

The utilities behind CapX2020 and the Wisconsin PSC contend the line is needed for “regional reliability.” Those leading the court challenge against the line believe this is a manipulation of the term as it is economically driven and defined by the ability to more reliably move electricity around to sell to other markets.

It is time to for utilities to embrace another approach and to more fully acknowledge inherent issues in monitoring and controlling an interconnected grid. Dr. Sovacool warned in his 2007 testimony, “Long distance transmission is not reliable. Given the complexity of the modern electrical system, and what we know about the role reactive power has played in recent outages, relying on longer transmission lines to wheel greater amounts of real power is perhaps the worst strategy for ensuring system reliability. Large and long transmission lines lose reactive power the larger and longer they become, requiring the system to compensate in ways that increase the likelihood of systems collapse.”

Dr. Sovacool also shared how catastrophic failures are most often the result of human error, inadequate diagnostics, and/or voltage instability due to insufficient reactive power — the power that keeps voltage and current in phase.

In electric transmission, if a fault occurs and takes a line out, the change in current flow is compensated by other transmission lines. If they lack the capacity to carry the excess current, overload protection in those lines will also trip, causing a cascading failure as the excess current is switched onto neighboring circuits running at or near their capacity.

The role of a system operator is to monitor power supply and demand to keep them balanced and within safe operational limits. If a system failure occurs, operators must get power from generators or other regions or reduce their load to bring the system into balance and, hopefully, avoid a cascading system failure. Computer systems, with backups and alarms, are used to monitor the system. If the computer systems fail, system operators monitor the grid manually. Local operators are coordinated by regional centers, but the operating principle is the same for the larger network. Applying this and lessons learned in the 2003 and 2011 US blackouts and to Black Tuesday in India -- the largest in human history – is highly relevant and insightful.

Human and equipment error will continue to happen, and interconnected systems are vulnerable to cascading failures. It simply is what it is. Fortunately many of India’s major corporations and industrial groups were spared much of the blackout disruption because they generate their own power.

Perhaps, in the US, we are not encouraging investment in the right kind of improvements to enable similar avoidance of distress. Perhaps it is time to invest in an efficient, diverse, dispersed electricity system, where major failures—whether by accident or malice—become improbable by design rather than inevitable by design. The number of citizens, municipalities, states and associations asking that viable, cost-effective and sustainable alternatives to high voltage transmission be evaluated is growing. Unfortunately, so is the number of transmission lines being built and planned.

Due to this pressure, FERC has agreed to evaluate whether its own incentives are leading to an over-application for transmission and subsequent profits. Citizens are also suggesting that a conflict-of interest may exist in the planning groups of the Midwest regional grid operator (MISO) by having for-profit transmission builders at the helm of their Planning Advisory Committee and Planning Subcommittee. The dauntingly high operating-margins provide further insight into why some feel it is
greed, not need, that is driving this push for transmission.

In December 2011, Financial News Network reported that ITC Holdings, the largest for-profit transmission only company, has the highest operating margins in the electric industry (51.7%). ATC, which wants to build the high voltage line connecting La Crosse to Madison, has an even higher margin of 54.9% when dividing 2010 operating income by revenue. In Wisconsin, a legal battle has ensued between Xcel and ATC regarding ownership of the Badger Coulee line and the subsequent profits.

The public also is not accepting ATC’s claim that looking into non-transmission alternatives is “beyond the scope of the (transmission) project.” Instead, ratepayers are asking the Wisconsin PSC for cost/benefit analysis of feasible alternatives, including how they impact grid reliability and the sustainability of our natural resources. They are educated on job creation and energy savings benefits of energy efficiency over transmission, as well as the benefits of home grown energy and a decentralized grid.

The commitment and tenacity to address these issues is evidenced by groups including Citizens Energy Task Force (CETF)/No CapX2020, Piedmont Environmental Council and Stop PATH WV, which are willing to lead the charge all the way to the courts.

Incidents such as the black-out in India, terrorist attacks on September 11, 2001, the Northeast Blackout of August 2003 and Hurricane Katrina are wake up calls. They remind us how dependent we are on electricity and how fragile a brittle grid can be.

We’re at a fork in the road.

Before we invest hundreds of billions of dollars in interconnected transmission, we must heed the experts and activists who are working to replace the outdated paradigms of infrastructure protection and infrastructure centralization with infrastructure resilience.

