PJM Consumers on the Hook for $80.5M for Failed MAPP Project

3/5/2014

4 Comments

 
A settlement has been approved by the Federal Energy Regulatory Commission in the matter of recovery of costs of PJM's failed Mid-Atlantic Power Pathway (MAPP) project.

MAPP was one of four unnecessary transmission projects proposed by PJM in their Project Mountaineer initiative to increase the use of coal-fired resources by shipping 5,000MW of coal-fired electricity from the Ohio Valley to the East coast.  Of these 4 projects (MAPP, PATH, TrAIL and Susquehanna Roseland), two have been cancelled, one has been completed, and one is under construction.  The only difference between them is timing and execution by their owners.

All four of these projects took advantage of newly-minted transmission project incentives available from FERC, brought to you by the Energy Policy Act of 2005.  One of the incentives granted to these projects was the guaranteed recovery of prudently-incurred project investment in the event the project was abandoned and not built through no fault of the owner.

Therefore, once MAPP was abandoned, its owner, Pepco, filed with FERC for permission to recover its investment in the unbuilt project.  Unrecovered investment included capital expense "construction work in progress" costs, which is roughly defined as all expenses for electric projects under construction, including such items as land purchased, labor, engineering and regulatory costs.  The amount Pepco filed to recover was $87.5M.

Because some parties intervened and protested the recovery, FERC set the matter for settlement and hearing.  A settlement was reached and recently approved by the Commission.

The settlement allows Pepco to recover $80.5M in abandonment costs over a three year period, and allows the company to maintain ownership of all land and land rights purchased as part of the project.  However, Pepco must remove the land from its rate base (capital account) that earns a yearly return paid by all electric consumers in the PJM region.

In its cost recovery filing, Pepco valued its land acquisition activities at $38.1M, although actual land values would most likely be much less.  So, how much land did Pepco buy for MAPP that the company now owns free and clear?
Converter station sites in Calvert and Wicomico County, MD and Sussex
County, DE were acquired;

Takeoff points into and out of the Chesapeake Bay were acquired;

Transition station locations in Dorchester County were acquired; and

Transmission line right-of-way for entire length was acquired, except for one property in Dorchester County where negotiation was pending.
Looks like Pepco has enough land to concoct another unnecessary transmission project at ratepayer expense, and it looks like Pepco still holds these landowners' lives in limbo under the threat of building a transmission line across their properties.  Let this be a lesson to you... do NOT sign right-of-way agreements early in the process, before a project is approved and receives a permit from all states through which it is routed.

Ratepayers in 14 states will remember PJM's failed Project Mountaineer as they pay off Pepco's unbuilt MAPP debt in their electric bills for the next three years.
  Thanks, PJM!



4 Comments
Suze
3/5/2014 09:38:18 pm

80 milliion is a lot of money. With that kind of money, I could buy myself 15 private islands in the caribbean. It would pay fat cat Rigby's salary for 7 years. what a ripoff!!!!!

Reply
Anya Schoolman
3/10/2014 12:46:52 am

Reply
Jim Long
3/13/2014 09:19:24 pm

It sounds like ratepayers are buying right-of-way, and then giving the land to Pepco. Is this a correct interpretation?

Reply
Keryn
3/14/2014 12:30:57 am

Good question, Jim, and one you could rightfully pose to your Office of People's Counsel, who appears to have been a settling party. There was some reduction in dollar value from $87M to $80M, and some other concessions made (read the settlement agreement), but since FERC settlement negotiations are confidential, I'm not sure how much of an explanation you may get. None of the agencies participating in settlement are concerned about landowner issues, and no landowners intervened and participated. And that's the way this system works -- if you don't participate, you have no say in the outcome. There was an opportunity for affected landowners to participate in the settlement process (as landowners/ratepayers have done with the PATH abandonment settlement still in process) but no one took advantage of the opportunity in the MAPP abandonment case.

As long as consumers/landowners/ratepayers divorce themselves from government processes, they remain victim to having their fate discussed around a conference table by officials who may not have their best interests in mind. It's much easier to affect the outcome when participating in the decision-making process, than to attempt to change a decision after the fact.

True change is a constant, not a one-off.

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.