7/31/2014

6 Comments

 
W T
PPL?
I think PPL needs to do a round of drug testing of its employees.  Whoever came up with this idiotic idea must be on something.

PPL announced today that it had "submitted an application to PJM" to build a 725-mile 500kV line, estimated to cost $6B, through four mid-Atlantic states.

Never going to happen.

Residents of affected states are still reeling from PJM's last big transmission building idea, Project Mountaineer, that cost them billions, including nearly half a billion dollars for planned projects that were never built.  Try it, PPL, and you will experience coordinated, strategic opposition like you've never seen before!

The Morning Call seems to be the first media outlet to... err... call PPL out on its outrageous money-making scheme.  PPL interstate transmission project both costly and lucrative:  Project would fill utility coffers while costing ratepayers billions of dollars.

Morning Call says:
The project also would be a significant source of revenue for PPL Corp., PPL Electric Utilities' Allentown-based parent. Under Federal Energy Regulatory Commission rules designed to encourage infrastructure investment, utilities may earn a profit of 11.68 percent on transmission projects.
That translates into a profit of up to $700 million. PPL would share the money with any other utilities that participate in the project.
PPL customers, meanwhile, would see the cost, including utility profits, reflected in their rates — though the burden of paying for the project would be shared by ratepayers in all four of the states involved.
But, Morning Call only sees the tip of this iceberg.  PPL can apply to the Federal Energy Regulatory Commission for transmission rate incentives that would up its profits significantly.  In addition to incentive ROE adders that can increase the 11.68 percent several percentage points, PPL can also ask for guaranteed cost recovery in event of abandonment, a return on construction work in progress that enables them to begin earning that juicy return immediately, even before the project is completed, and many other outrageous financial rewards.

In addition, Morning Call's math is wrong.  The $700 million profit the reporter calculated is only that earned in THE FIRST YEAR of operation.  Transmission project rates work sort of like a 40-year mortgage.  The return is calculated and paid on the depreciating balance of the project cost every year!  So, in the first year of operation, PPL would earn a return on $6B and collect a certain amount of depreciation on the project assets that would lower the balance owed by ratepayers.  The second year, PPL would earn a return on the depreciated balance, and additional depreciation.  And so on, over the 40 year (or more) life of the capital assets.  PPL's possible profit from this ridiculous project is a nearly endless goldmine!

And, one last thing Morning Call gets wrong -- this project will be paid for, in part, by ratepayers in all 13 states in the PJM region because of its size.  A 500kV project built in PJM is cost allocated at 50% to all ratepayers based on peak usage, with the other 50% being assigned to the cost causers/beneficiaries.

Moving right along into PPL's feeble assertions that its project will:
If approved, PPL predicts, the project will improve energy reliability and security and provide customer savings by eliminating transmission bottlenecks and encouraging development of lower-cost natural gas-fueled generation plants.
The new plants would help replace energy supplied today primarily by coal-fired plants that, under increasingly stringent federal air quality standards, are expected to be retired in coming years.
This doesn't even make sense.  The coal-fired plants that will be closing are located in the Ohio valley, not on the east coast.  Once those coal-burners are offline, it will free up significant transmission capacity for any new "mine mouth" Marcellus shale gas-fired plants built in the Ohio valley.  Why would we need to build a new west to east transmission line when there's already plenty of them sitting idle due to coal-plant closings?

PPL says they will have a robust public input process to find out where to site the line.  Seriously?  That strategy doesn't work anymore.  It's all about need for the line in the first place, not where to put it.  Get with the brave new world of transmission opposition, PPL!

And speaking of siting the line... where is that new Maryland substation supposed to be on that featureless map?  If you compare it to a real map of Maryland, it looks like it's in Howard or Carroll counties.  But, what if there was land available in neighboring Frederick County for a proposed substation?  Oh, deja vu!

This has got to be the most thoughtless transmission proposal I've ever seen. 

Never going to happen.
6 Comments
Patience
8/1/2014 11:01:01 am

Hmmm ... besides the substation somewhere in MD, am I the only one to think about the prospect for a resurrection of the St. Albans-to-Kempton - i.e., PATH - line?

Reply
Keryn
8/1/2014 11:33:48 am

Don't ya think we should finish paying for PATH before creating Son of PATHenstein?

Reply
Patience
8/3/2014 10:13:38 pm

Hell, no! Don't you think that Tony the Trickster, et al, would laugh their @$$e$ off at the prospect of getting paid TWICE for the same ridiculous project?!?

Reply
Keryn
8/4/2014 10:33:08 am

But don't you think Tony the Trickster should think twice about the prospect of taking us on TWICE for the same ridiculous project?!? We're twice as smart now, and 10 times as bitchy :-)

Scott
8/4/2014 10:10:33 am

Ah, tell me why again are we in Illinois paying to "fix potholes" out in New York? How does this benefit me in Illinois?

Reply
Keryn
8/4/2014 10:31:31 am

Well, Judge Posner says it doesn't benefit you. FERC and PJM say it does. The jury's still out on that one...

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.