StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Groundhog Day!  Transource is Back!

9/24/2022

0 Comments

 
Thought you were done with the Transource Independence Energy Connection when the Pennsylvania PUC denied their application to permit the project?  Thought you were done with it when Transource lost its appeal in the Commonwealth Court?

Sorry.  Even though that case has not quite exhausted its appeal in the U.S. District Court for the Middle District of Pennsylvania, and even though PJM suspended the project and removed it from its planning models, Transource has chucked that plan and resubmitted the same project in PJM's July 2022 competitive proposal window to solicit project proposals to address numerous reliability criteria violations on several flowgates in Maryland, Virginia, and Pennsylvania.

You can see Transource's new (old) proposal here. (Click to expand 2022 RTEP Window 1 at the top of the list.)  It's project number 633.  Transource describes its new proposal as:
This Proposed Solution is a resubmittal of the modified Independence Energy Connection (IEC) Project. The Proposed Solution consists of: (1) the IEC West Portion, which is comprised of approximately 29 miles of new double-circuit 230 kV AC overhead transmission line between the existing Potomac Edison Ringgold Substation in Washington County, Maryland to a new Rice Substation in Franklin County, Pennsylvania; and (2) the reconfigured IEC East Portion, which is primarily comprised of adding 230 kV AC overhead transmission lines between a new Furnace Run Substation in York County, Pennsylvania, and the existing BGE Conastone (via Baltimore County) and Graceton Substations in Harford County, Maryland.
That's right... Transource has taken its old project and resubmitted it to solve new "reliability" needs.

It's Groundhog Day!

It's not like Transource didn't already try to morph the IEC into a "reliability" project after the economic need for it evaporated during the PA PUC evidentiary hearing.  They tried really hard to find new reasons to build the same old, tired project without having to start again.  But the PA PUC rejected the idea that it could substitute a new "need" for the old one without PJM going through the whole planning cycle to determine if IEC was a good solution for the small reliability issues that may arise in the future. 

The jury is still out on that one.  When PJM suspended IEC, it noted:
Violations are small in magnitude and operating steps for a short term duration can mitigate issues pending further review in 2022 RTEP.
And now here we are... in the 2022 RTEP, where PJM has opened a competitive window for projects that would solve those "small in magnitude" reliability violations.  Transource still has to be selected as the best project submitted in the window, and approved by the PJM Board of Managers, and that hasn't happened yet.  There are plenty of other projects that have also been submitted.  Some projects are cheaper, some projects ar less invasive, some projects are more likely.  Transource's chances here are not great, but it bears watching.

Why would PJM waste another 7 years on a project that has already been rejected by a state utility commission?  And what if Transource wins its federal court appeal and the denial is remanded to the PUC?  Does that mean Transource will build the same project twice?  Seems like the more logical solution for PJM is to go with a new and different project without all IEC's baggage.  But when has PJM ever done anything logical when selecting projects?  Transource has already poured tens of millions into the IEC, and ratepayers are on the hook to pay for it, whether it is ever built or not, thanks to recovery guarantees granted by the Federal Energy Regulatory Commission.  Why would PJM encourage dumping more ratepayer money into the black hole of a project that is unlikely to ever be approved and built?  And why would PJM select a project with entrenched opposition, knowing that it would be hotly opposed from Day 1?

It seems that the good citizens of Pennsylvania and Maryland may never be free of the Transource IEC if the company keeps resubmitting the same project over and over, like a monkey flinging poop on the wall to see what sticks.  Nothing is going to stick, but it doesn't keep Transource from trying.  After all, ratepayers are on the hook for all the costs of Transource's Ground Hog Day project.

The least they could have done is rename it this time around.  How does Transource Groundhog Day Project sound?
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.