MARL and Gore-Doubs-Goose Creek are the SAME project!

8/27/2025

0 Comments

 
The companies assigned to build one of the components of PJM Interconnection's project B3800 have made an absolute mess of the public's understanding of the project.  Congratulations, NextEra and FirstEnergy!  This is all your fault!

PJM doesn't invent and assign cutsie-poo names like MARL or Gore-Doubs-Goose Creek to the projects it approves and orders.  It gives them numbers.  B3800 was assigned to this project when it was approved in December 2023.  Names like MARL and Gore-Doubs-Goose Creek are inventions of the companies that PJM assigns to build the projects it orders.  Different names do NOT mean different PJM projects.  They're all B3800.

Here's the only thing you need to know about MARL and Gore-Doubs-Goose Creek.
Picture
A picture is worth a thousand words, right?  If you study this one, you'll figure it out, despite the stupid stuff NextEra and FirstEnergy are saying right now.  Block all their nonsense out of your mind.  This is one continuous 500kV transmission line.  It's all connected, just like a gigantic extension cord.  Pay attention to the key on this map.  There is a table called  "Transmission System Enhancement" that lists the different color-coded line segments and the companies that PJM assigned to build each segment of this ONE 500kV line. 

Starting at the top of the list is a dark pink/purply segment assigned to AEP.  AEP stands for American Electric Power, who owns a section of existing 500kV line between the Kammer substation and the 502 Junction substation.  AEP's part of this project was to study its existing line to assure it could pump more power from Kammer.  Kammer is the name of the substation at AEP's Mitchell Power Generation station in Marshall County, WV.  AEP is not building a new line here (at least not in this project).

Next the table lists yellow for Dom.  That stands for Dominion.  Dominion is the Virginia-based utility that will be building the last 3 miles of this 500kV circuit from Edwards Ferry to Goose Creek in Loudoun County, Virginia.  It's really impossible to see the yellow part of this map because it's tiny compared to the rest of the line's mileage.  Just know it's there, at the eastern end of the line.

Then we have red for Exelon.  Exelon owns a short segment of existing line and easement in Montgomery County, Maryland that would be reconfigured to change a corridor containing one 500kV line and two 230kV lines into a corridor that contains three 500kV lines and two 230kV lines.  One of those new 500kV lines in Maryland is part of B3800, the continuous 500kV line from 502 Junction to Goose Creek. You can barely see the red if you look hard.

And now we're getting to the real meat here... blue and peach.  The blue part of the line is owned by FirstEnergy (FE) subsidiary Potomac Edison.  The FE part of the line begins at a point in Frederick County, Virginia where the NextEra part ends and runs east through Jefferson County, WV, Loudoun County, VA, and Frederick and Montgomery Counties, MD to a point at Edwards Ferry where Dominion picks up the construction of the 500kV circuit.  The blue part of the line is approximately 45 miles long.  The blue part of the line plans to tear down an existing 138kV circuit on 65 ft. tall towers and replace it with double circuit 500/138kV lines on a new tower 185 ft. tall.  FirstEnergy named this part Gore-Doubs-Goose Creek.

And last, but certainly not least, the peachy colored part of the line that is assigned to NextEra.  This 105-mile long segment begins at 502 Junction substation and ends at a point in Frederick County, Virginia were FirstEnergy's segment of the project begins.  We're literally talking about two adjacent transmission towers carrying one continuous 500kV circuit, except one tower is owned by NextEra, and the other is owned by FirstEnergy.  These are not two separate projects physically.  The separation only exists in legal documents and the balance sheets of competitors NextEra and FirstEnergy.  NextEra named its peach MARL.

To put the parts of the map in order from west to east:  dark pink (AEP), peach (NextEra), blue (FirstEnergy), red (Exelon), more blue (FirstEnergy), and then yellow (Dominion), which connects to a substation that serves Loudoun County's data centers.

PJM approved and ordered ONE 500kV circuit between 502 Junction and Goose Creek and then assigned the project to 3 different companies to build.  Each company has made up its own name for its segment.  NextEra calls its 105-mile portion of the project MARL.  FirstEnergy calls its 45-mile portion of the project Gore-Doubs-Goose Creek.  Dominion has not come up with a name for its 3 mile section in Virginia because it has not presented the project to the public yet.

This confusion about who owns what and what the project is called and what connects to what can be flung directly on the door step of NextEra and FirstEnergy.

NextEra has been playing pretend games that its 105-mile segment of PJM's 500kV circuit is a separate project not connected to anything else.  NextEra says it begins in PA and ends in Frederick County, Virginia.  The media has added the narrative that MARL connects with "a data center in Frederick County, Virginia" which is just false.  There are no significant data centers in Frederick County.  All the data centers are in Loudoun County.  Loudoun and Frederick are not even contiguous counties.  Jefferson County, WV sits between them.  We need some basic geography here!

NextEra may have created this false narrative in the press because it thought that it could escape any bad data center juju being attached to its project.  Didn't work.  We all know MARL is a data center extension cord.  All that narrative did was confuse the heck out of people when Jefferson County popped into the picture on Monday when FirstEnergy filed a Notice of Intent at the PSC.

FirstEnergy, for its part, contributed to this confusion by refusing to name its project, or to do any public relations about it until just recently (and still its attempts can be called anemic at best).  The citizens of Jefferson County have been fighting FirstEnergy's part of PJM's 500kV circuit for 2 years now.  Because FirstEnergy refused to acknowledge the project, we named it for them, and we called it MARL, adopting NextEra's name for this 150-mile long 500kV circuit.

So, when FirstEnergy's Potomac Edison filed its Notice of Intent at the PSC, it said the project was "also referred to as MARL".  That is absolutely 100% true.

And the media circus began.  The stories pumped out don't even make sense, and the confusion becomes deeper and deeper.  Take a deep breath... just look at the map!
Picture
I'm guessing that NextEra got its corporate panties in a wad yesterday because FirstEnergy had used their MARL name in their Notice of Intent at the PSC. FirstEnergy tried to issue a retraction yesterday.  This confused things even more.
And, using my best mom voice, here's some advice that NextEra and FirstEnergy should take to heart.

GET OVER YOURSELF, KIDS!

Stop your bickering and squabbling and not wanting to be associated with each other.  It's going to come back and bite you in the butt at the PSC.

The PSC will have two separate applications for two different segments of the same transmission line.  Are the companies going to keep pretending they have nothing to do with each other before the PSC?  That's going to be a little uncomfortable for PJM's witness, won't it?  You'll never get away with it.  And it would serve you right if the PSC denied one of these segments because they didn't know the other was connected to it.

​FIX THIS MESS!
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.