The time to change our course is now, before what happened in India threatens half the American public.

1 Comment

Columbus

8/5/2012

0 Comments

 
Are you getting impatient?  Wondering why there's been a lack if new posts here latey?  Sorry... busy!

Now if you're wondering what I've been busy doing... you'll see shortly.  

Today, Patience and I were busy sampling the ice cream here.  We decided on the dark chocolate and the black coffee today.  Tomorrow, we may be more adventuresome.

We're also really looking forward to having a conversation with AEP tomorrow. 

Columbus is a much nicer place than Charleston, and has better ice cream (and the Margaritas aren't bad either).  Stay tuned...
0 Comments

A Quarter Billion Dollars Wasted - Thanks for Nothing, PATH!

7/30/2012

4 Comments

 
You regular readers know how much I love numbers.  They're black and white and they never lie to you.  I needed a certain number today for insertion in something I was writing.  I needed the total amount PATH has collected from millions of ratepayers in PJM's multi-state region (all or parts of Pennsylvania, New Jersey, Maryland, Virginia, West Virginia, North Carolina, Tennessee, Kentucky, Delaware, Ohio, Indiana, Illinois, Michigan and the District of Columbia) through its annual transmission revenue requirements from the inception of its formula rate in 2008 through the end of this year, 2012.

I'm not sure why I didn't have this number already at hand, it's just never had a use before, I suppose.  Are you ready to know how much of your money has been wasted over the past 5 years on a transmission project that was never constructed, was never permitted, and will never provide the smallest benefit to the electric consumers who financed it?

Ninety-five million dollars.  That's right $95M!  PATH has poured $95M of your hard-earned money down a rathole attempting to promote, site and permit a project that was never needed in the first place.  What an incredible waste!  How many other uses for $95M can you think of that would have provided some benefit to society?  Instead, the only benefits have been the financial ones that ended up on corporate profit statements.

Separate and apart from that $95M of your money that PATH has already collected and spent, they have also invested over $130M of their money in the project's rate base.  You will continue to pay them 12.4% annual return on their $130M investment until the project is officially abandoned.  When abandonment finally happens, the $130M will be fought over and eventually an amount will be set for recovery from ratepayers over a set number of years.

If we add the $130M investment PATH is going to want back to the $95M they have already collected and spent, we've got a total of $225M, nearly a quarter of a billion dollars of our money, that has been wasted by American Electric Power and FirstEnergy on a get-rich quick scheme to build unneeded transmission infrastructure.

Thanks for nothing, fellas!
4 Comments

Appalachian Power and the WV PSC's 2012 Rate Increase That Wasn't

7/29/2012

3 Comments

 
Appalachian Power and the West Virginia Public Service Commission are attempting to pull a fast one on the utility's customers in the state.

Last week's news headlines trumpeted, "PSC issues order to keep AEP electric rates from rising,"  and the PSC issued a press release titled, "PSC Maintains Current Level for Electric Rates."  Nothing could be further from the truth!  However, APCo and the PSC think you ratepayers are dumb and easily fooled by their semantics games.  A review of the PSC's order in the case reveals that the claims of "no rate increases" are nothing but smoke and mirrors, and here's why:

1.    The "current rates" that are being "maintained" are the product of a series of rate increases over the past four years that were supposed to pay down a huge unrecovered fuel cost balance from 2008 and 2009.  These higher rates were supposed to be temporary increases granted to pay off a debt to the company.  However, APCo has continued to overspend, and at the end of the temporary rate increase period no substantial amount of old debt has been retired, or paid, by these increased rates!  Therefore, the 2008 and 2009 balance owed to APCo by ratepayers remains, and now has $25M in carrying costs (interest) tacked on to it!  Here's how the PSC describes it in their order: 

"Over the past several years, the APCo/WPCo customer rates have increased significantly primarily because of the increased costs to acquire fuel (coal) for power
generation and expenditures to meet more stringent environmental regulations. The 2012 ENEC filing was intended to be the last year of a four-year phase-in rate plan approved in Appalachian Power Co. & Wheeling Power Co., Case No. 09-0177-E-GI (Order dated September 30,2009) (2009 ENEC).

