StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

How Much Does It Cost To Bury Transmission Lines?

7/22/2015

6 Comments

 
Ask a transmission developer proposing a new transmission line and you'll get an answer in the neighborhood of 10 times the cost of an overhead line.  (Example: $1B overhead = $10B buried)

Ask an engineer for a company proposing an underground project and you get an estimate that burial would double the cost of a similar overhead line.
(Example:  $1B overhead - $2B buried)

I've been told both of these things.  So, who to believe?  Who might be exaggerating to serve their own purposes?

Apparently it only does "almost double" costs to bury HVDC transmission.
  That's what the Department of Energy concluded in its recently released draft environmental impact statement on the ill-fated Northern Pass project.

A complete burial of the Northern Pass transmission line would nearly double the project’s cost, but reduce potential negative impacts on the environment, tourism and local property values, according to a draft report released by the U.S. Department of Energy Tuesday.

While the proposed Northern Pass project — made up primarily of overhead lines strung between Pittsburg, N.H., and Deerfield, N.H. — would be the cheapest option at roughly $1.02 billion, it would also pose the greatest environmental and visual impact, the report says.

Four of the alternatives call for a complete burial of the transmission line. Another calls for partial burial beneath Interstate 93 through Franconia Notch, or along Routes 112 and 116 through the White Mountain National Forrest.

Five call for burial along existing roads and highways, options with the least environmental impact, the report says. All of the underground alternatives carry the highest costs, ranging from $1.83 billion to $2.11 billion.
But nowhere near a magnitude of 10 times the cost.  Liar, liar, pants on fire!

In addition, a buried line provides significant benefits over its aerial cousin.
The visual impact, which includes “large industrial-appearing lattice structures,” could negatively impact New Hampshire’s tourism and recreation, the report says. And the proposed overhead route likely would cause the largest drop in residential property values and have the least economic tax benefit to host communities.

Putting the line underground, as opposed to overhead, lessens the impact on tourism, recreation, historic resources and the environment, the review says.

Burying the line requires less vegetation removal and has fewer effects on wildlife, including protected species. The buried lines are less susceptible than the overhead lines to damage from extreme weather.

Construction of the overhead line would generate fewer short-term and permanent jobs than an underground alternative, the report says.
But wait...
But, the report says, blasting during construction would generate more noise than putting the lines overhead. And burial of the line would increase the potential for erosion.
Really?  That's the only drawback?  Noise from blasting?  So, how much "blasting" would Clean Line need to do to bury its proposed transmission lines across Midwest farmland?  Little to none?  What if much of the additional cost of burial was tied to blasting up the "Granite State" to create trenches?  And erosion?  I think that could probably be handled.  Once buried, out of site, out of mind, right?

C'mon, Clean Line, get with the program and re-engineer your projects as underground lines!  How much have you spent (and moreover how much will you have to spend in the future) trying to get your lines permitted?  It would have been much cheaper (in terms of both money and time) to have done the smart thing and proposed your projects as buried lines in the first damned place!

And don't give me any of that crap about how its technologically impossible to bury long lines.  The engineer who gave me the spot on double cost estimate also told me there is no mileage limit.  He's got a lot more cred than you do at this point...

How much does opposition cost?  How much does buying support cost?  How much does lobbying to change laws cost?  How much are a whole bunch of contested eminent domain cases going to cost?  How much do repeat or additional approval processes cost?

Clean Line says its currently proposed transmission line will only add something like 2.5 cents per kw hour to the 2.5 cent cost of wind energy.  So, even doubling the project costs, it's still possible to deliver at 7.5 cents/kwh, right?  Well, unless Clean Line has been lying about the delivered price of wind via its projects...

Maybe Clean Line's projects won't be "economic" enough to provide big returns to their investors without foisting some of its costs off onto bypassed landowners by taking land as cheaply as possible through condemnation and eminent domain?

We all know that the public's appetite for "green" energy only stretches so far as their wallet.  When faced with increased electric bills for "green" energy, the majority of the public will snap their wallet shut and oppose it.  So, why would this same public expect that Midwest landowners should accept economic sacrifice and burden to keep urban electric bills low?  It's only appealing when its been greenwashed and politicized, and none of that nasty infrastructure gets planted in THEIR backyard!

And... this question bubbles up... why does the DOE's draft EIS for the Northern Pass include multiple routing options that require underground lines when DOE's draft EIS for the Clean Line Plains & Eastern project proposed NO underground options?  Are the people and environment of Oklahoma and Arkansas worth less than those in New Hampshire?  Or is it just that Northern Pass has gotten bigger, politically-connected, push back and top-notch legal help?

It's about time to recognize that the public will no longer accept the burden of overhead lines.  Anywhere.  There's a better way.  "Green" energy costs more.  Deal with it.
6 Comments
Joel Dyer
7/22/2015 09:58:27 pm

I don't want Clean Line crossing my property. CL wants to build an overhead transmission line across my property. A buried line would be the perfect compromise.

"Are the people and environment of Oklahoma and Arkansas worth less than those in New Hampshire? Or is it just that Northern Pass has gotten bigger, politically-connected, push back and top-notch legal help?" I think it's the second choice, but I'm not positive.

Reply
Keryn
7/22/2015 10:10:51 pm

You're absolutely right, Joel! And where does the top-notch legal help come from? The environmental community! Those same hypocrites that support the ruination of your place in the name of "green." Who will stand up for the people in Arkansas?

Reply
Joel Dyer
7/23/2015 12:32:50 am

Well. It appears the Arkansas Senators and Representations are standing up for us. That's the way it appears, but appearances can be misleading. Especially to desperate people.

Natalie
7/23/2015 01:21:00 am

Interstate 70 stretches over 660 mile of GBE's 780 mile long path (by my calculations) between Kansas and Indiana and Interstate 80 stretches across the entire states of Iowa and Indiana, the path of RICL. If these projects are so important "to the public", then bury the HVDC lines along the right of way of both these interstates where land has already been acquired and impacted. Doing this for both of these projects is a viable alternative which minimizes environmental impact and does not take land from the people who own it.

Reply
Keryn
7/23/2015 01:45:00 am

Good point, Natalie! The beneficiaries of these projects are not in the transgressed states, but in those unnamed states "east" who Clean Line speciously claims are clamoring for its project. If these consumers desire the wind transported by Clean Line, then they shall pay its true cost, not foist impact off onto Midwest landowners. If it costs more to avoid impact to transgressed states, then that's the cost of the project and shall be borne entirely by the beneficiaries, as decided by the FERC in Order No. 1000.

Reply
Natalie Locke
11/11/2015 06:37:00 pm

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.