Learning from the Cascading Power Failures that Brought Down the Power Grid in India

8/6/2012

1 Comment

 
by Deb Severson

On Tuesday July 31, 2012, India’s interconnected power grids failed, leaving half the population without electricity.

Cascading failures occur in systems of interconnected parts. They usually begin when one part of the system fails. Nearby system parts must then compensate for the failed component, which can overload that part to trigger a vicious cycle as successive parts fail.

When Federal Energy Regulatory Commission (FERC) chairman Jon Wellinghoff was asked if power problems in the Northeast could spread all the way to California, he told ABC News, “It’s very, very unlikely that ultimately would happen.” Part of why the risk is low, the ABC story conveyed, is due to our nation’s grid being divided in the middle.

Unfortunately, this division still leaves hundreds of millions at risk for cascading failures, and increased investment in transmission is in NOT the answer.

A comprehensive, three-year DoD and Federal Emergency Management Agency study — Brittle Power: Energy Strategy for National Security — concluded that relying on massive, complex, and interconnected infrastructures that need to transmit and deliver power from centralized generation create unavoidable (and costly) vulnerabilities.

Cascading failures in “brittle” interconnected electrical systems can be induced by severe weather, human error, sabotage, or even the interference of small animals. Conversely, resilient infrastructure systems are less likely to collapse in the face of natural or manmade disruptions and will limit damage when disruptions occur.

A 2007 US Department of Energy (DOE) study, The Potential Benefits of Distributed Generation and Rate-Related Issues that May Impede Their Expansion, provides compelling evidence of how a distributed network of smaller sources was able to adjust to problems without causing major consequences. A decentralized system also reduced the magnitude and duration of failures.

The DoD study on “brittle power” further concluded that centralized energy facilities create tempting targets for terrorists because the terrorists would need to attack only a few, poorly guarded facilities to cause large, catastrophic power outages. In a complementary study, Energy Security in a Dangerous World, the International Energy Agency reaches the same conclusion.

Examples from nearly every area of critical infrastructure defined by the Department of Homeland Security verify distributed generation (DG) to be a viable means for reducing vulnerability to terrorism and improving the resilience of electrical infrastructure. This is based on actual cases where DG continued to provide power to critical facilities during times of large-scale power disruptions and outages, and is documented in the 2007 DOE study.

Richard Clarke, a former national security adviser and ABC News consultant also conveyed, during the ABC Nightly News coverage of Black Tuesday, that today’s biggest grid threat is cyber-attack. “The U.S. power grid is extremely vulnerable to cyber-attack,” Clarke said. “The government is aware of that. Recently the government held a White House level cyber exercise in which the scenario was a cyber-terrorist attack that took down the power grid.”

A July 17, 2012 webinar, New Approaches to Grid Security, featured three of the electric industry’s most knowledgeable and influential leaders in grid reliability -- Terry Jarrett, MPSC regulator and chair of NARUC committee on critical infrastructure, Terry Boston, president and CEO of PJM Interconnections, and Gerry Cauley, president and CEO of North American Electric Reliability Corp.

Each of these experts stressed the importance of resilience – the ability of the electrical infrastructure to quickly respond to cyber, terrorist and weather induced attack. Mr. Cauley also conveyed how the interconnected grid throughout the US and Canada created challenges to protecting the grid from cyber-attack due to issues related to information sharing and analysis.

Expert testimony from Dr. Benjamin Sovacool regarding a 500 kV transmission line in Virginia demonstrated how long-distance transmission reduces the stability of the electric grid. Dr. Sovacool concluded, “The proposed project should be rejected on grounds that it fails to provide substantial reliability and security as defined by (the utility) Dominion itself. Instead, the proposed line increases the vulnerability of Virginia and the National Capital Area to critical national security threats.”

Dominion -- one of the nation's largest producers and transporters of energy, which serves electrical needs for customers in Virginia, West Virginia, Ohio and North Carolina -- received permission to construct this project connecting Meadow Brook to Loudoun. The $243 million, 65-mile long overhead transmission line was placed in service in mid-2011. On June 29 2012, more than a million customers in DC, Virginia and Maryland suffered mass power outoutages due to “derecho” storms. The area’s electrical grid was slow to recover.

The August 14, 2003 rolling blackout of the East Coast was, at the time, the second most wide-spread blackout in history, affecting an estimated 45 million people in eight U.S. states and 10 million people n Ontario. In this disaster, a power surge affected the transmission grid, resulting in a cascading failure. The tools in place to analyze the “what ifs” didn’t do their job and the appropriate people didn’t understand the issue was theirs until their own lights went off. By then, an uncontrollable cascading failure was under way and it was too late for human intervention to save the grid.

In 2005, Congress put in place financial incentives to improve existing transmission to prevent future blackouts. Since then, most of the funding has been diverted to new transmission and, in 2011, the US experienced another significant black-out.

In reviewing the cause of the September 28, 2011 blackout, which affected up to 5 million people in California, Arizona and Mexico, NERC and FERC found “common underlying causes” to the 2003 East Coast black-out. The power loss should have been limited to the Yuma, Arizona, area but, according to the power company, Arizona Public Service, “…an employee was just switching out a piece of equipment that was problematic."

