StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Independence Energy Connection Causes Uncontrolled Congestion and Reliability Violations

6/15/2024

0 Comments

 
Picture
Did you oppose the Transource Independence Energy Connection transmission project ordered by PJM in 2016 to run through York and Franklin Counties, Pennsylvania?

THANK YOU!!!

After years of battle, PJM has finally re-evaluated IEC and made the determination that it causes uncontrolled congestion and reliability concerns starting in 2030.  You can read PJM's re-evaluation here, beginning at page 19.

If you had not stood up to PJM and delayed this project like you did, it would be built and causing problems right now.  You saved PJM's ass!

It's about time PJM acknowledged that IEC was a folly that never should never have been approved.

However, Transource has managed to spend $107.96M (that's millions, folks!) on this project, and it's going to want its money back.  That's right, we'll all get to pay Transource back for all the money it spent harassing landowners, conducting turtle hunts and netting bats, and of course all its costs to pursue appeal of the Pennsylvania Public Utility Commission's denial of a permit for this loser project.

PJM has *still* not abandoned this project.  It is still "suspended."  As long as it is suspended, ratepayers are on the hook for anything Transource spends on lawyers to pursue its appeal.  The appeal is currently before the Third Circuit.  You can read the PA PUC's brief here.

If PJM abandons IEC, then we stop paying for Transource's lawyers, but PJM has not done that.  Here's why... Transource's appeal to PA state court was unsuccessful, so it bumped it up to federal district court.  That judge found that the PA PUC's denial was unlawful because the PUC should be forced to accept PJM's determination of need for the project and was prohibited from making its own evaluation of need.  Essentially, that court decision hamstrings all state utility commissions from making their own determination of need for new transmission and makes them subservient to the RTO's findings of need for a transmission project.  It turns the PUC into a kangaroo court, where they must rubber stamp an RTO's need for a project.  This is incorrect on so many levels, but the only way to set things right again was for the PUC to appeal the district court's decision to the federal circuit court.  And that is where it currently sits.

Never mind that PJM has now found that the project isn't really needed after all, PJM wants to have the power created by that federal district court decision to usurp state authority to make the need determination required by state law going forward.

And the costs continue to rack up...

If PJM actually officially abandons IEC (instead of leaving it in a suspended state) the handouts would cease and Transource would have to proceed to FERC to have them determine how much of Transource's costs will have to be repaid by ratepayers.  When PJM ordered IEC, Transource went to FERC and asked them for a rate of return of 10.4% and special incentives for the project.  One of those incentives is what is known as the Abandonment incentive.  That incentive, granted by FERC, allows Transource to make a filing to collect all its sunk costs that are determined to be prudent in a future filing, plus the 10.4% rate of return.  Transource says it spent $107 MILLION dollars, and once PJM abandons the project, it is likely that FERC will order ratepayer reimbursement.

It's all over but the payback.

Shame on Transource for spending so much money on a project that never stood a chance of being approved!

And shame on PJM for approving this project in the first place and avoiding its ultimate abandonment!
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.