StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

FERC Transmission Incentives - Evaluating Existing Incentives

4/30/2019

0 Comments

 
Here's where FERC should have started with its transmission incentives review, except it got so excited by proposals for new incentives, the existing incentives ended up at the back of the rack as a mere afterthought.  While not as exciting as FERC's proposals for new incentives, these still require a look because they are the source for all the "FERC candy" comments, and have driven many bad transmission ideas that are bankrupting consumers and causing increased opposition to bad projects.

ROE Adders for Transmission Only Companies:  This incentive adds 50 points to a transmission company's return on equity.  In people-speak, that equates to an additional half a percent of interest on a company's rate base.  Rate base is the cost of projects that have not yet been repaid by consumers.  When a project is completed, its total cost goes into the rate base and it is repaid to the transmission owner over the useful life of the asset (approximately 40 years for transmission).  With transmission projects costing multiple billions, that extra half a percent interest on a balance that slowly depreciates over 40 years can add up to big bucks.  So, the Commission wanted to give an incentive to independent transmission owners, who perhaps it felt needed a leg up to compete with incumbent utilities.  Independent transcos also should not have any interest in generation or distribution companies that may cloud their thinking about what to build, nor compete for parent company investment dollars.  Sounds good on the surface, but guess what happened when FERC put this into practice?  Suddenly all the incumbents created spin-off companies that were supposedly "independent" in order to win that extra interest.  These spin-offs enjoy parent company benefits, such as being able to borrow money at a low rate to finance the project, then collect extra interest on their borrowed "equity."  If a parent can borrow at 3%, then use that money to inject "equity" into their transmission-only spin-off, they can earn maybe 10% (or more) on that money, while only having to re-pay the loan at 3%.  That extra 7% is gravy for the parent company.
Q 57) Does the Transco business model continue to provide sufficient benefits to merit transmission incentives? What information should an entity seeking a Transco incentive provide to demonstrate sufficient benefits?

Q 58) Should the Transco incentive remain available to Transcos that are affiliated with a market participant? If so, how should the Commission evaluate whether a Transco is sufficiently independent to merit an incentive?

Q 59) Should a Transco incentive be awarded on a project-by-project basis?

Q 60) Should the Transco incentive exclude assets that a Transco buys, rather than develops?

Another gravy-maker is the RTO/ISO membership incentive.  Sec. 219 tasked FERC with developing incentives for transmission companies that JOIN an RTO/ISO, figuring that membership provided benefits to consumers.  Can't change this now, it's in Sec. 219.  The incentive FERC developed for this instance was another 50 points on the ROE.  However, FERC interpreted Sec. 219 incorrectly in order to award the incentive to every transmission company that IS a member of an RTO/ISO.  Therefore, companies that have been members for years are routinely awarded that extra interest just for maintaining their membership, something they were most likely going to do anyways.  Providing extra interest isn't going to make or break RTO membership, except maybe in the case of a new entrant.  In addition, the incentive may be awarded to multiple spin-offs and projects of the same parent company, based on one membership.  The incentives for continued membership simply have to stop.  It's a misinterpretation of Sec. 219 that costs consumers billions they wouldn't spend otherwise.

Q 61) Should the Commission revise the RTO-participation incentive?

Q 62) Should the Commission consider providing incentives other than ROE adders for utilities that join RTO/ISOs, such as the automatic provision of CWIP in rate base or the abandoned plant incentive for all transmission-owning members of an RTO/ISO? If so, what other types of incentives would be appropriate?

Q 63) If the Commission continues to provide ROE adders for RTO/ISO participation, what is an appropriate level for an ROE adder?

Q 64) Should the RTO-participation incentive be awarded for a fixed period of time after a transmission owner joins an RTO or ISO?

Q 65) Should the RTO-participation adder be awarded on a project-specific basis?

Q 66) In Order No. 679, the Commission found that “the basis for the incentive is a recognition that benefits flow from membership in such organizations and the fact that continuing membership is generally voluntary.”
Should voluntary participation remain a requirement for receiving RTO/ISO incentives?
Transmission companies can also request an additional 50 points for using "advanced technology" in their transmission project.  However, requests for this incentive have been few and far between.  What exactly defines "advanced technology," and for what period of time is this technology actually "advanced" before it becomes routine?  FERC created an impossible task of defining "advanced technology," and besides, transmission owners are a pretty staid bunch, preferring to use "technology" that would be recognized by Thomas Edison.  More Tesla, less Edison.
Q 67) Why have few transmission developers sought transmission incentives for the adoption of advanced technology?
Q 68) Do NERC reliability standards affect the willingness of transmission developers to enhance existing transmission facilities by deploying new technologies because of concerns these technologies may increase the risk of standards violations?
Q 69) Are there any types of transmission incentives that could better encourage deployment of new technologies? If so, please describe them.