In the 2009 ENEC proceeding, the Companies filed for the largest rate increase ever requested by a utility in the State. That filing related to the energy cost increases
experienced in 2008 and 2009. In the 2009 ENEC, the Commission authorized a four-year phase-in plan of a $366.7 million rate increase, with the first ENEC increase of approximately $106.6 million, or a 10.5 percent increase in overall rates, and an $18.1 million Construction and Post-construction surcharge increase."


2.    APCo didn't ask for, and the Commission didn't approve, an additional ENEC rate increase because the company, the PSC, and the legislature are trying to avoid your scrutiny and anger over another huge rate increase.  These entities passed legislation this year that allows them to simply hide the huge rate increase necessary to pull their feet out of the fire.  They are hiding the gigantic rate increase by mortgaging it in your name over a 10 year period and tossing words and ideas around that they are hoping will confuse you.  "Securitization," or the "selling of bonds," is nothing more than the company taking out a mortgage and sticking you with the payments and interest.  APCo is tired of carrying this huge unrecovered balance.  If they "sell bonds" it means they take the cash from the mortgage loan, and the obligation to repay belongs to ratepayers.  This is a rate increase you will be paying over the next ten years, with interest.  APCo has tossed all its debt, both historical and current, into the amount of the rate mortgage that they will be applying for soon.  There is no rate increase simply because the actual rate increase will be a separate "securitization" case that is expected to be filed in the next couple of weeks.  The PSC took no action to "keep rates from rising," they simply deferred the huge rate increase to another case.  Parent company AEP stated in a recent presentation to their investors that the amount of the West Virginia rate increase will be $400M.

3.    Let's talk about utility "deferrals."  When the utility spends money that they are unable to recover through current rates, they "defer" it by creating a regulatory asset in their accounting system.  This debt belongs to the ratepayers, and at some point, the utility will ask the PSC for permission to recover it from you through a future rate increase.  APCo plans to clean up all outstanding deferrals on its books through "securitization" and transfer all that debt to ratepayers.  APCo also plans to put you right back into debt by "deferring" $56M of recent storm restoration costs.  You will pay for this "deferral" later.  APCo "deferred" its gigantic fuel cost increase from 2008 & 2009, and the cost of certain deals for lower rates it made with certain industrial customers in prior rate cases (such as Century Aluminum).  When APCo negotiates a lower rate for certain big electric users, they are not absorbing the discount.  They simply book the difference between their cost and the lower rate that these customers pay as a "deferral."  Now APCo wants you to pay for the discount other customers received in their bills in prior years.

"Deferrals" and "securitization" and the "selling of bonds" are not actions that cost APCo money.  They are debts that are incurred in your name by the utility, and they will all come due.  It's time for APCo customers to pay the piper, while the PSC and your state legislators hide behind big words and accounting mumbo-jumbo and try to trick you into believing that there will be no rate increases.
3 Comments

What AEP Doesn't Want You to Know

7/24/2012

2 Comments

 
Whoever said corporations are faceless?  Investor owned utilities have two faces:  one face for the consumers who fund them, and a different face for their investors, who reap the financial benefits provided by consumers.

Here's the face AEP wants you consumers to see -- Pablo the AEP Answer Man.  He's a regular guy, just like you, right?  Were you all feeling as "strained" as poor Pablo, bravely "starring" in another one of his ridiculous youtube videos, after a grueling 18-hour day attempting to cover AEP's derriere over their poor post-storm performance?

Late one night, recording a video update on the restoration effort, he recalled feeling the accumulated strain of days without much sleep.“I couldn’t get complete sentences out that made any sense,” he said.

AEP is getting a bit carried away with the plain folks propaganda.  We thought it would be funny to see the corporate bigwigs hurling dodge balls at each other in TV commercials when we suggested it.  The ugly tie collection and experiments with different outfits and backdrops were amusing for a few minutes, but folks are over it.  AEP just doesn't know when to quit, however.

The other face AEP presents to its investors can be seen in this transcript of AEP's 2Q 2012 earnings call held on July 20.  There's so much bragging about how they're sticking it to consumers in order to make huge profits, I'm just going to paraphrase the highlights.  Be sure to read the entire transcript yourself for even more filthy rich one percent goodness.

1.    Quarterly earnings were .75 per share.  Year to date earnings were $1.55 per share.  Earnings were $370M for the quarter, and $759M year-to-date.  It was a "pretty good" quarter for AEP.

