StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

PJM's Constructability Farce

12/1/2023

0 Comments

 
Constructability?  Is that a word?  My internet spelling police hates it, but constructability is defined as:
Constructability (or buildability) is a concept that denotes ease of construction. It can be central to project management techniques to review construction processes from start to finish during pre-construction phase. Buildability assessment is employed to identify obstacles before a project is actually built to reduce or prevent errors, delays, and cost overruns.
PJM loves its constructability analyses to select a project from a pool of many options.  PJM pretends it's all so scientific and dependable.  But, is it really?

Here's PJM's Constructability and Financial Analysis Report.  I didn't expect it to be anywhere near correct or accurate, and I wasn't disappointed.  It's completely illogical to the point of demonstrating bias.  Why is it that PJM has selected some of the most risky projects to recommend for approval by its Board of Managers?  Here's what I mean (see page 115 of the report for larger image):
Picture
Out of this "west" group, PJM has selected the riskiest project, Proposal 853.  853 has two "high" risks, two "medium-high" risks, and two "medium" risks.  It's the riskiest one in the table.  So, maybe it's about costs?  Proposal 853 costs $1,195,240.  It's still more than the cost of Proposal 904 at $1,122,400.  It can't be based on price.  Just what DID motivate PJM to select 853 instead of 904 or one of the other projects on the table?

What is proposal 904?  It's the building of a new 765kV transmission line through a section of central Virginia.  904 connects the data centers to a huge inventory of fossil fuel generators in the Ohio River Valley using AEP's 765kV transmission network.   Significantly, proposal 904 keeps all the transmission necessary to serve Virginia's new data center build in Virginia.  The other proposals inflict the burden of serving Virginia's data centers on other surrounding states.  Keep that in mind as we examine these two competing proposals as PJM did in its Constructability report.

Project 853
Overall, the ROW risk for the new West cluster transmission line components in this proposal is medium-high to high, as the proposed new transmission lines are routed parallel to an existing ROW for majority of their alignment. 

Environmental Risk Analysis
46a – 502 Junction to Black Oak OH 500 kV Line
Route crosses West Virginia and MD Department of Natural Resource (DNR)-recognized public lands and is also within a short distance of residential areas.
4CA – Black Oak to Woodside OH 500 kV Line
Route crosses through the Appalachian Mountains and intersects with VA Natural Heritage easements.
10C1A – Woodside to Gant (Segment 1) OH 500 kV Line
The proposed route for this line segment goes through several national scenic and historic trails (Harpers Ferry National Historical Park and the Appalachian Scenic Trail), and intersects public lands and conservation easements. This may require permission from the National Park Service (NPS) and require an Environmental Assessment (EA) pursuant to the National Environmental Policy Act (NEPA) to analyze the impacts to the environment and park resource, which could be a lengthy process. This route is also within a short distance of residential and commercial areas.
10C3 – Woodside to Gant (Segment 2) OH 500 kV Line
The proposed route for this greenfield line segment goes through highly developed residential and commercial developments, as well as state and local conservation easements. This route also crosses the Washington & Old Dominion (W&OD Trail), a regional park in northern Virginia. There is significant risk of public opposition to the proposed route, which may lead to rerouting this segment along the existing corridor from Doubs to Goose Creek.

Overall, for Proposal 853, medium-high constructability risks are assessed for the proposed line routes due to anticipated lengthy regulatory process, potential public opposition, construction difficulty, environmental constraints and property acquisition, which may have significant impacts on the cost and schedule for the proposed project.

Transmission Line Risk Analysis
Significant engineering and construction challenges are anticipated for the proposed lines to construct a total of 167 miles of new transmission through four states and will require parallel crews and construction where possible to mitigate schedule challenges that will be introduced by the anticipated lengthy permitting and land acquisition process.
For the rebuild portions of the proposed line routes, there are challenges with existing overhead transmission infrastructure components needing to be removed/salvaged before construction of proposed brownfield lines can commence, and potential design and ROW limitations for reuse of existing infrastructure/assets.
Other medium risks for this project involve the existing facility outages that will be necessary for the project, particularly for the line rebuild and substation upgrades. 