This clearly indicates that transmission incentives have not produced a corresponding increase in reliability that would prevent future blackouts, as Congress intended. Despite this, building more and more interconnected transmission is rampant. $170 billion in new transmission is planned nationally between now and 2020. In Wisconsin alone eight new high voltage lines planned that will greatly increase inter-connection from Maine to the Dakotas.

CapX2020, a controversial and contested high voltage transmission line, is planned to cross the Mississippi River at Alma, Wisconsin. Despite testimony of inherent grid instability, the Wisconsin Public Service Commission (PSC) approved CapX2020 on May 30, 2012.

The next interconnected segment of this line, known as Badger Coulee, would connect to Madison.

This type of transmission expansion is planned all over the country, making further interconnection of the nation’s grid imminent and immense.

The utilities behind CapX2020 and the Wisconsin PSC contend the line is needed for “regional reliability.” Those leading the court challenge against the line believe this is a manipulation of the term as it is economically driven and defined by the ability to more reliably move electricity around to sell to other markets.

It is time to for utilities to embrace another approach and to more fully acknowledge inherent issues in monitoring and controlling an interconnected grid. Dr. Sovacool warned in his 2007 testimony, “Long distance transmission is not reliable. Given the complexity of the modern electrical system, and what we know about the role reactive power has played in recent outages, relying on longer transmission lines to wheel greater amounts of real power is perhaps the worst strategy for ensuring system reliability. Large and long transmission lines lose reactive power the larger and longer they become, requiring the system to compensate in ways that increase the likelihood of systems collapse.”

Dr. Sovacool also shared how catastrophic failures are most often the result of human error, inadequate diagnostics, and/or voltage instability due to insufficient reactive power — the power that keeps voltage and current in phase.

In electric transmission, if a fault occurs and takes a line out, the change in current flow is compensated by other transmission lines. If they lack the capacity to carry the excess current, overload protection in those lines will also trip, causing a cascading failure as the excess current is switched onto neighboring circuits running at or near their capacity.

The role of a system operator is to monitor power supply and demand to keep them balanced and within safe operational limits. If a system failure occurs, operators must get power from generators or other regions or reduce their load to bring the system into balance and, hopefully, avoid a cascading system failure. Computer systems, with backups and alarms, are used to monitor the system. If the computer systems fail, system operators monitor the grid manually. Local operators are coordinated by regional centers, but the operating principle is the same for the larger network. Applying this and lessons learned in the 2003 and 2011 US blackouts and to Black Tuesday in India -- the largest in human history – is highly relevant and insightful.

Human and equipment error will continue to happen, and interconnected systems are vulnerable to cascading failures. It simply is what it is. Fortunately many of India’s major corporations and industrial groups were spared much of the blackout disruption because they generate their own power.

Perhaps, in the US, we are not encouraging investment in the right kind of improvements to enable similar avoidance of distress. Perhaps it is time to invest in an efficient, diverse, dispersed electricity system, where major failures—whether by accident or malice—become improbable by design rather than inevitable by design. The number of citizens, municipalities, states and associations asking that viable, cost-effective and sustainable alternatives to high voltage transmission be evaluated is growing. Unfortunately, so is the number of transmission lines being built and planned.

Due to this pressure, FERC has agreed to evaluate whether its own incentives are leading to an over-application for transmission and subsequent profits. Citizens are also suggesting that a conflict-of interest may exist in the planning groups of the Midwest regional grid operator (MISO) by having for-profit transmission builders at the helm of their Planning Advisory Committee and Planning Subcommittee. The dauntingly high operating-margins provide further insight into why some feel it is
greed, not need, that is driving this push for transmission.

In December 2011, Financial News Network reported that ITC Holdings, the largest for-profit transmission only company, has the highest operating margins in the electric industry (51.7%). ATC, which wants to build the high voltage line connecting La Crosse to Madison, has an even higher margin of 54.9% when dividing 2010 operating income by revenue. In Wisconsin, a legal battle has ensued between Xcel and ATC regarding ownership of the Badger Coulee line and the subsequent profits.

The public also is not accepting ATC’s claim that looking into non-transmission alternatives is “beyond the scope of the (transmission) project.” Instead, ratepayers are asking the Wisconsin PSC for cost/benefit analysis of feasible alternatives, including how they impact grid reliability and the sustainability of our natural resources. They are educated on job creation and energy savings benefits of energy efficiency over transmission, as well as the benefits of home grown energy and a decentralized grid.

The commitment and tenacity to address these issues is evidenced by groups including Citizens Energy Task Force (CETF)/No CapX2020, Piedmont Environmental Council and Stop PATH WV, which are willing to lead the charge all the way to the courts.

Incidents such as the black-out in India, terrorist attacks on September 11, 2001, the Northeast Blackout of August 2003 and Hurricane Katrina are wake up calls. They remind us how dependent we are on electricity and how fragile a brittle grid can be.

We’re at a fork in the road.

Before we invest hundreds of billions of dollars in interconnected transmission, we must heed the experts and activists who are working to replace the outdated paradigms of infrastructure protection and infrastructure centralization with infrastructure resilience.

The time to change our course is now, before what happened in India threatens half the American public.

1 Comment
Diploma project centers in chennai link
6/25/2014 09:55:50 pm


VLSA Global Services helps you with practical sources of advice which will enable
you to successfully write your final year project, dissertation or thesis.

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.