2.      Ohio has been a problem for AEP due to customer switching, low demand and their issues with rate cases.

3.    "Investment" in their regulated (monopoly) subsidiaries and transmission will provide 4 - 6% growth in earnings.

4.    Poor, poor, AEP CEO Nick Akins has had two "storms" to deal with since he became CEO 8 months ago.  One "storm" was created by Mother Nature on June 29.  The other "storm" was a regulatory one created by consumers in Ohio.

5.     The June storm cost AEP $230 million.  They will defer much of the cost for future recovery from consumers.  As soon as the consumer anger begins to die back and you all take your eye off the ball, AEP's planning to stick it to you.  $70M will be recovered through future rate cases.  $130M will be deferred for future recovery from consumers.  AEP has $4M budgeted for storm costs this quarter, so that only leaves $26M of cost coming out of AEP's shareholders pockets for the quarter.  However, AEP's shareholders have been collecting profits from unspent budgeted O&M in other quarters, so they're still way, way ahead.

6.    AEP was glad the June storm came along in order to take focus off the hot water they were in at PUCO.  This is a direct quote from Akins:  "...in an odd and perhaps, morbid way, it gave the management team a brief reprieve from the challenges of the other storm that occurred -- the regulated storm we call Ohio."

7.    AEP is looking forward to the PUCO allowing the company to recover deferred capacity costs from consumers when their rate case is decided in August.  PUCO declared both AEP and FirstEnergy winners in the dodgeball game by allowing FirstEnergy to pay a lower cost while also allowing AEP to charge a higher cost.  How can this be so?  Because the consumers are going to pick up the difference between what AEP is allowed to charge and what FirstEnergy has to pay.  Consumers are the big losers in Ohio, once again.

8.    AEP also wants PUCO to approve their rate stability rider "to ensure AEP's financial integrity," their distribution investment rider and allow recovery of deferred fuel costs and other regulatory assets totaling $800M.  Of course, these are all additional costs that consumers will end up paying, and paying, and paying.

9.    AEP needs a fistful of your cash to complete their corporate separation and start their competitive generation company.  In order to do this, AEP is going to "sell" a bunch of their Ohio generation assets into West Virginia and Kentucky's regulated environments, where consumers in those states will end up paying for them so that AEP doesn't have that financial liability mucking up their competitive company profit margins.

10.    AEP's new transmission projects will "really provide the earnings growth for the future."  Transmission will provide the "critical mass" for future earnings growth and AEP has "plenty of projects" that can take the place of those that don't work out.  So, AEP will just keep proposing and building new transmission projects as a way to make money, not because the transmission is truly needed.  Consumers will pay for all this unneeded new transmission.

11.     AEP is looking forward to getting their new pulverized coal plant on line in Indiana so they can start collecting the cost of it from ratepayers.

12.    AEP is concentrating on cutting operations & maintenance spending in order to make up for customer switching in Ohio and other areas where their earnings are lagging.  AEP added .13 per share this quarter by reducing O&M.  How did their skimping on maintenance work out for you on June 29?

13.    AEP is looking forward to $400M in "securitization opportunities" in West Virginia.  That means that they are anxiously awaiting all that beautiful cash they will get by mortgaging all their old coal debt in the name of West Virginia consumers, who will end up paying for AEP's past coal-buying mistakes for the next ten years.

14.    The profit AEP is making at their regulated companies in other states is propping up their big losses in Ohio.  Consumers in other states are making up for any savings Ohio consumers receive.  O&M cuts and transmission are really the only things propping up AEP right now.

15.    Akins had an epiphany moment where he toyed with the idea that the sustained decline in residential sales could possibly be due to increased energy efficiency.  Ya think, Nick, old boy?  Nick gets the Captain Obvious Award!

So, while AEP cries "poor me" to the consumers with one face, their other face is laughing all the way to the bank.  AEP thinks you're never going to know what they do behind your back.  Oops.
2 Comments

West Virginia Can't Afford Electric Reliability

7/24/2012

2 Comments

 
Check out the West Virginia PSC's reliability "fan dance" on The Powerline.  Bill does an excellent analysis of the PSC's post-storm posturing and how none of it is likely to result in any real increase in reliability.  If you want real reliability, you have to make it yourself.

Because Mother Nature aptly demonstrated how unreliable our current centralized generation and transmission system of providing electricity is on June 29, public officials are running for cover.

