FERC's Transmission Incentives - The Role of Cost Estimates

7/5/2011

0 Comments

 
In the NOI, Promoting Transmission Investment Through Pricing Reform, FERC is seeking comments about the effect of its incentives on promoting transmission.  If you're going to comment, you need to understand what the incentives are, and what they are intended to do.

We all know about budgets.  People live within their own financial comfort zone, and even corporations and governments must operate within certain set budgets (no, we're not starting a political debate!)  Failure to stay within budget causes personal financial problems, and in the case of corporations and governments, failure to stay within budget can turn a project into financial disaster.  Imagine a product that costs more to make than can be recouped through sale.  You wouldn't stay in business long if you were unable to properly budget.

FERC believes that transmission projects that receive incentives should not be limited by a budget.  In FERC's world, the cost of a project will never outweigh its benefits to consumers.  This is unrealistic because there is always a tipping point when the cost becomes greater than the benefit.  Now FERC ponders if there is a role for cost estimates in their transmission incentives policy.  However, they worry that limiting incentives to original budgeted amounts could be punitive when escalating costs are beyond the control of the transmission owner. 

FERC is under the assumption that the regional planning process places some weight on cost estimates when evaluating projects.  During the PATH battle, we have heard that there is no price too high at which point building PATH would become uneconomical.  The cost of PATH played no role in PJM's selection and stubborn loyalty to this project, even when faced with less costly alternatives, such as the Liberty Line and Dominion's Alternative One.  In fact, PJM went so far as to evaluate the cost of the Liberty Line in a biased manner that created a conflict of interest, in order to make the cost of PATH appear "economical".  We know that PJM is incapable of rationally utilizing cost estimates in selection of projects.  FERC gives them way too much undeserved credit.

FERC should limit transmission incentives to budgeted amounts only.  Their current system encourages unbridled spending because the more the project costs, the greater the financial reward for the transmission owner.  A project should be re-evaluated if cost estimates change.  FERC needs to remember the consumer whose cost of delivered power is being reduced by the transmission project because there will come a point at which project costs actually increase, instead of reduce, the consumer's cost of delivered power.

Now that you've contemplated the role of cost estimates, go look at FERC's questions beginning on page 21 of the NOI and formulate your comments/suggestions for FERC.  I'm sure you creative consumer "stakeholders" can make suggestions that the industry won't even ponder.  The industry will be letting FERC know how they can and should sweeten the pot even further for them.  It's up to you to provide balance with a little real world sanity.

If you found this helpful in crafting your comments, you are encouraged to browse the entire FERC Transmission NOI category at StopPATHwv.com for other useful material.  You don't have to comment on all aspects of the NOI if that's too burdensome.  In fact, if you want to concentrate in detail on just one aspect that interests you and about which you have strong feelings, that's a perfectly acceptable approach to producing effective comments.

0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.