StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

GBE Won't Commit to its Project

12/11/2022

0 Comments

 
Picture
If you're a person in the Grain Belt Express target zone who is currently being harangued and pursued to sign an easement, or perhaps a utility regulator being told that GBE is a sure thing, you might find this interesting.

About a month ago, Invenergy filed with FERC a "Request of Grain Belt Express LLC for Prospective Tariff Waiver, Expedited Action, and Shortened Comment Period."

The gist of this filing is that MISO has tendered an interconnection agreement for GBE and Invenergy only has 60 days to negotiate and sign it, or to file it unsigned.  GBE's negotiation period ends December 31.  GBE wants FERC to grant a waiver so that Invenergy can wait until some time next year to sign the agreement and make two large deposits for the transmission upgrades its GBE project will cause.

GBE has applied at MISO for both interconnection of its project and injection rights.  Interconnection and injection rights are two separate things.  Interconnection allows GBE to connect to MISO's existing system, but injection rights allows GBE to inject a certain amount of electricity into MISO at the interconnection site.  Both the interconnection and injection rights require MISO study to identify and plan any upgrades to the system that they will cause.  Interconnection and injection rights run on two different study tracks.  MISO determined that GBE's interconnection will require approximately $144,248,000 worth of work to the existing system to support the interconnection.  However, MISO has not yet completed the study that will determine the cost of the injection rights work, although GBE estimates it will be an additional more than $177 million.  GBE wants to know the injection rights number before it negotiates and signs the interconnection agreement, because once it signs the agreement it is obligated to make non-refundable deposits totaling approximately $77 million before it knows the injection rights number.

Let that sink in... Invenergy doesn't want to spend money on a project without knowing its full cost.  As Invenergy puts it
Otherwise, GBX will be placed in the position of having to decide whether to commit millions of dollars in security or cash pursuant to the executed TCA before it understands its total upgrade cost exposure associated with the Injection Rights.
This would have absolutely no relevance if there was not the possibility that Invenergy would cancel this project if the injection rights end up costing too much.  If Invenergy is going to proceed with GBE no matter how much injection rights cost, then the deposits don't matter.  The deposits would only represent a loss for Invenergy if it cancelled the project.

Apparently Invenergy is not going to know whether its project is going to proceed until at least the end of April, 2023.  But yet there are reports that Invenergy is filing eminent domain suits and taking landowners to court.  And, of course, Invenergy is pushing state regulators to approve its project in a big ol' hurry, even though Invenergy wants another 5 months to decide if its even going to proceed with interconnection to the existing transmission system (and that's if MISO's study gets completed on time, which in these days of clogged interconnection queues may not happen). 

Invenergy says having to put up cash as surety for its project is "too risky" for the company but taking your land via eminent domain isn't risky at all for Invenergy.  It's all about who bears the real risk, isn't it?
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.