Governor Tomblin ordered a "storm review" investigation.

Senators Manchin and Rockefeller and Rep. Rahall begged for and were awarded federal disaster relief.

So, what is West Virginia going to do with the money?  Are our politicians going to do what they usually do and funnel the money to favored contractors for "make work" projects intended to enrich their friends?

The federal money shower is also intended to prevent a recurrence of the "disaster."  Instead of wasting money on empty promises, Tomblin, Manchin, Rockefeller and Rahall should spend more time looking for real solutions.

"To combat future widespread and extended power outages, Carnegie Mellon University researchers have devised a strategy to use local distributed electricity generation, distribution automation, and smart meters to form small electricity "islands" that would support critical social services in the event of a substantial disruption resulting from extreme weather, terrorism, or other causes."
2 Comments

FERC Denies Complaint of Primary Power

7/24/2012

0 Comments

 
As part of a series of decisions over transmission owner squabbles last week, FERC denied the complaint of Primary Power that we have been following.

You can read the Commission's Order here.


Read the statements of Commissioners Wellinghoff and Norris regarding these decisions.

FERC says that they had to follow the RTO agreements currently in effect.  In the Primary Power case, they relied on PJM's findings that the SVC projects would be cheaper if constructed by the incumbents.  Sounds great right?  After all, who doesn't want to save money?

However, PJM's evaluation of the projects was based on completely bogus cost estimates from the incumbents.  PJM's selection of incumbents to build the projects provides no guarantee that the incumbent projects will actually end up being cheaper.  In fact, the way things are set up now, there is no cost control or performance standard for the incumbents to meet.

" Primary Power challenges the Dominion and FirstEnergy claims of lower cost and avoiding duplication of facilities as lacking technical analysis and development work.  Primary Power claims that neither Dominion nor FirstEnergy proposed any SVC projects in the Meadow Brook or Mt. Storm areas prior to the November 2011 Advisory Committee meeting and notes that FirstEnergy initially objected to installing an SVC at Meadow Brook, favoring a static capacitor-based alternative.  Primary Power notes that it committed to the PJM Board that it had “plenty of time” to obtain a certificate of public convenience and necessity and complete construction before the June 1, 2014 in-service deadline. Primary Power challenges FirstEnergy’s cost estimate, noting that FirstEnergy exceeded its estimate when it built the Black Oak SVC.  Static capacitors, unlike SVCs, do not absorb VARs and do not provide a range in output, but may only be switched on or off."


The PJM cartel supposedly made its decision favoring the incumbents based on cost.  PJM is always thinking about you ratepayers, you know, and putting your needs first.  However, Primary Power claims that FirstEnergy and Dominion simply made up cost estimates based on rough calculations, with the goal being to arrive at a lower cost estimate than Primary Power's, which was already on the table.  How easy was it to simply make crap up when the incumbents know they won't be held to their estimates?

FirstEnergy will most likely request incentives and add this project to their TrAILCo shell company's formula rate.  Perhaps FERC can make these projects the first to be held to cost control and performance standards under a revamped system of awarding incentives.  After all, PJM's reasoning for awarding the projects to incumbents completely fails if the projects end up costing more than Primary Power's estimates when fantasy meets reality.  It would be just desserts for the incumbents to have to actually build these projects for the amounts they have estimated.  I'm quite sure they'll have an audience.


0 Comments

"Citizen Group Blast Transmission Proposal - WV Line Under Attack"

7/20/2012

2 Comments

 
Shh!  Be vewy, vewy quiet, the Coalition is hunting wabbits!

The trade press seems to be vewy, vewy disturbed by the Coalition for Reliable Power's filing at the WV PSC regarding FirstEnergy's "plan for reconductoring existing transmission lines" that was ordered by the Commission in the TrAILCo order.

Read the re-hash  that appeared in "EnergyBiz" (for leaders in the global power industry) of Pam Kasey's State Journal article.

When "leaders in the global power industry" decide to pursue an unneeded transmission project that costs you time and money, they're not "blasting" consumers and landowners.  But when a citizens' coalition dares to speak up about "a leader in the global power industry's" failure to comply with a legal order, all of a sudden the coalition is "blasting" them, and inexplicably, "WV line [is] under attack."  What line is that, EnergyBiz?