Schedule Review
The proposed in-service date of June 2027 is very aggressive for the proposed scope of the project considering the significant permitting and land acquisition challenges associated with the proposed 500 kV greenfield line routes through four states. Overall, the schedule risk is considered medium-high. 
Project 904
Environmental Risk Analysis
Joshua Falls-Yeat 765 kV OH Line
The proposed line route has the potential to impact environmental and cultural resources including: the Southern Albemarle Rural Historic District, a FEMA High-Risk Flood Zone, wetlands and several waters subject to USACE Section 10 permitting, the most significant being the James River. The route also intersects local conservation easements and appears to co-locate with pipeline ROWs.
Warrenton-Wheeler 230 kV OH Line
The line crosses woodland, residential and agricultural parcels in Fauquier and Prince William counties in Virginia. The route intersects local conservation easements and potentially impacts environmental resources such as Auburn Battlefield Historic District, flood plains and wetlands.
There are medium constructability risks assessed for the proposed line routes due to anticipated lengthy land acquisition process, potential public opposition and environmental constraints, which will have impacts on the cost and schedule for the proposed project.
Transmission Line Risk Analysis
Transource has an optimistic schedule for several aspects of this component and would require a near perfect execution to maintain the proposed in-service date. Given the scale of the component, a 135 mile 765 kV line with everything from permitting to land acquisition to construction poses a risk for delay, the most critical being land acquisition.
For the 230 kV developments, Yeat-Clover Hill and Warrenton-Wheeler, these facilities will utilize BOLD (Breakthrough Overhead Line Design), which is a structure family developed by AEP. The design features a monopole structure with two arched crossarms to hold two circuits in a delta configuration. Benefits of BOLD include increased line capacity with lower-profile structures. However, utilizing this structure family poses risks to the schedule, specifically procurement of the arched crossarms, construction and maintenance of a non-typical design.
​
Schedule Review
This proposal includes 765 kV substation and transmission line construction, as well as utilization of BOLD (Breakthrough Overhead Line Design) technology for the greenfield 230 kV lines. The sum of all components is a very aggressive undertaking to be completed within the proposed schedule. The primary risks for this proposal are related to the magnitude of the scope of work, procurement and construction of 765 kV equipment and BOLD structures, state permitting and land acquisition for both the 765 kV and 230 kV developments. These all pose a medium-high risk to the December 2029 in-service date proposed by Transource. 
Project 853 has medium-high constructability risks, while 904 has medium constructability risks.  Gee, no help there either.  904 is cheaper and less risky, but PJM still selected 853.

And then there's this tidbit... did you catch it the first time you read it?  
There is significant risk of public opposition to the proposed route, which may lead to rerouting this segment along the existing corridor from Doubs to Goose Creek. 
PJM KNOWS this project isn't going to happen the way it was proposed and recommended for approval.  PJM is already anticipating so much opposition to the new greenfield segment in Loudoun County that it will have to abandon this plan and move the proposed new 500kV transmission line over to an existing corridor between Doubs and Goose Creek.  What is that corridor?
Picture
The 853 project in Loudoun is represented by that green line.  The Doubs corridor is represented by that roughly parallel yellow line to the east.  Sounds like a solution, you think?  Think again!  PJM has also recommending work on the Doubs-Goose Creek corridor to add another 500kV line to its existing 500kV and 230kV lines.  In order to squeeze another 500kV line in there, PJM proposes to rebuild the existing 230kV line as a double circuit 230/500 kV line, and then add a second 500kV line.  Moving the 853 project over to the Doubs corridor would add a THIRD 500kV line to that existing corridor.  Would that be a double circuit 500/500 kV, in addition to a 230/500 kV double circuit?  Or would there be one 230/500 kV double circuit, and two separate 500 kV lines?  Either way, it will require significant expansion of the current easement through a heavily developed area of Frederick and Montgomery Counties (Maryland) and construct an unimaginable amount of power in that corridor (three 500kV circuits + one 230kV circuit).  Chances of success on this idea rate right up there with the survival of a snowball in Hell.  Which area is capable of forming bigger opposition?  Loudoun County or Frederick/Montgomery Counties?  Personally, I think it's a tie.  Either one is going to kill this project dead.  Remember, it's not about fighting each other to push the project off onto someone else, it's about stopping the bad project altogether.  Nobody wants this anywhere!

So, what did we learn from PJM's constructability analysis?  Not much.  PJM did not examine the gray areas of opposition that I did.  PJM pretty much ignored the possibility of opposition derailing their plans.  Dismissed!

But, we're not going away.  In fact, we're only going to get stronger.  I predict that this project will NEVER get built.  Maybe PJM should go back to the drawing board and take another look at project 904?  Why did they dismiss that project anyhow?  PJM never actually says.  In fact, after reading all of PJM's excuses, err I mean analyses, I came away more convinced than ever that this whole thing is a farce.  Some of the excuses for not selecting a project were so ridiculous, such as -- we didn't select this project because we selected a different project.  That's not a REASON for making a project selection.  I also got the idea that PJM is absolutely terrified of rich people opposition in certain areas of Northern Virginia.  PJM has bowed down to the wealthy and privileged due to their bad experience trying to route the TrAIL project through those areas.  PJM thinks it's a better idea to route its projects through disadvantaged areas that can't fight back (or so they think).  That kind of thinking is outrageous in this day and age of environmental and energy justice reform.  Add in the fact that PJM's new transmission lines are nothing but extension cords importing dirty, delicious, coal-fired electricity out of West Virginia and Pennsylvania and you've got a project idea that is dead on arrival when asking for federal help.

Stupid, stupid, stupid, on top of dumb, dumb, dumb, PJM!  It's obvious PJM has another agenda at work here and it's not providing needed electric service at the lowest cost.  Let's hope the PJM Board of Managers examines this farce carefully before making its decision on December 11.
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.