Notice how the industry's scribe goes out of his way to get comments from the PSC and First Energy, but ignores the Coalition, other than to report, in a dismissive fashion:
 
 "The CRP describes itself on its web page as a “grassroots citizens’ association” whose mission is "to create a vital public conversation about reliable electrical power and real alternatives to our dangerously centralized electrical grid.” The group lists six organizations and 43 individuals as its members."

Is your name on this list?  If not, email me, and your very own cartoon shotgun will soon be on it's way to you!

The PSC spokesperson had this vewy vapid comment to make:

“Had these come in while the case was active, then there would have been a set, 10-day response period,” the spokesperson said. “But, it being a closed case, there is no set response period.”

I'm not sure how the Coalition could have predicted that the Commission would order the report, and that FirstEnergy would fail to file a proper report, while the case was "active" in 2008, but maybe they need to borrow my Magic 8 Ball?

FirstEnergy said what they always say when they get clobbered by an unexpected kick in the gut:

"The TrAIL companies are in the process of reviewing CRP’s comments and will not have a response until their review is complete, a FirstEnergy spokesperson told TransmissionHub on July 18."  Translation:  "We will respond appropriately."

So, who else has gotten bombarded with "free" subscription offers from Transmission Hub lately?  Seems the industry-centric publication is getting pretty hard up for readers lately and has been harvesting email addresses from somewhere... like state PSC e-service lists.  Tsk, tsk, tsk!  What makes them think we want to read their drivel?
2 Comments

Keryn Newman v. Potomac-Appalachian Transmission Highline

7/19/2012

0 Comments

 
FERC noticed the complaint and set a deadline of August 7 for answers, interventions, protests or comments.

If you'd like to contribute you own two cents, follow the instructions on the notice.
0 Comments

Jefferson Co. Commission to Request Dominion Hold Public Information Meeting

7/19/2012

2 Comments

 
This morning, the Jefferson County Commission decided to send a letter to Dominion Power requesting that the company hold a public information meeting in the county regarding their Mt. Storm - Doubs 500kV transmission rebuild project.  The letter will also request that Dominion answer specific questions raised by citizens at today's Commission meeting (that Dominion couldn't be bothered to show up for).  Dominion may think that they can continue to ignore the citizens and local government in Jefferson County, but I wouldn't advise that plan of (in)action.

Citizen Robin Huyett Thomas spoke to the Commission during public comment and advised them that certain lenders will not approve financing for homes within the fall zone of transmission towers.  There are many homes in Jefferson County that are already affected.  However, Dominion's plan to increase the height of its towers by another 30 feet will necessarily affect additional homes.

Keryn Newman spoke to the Commission during a scheduled agenda item on the rebuild and presented the detailed public safety questions posed by citizen Sharon Wilson, who could not be present for the meeting.  Sharon is concerned about the public safety aspects of access roads, proximity of the work zone to homes, coordination with local public safety/emergency services, and possible future road closures during construction (remember, Dominion's line crosses both Rt. 340 and Rt. 9, in addition to many other secondary roads).

Keryn also presented her own personal concerns that a design defect in steel lattice transmission towers has been known to the industry for many years, but it appears industry has made no improvements to their design.  Commissioner Pellish commented that one of the references in the abstract of a recent engineering study of the design defect that was presented to the Commissioners went all the way back to 1996.  Utility engineers have been aware for at least 16 years that transmission towers are subject to failure from downburst wind, but have done nothing to change the design or reinforce their existing towers.  The Commission wants to know whether Dominion's new towers are designed to withstand downburst wind.  A simple "yes" won't do.  Show us.

Lastly, Keryn spoke on behalf of the StopPATH WV, Inc. organization, who supports Dominion's rebuild project.  However, public relations is an integral part of any major infrastructure project and Dominion has failed to provide information to the public.  Public trust in utilities is at an all-time low in Jefferson County, the legacy of the PATH project that just keeps on giving.  Our goal is for the community to be informed about what to expect, where to get relevant updates and information, and for Dominion to develop an ongoing relationship and dialogue with the citizens of Jefferson County, who want to see this project completed quickly, safely and as cost-effectively as possible.

Now the question is -- will Dominion step up here, or will the company continue to pretend that their project only affects those with towers on their property, and that the rest of us haven't noticed or don't care.  We have and we do.  The ball is in Dominion's court.
2 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.