Now let's move on to the non-ROE incentives, incentives that do other financial things other than increase a transmission owners' ROE.

FERC's jammed several things into a topic called "Regulatory Asset/Deferred Recovery of Pre-Commercial Costs and CWIP".  Pre-Commercial costs consist of a company's expenses that happen before FERC grants incentives and recovery of a transmission project's costs.  So, that could include everything from the moment some transmission genius rolls out of bed with an idea for a new transmission proposal, and FERC rate approval (including all costs to seek that approval in the first place).  This incentive allows the company to recover all these costs, plus interest, from consumers, generally over the first 5 years of rate recovery. 

CWIP stands for "Construction Work In Progress," which is basically a holding account for the capital costs of building a transmission project.  FERC's CWIP in Rate Base incentive allows the company to include its CWIP account in the Rate Base number upon which it earns a yearly return.  Even though a transmission project has not yet been built, or completed, a company can earn a return on its investment.  CWIP doesn't depreciate because the project has not yet gone in service, so this balance continually builds until the project's in service date, then it begins depreciating.

It's helpful to think of transmission finance sort of like a home mortgage you're familiar with.  ROE is interest, and depreciation is principal.  You pay interest for 30 years while your principal is slowly paid off during the term of the loan.

FERC doesn't ask many questions about these combined incentives... perhaps because they don't intend to change them at all, just expand them?

Q 70) Should the Commission continue to provide regulatory asset treatment and CWIP as incentives? Should these incentives be granted automatically to certain types of transmission projects? If so, how would the Commission determine what types of transmission projects?
Q 71) Should the costs of unsuccessful Order No. 1000 proposals be recoverable through regulatory asset and deferred pre-commercial cost recovery incentives? If so, what costs are appropriate for recovery?

Hypothetical Capital Structure -- Since rate setting begins before a transmission project is built and operational (remember, that guy rolling out of bed with an idea), FERC must set a capital structure long before it actually happens.  It's hypothetical.  A transmission owner's capital structure determines how much of the cost of the project is equity (money contributed or invested by the company out of its own funds) and how much is debt (money borrowed by the transmission owner to use to build the project).  Defining this is necessary because equity earns the "Return on Equity" or ROE interest rate set by FERC, and debt earns at the rate the money is borrowed.  Since the transmission company probably hasn't even borrowed the money, or set any real capital structure when rates begin, FERC has to guesstimate.  A basic rule of thumb is that 50% of the cost of the project will be equity, and 50% will be debt.  That is, half of the rate base earns at ROE rate, and half earns at debt rate.  However, a transmission owner may request a different split of equity/debt, such as 60% equity to 40% debt.  Obviously, this capital structure makes more money, right?  FERC can grant an incentive allowing return at this higher rate before actual capital structure is set by the borrowing of money.

Q 72) Should the Commission continue to utilize hypothetical capital structures as a transmission incentive? If so, what entities should be eligible to apply for a hypothetical capital structure?
Q 73) Have hypothetical capital structures been effective in reducing the overall cost of debt by rendering the capital structure more predictable? Q 74) In what circumstances, if any, should hypothetical capital structure incentives granted to an entity also be authorized for that entity’s yet-to-be formed affiliates?
Q 75) Under what circumstances, if any, should hypothetical capital structures extend beyond the construction period?
Q 76) Should the Commission provide a consistent hypothetical structure (e.g., 50 percent debt and 50 percent equity)? Alternatively, should the Commission cap the equity percentage at some upper limit (e.g., 50 percent)?

Abandoned plant incentive.  This one is a particularly bitter pill for ratepayers to swallow, where they end up paying for a transmission project that never actually gets built... and we're talking in the hundreds of millions of dollars, plus ROE over a set recovery period.  FERC's abandoned plant incentive guarantees that the transmission owner can recover its sunk costs if the transmission project is cancelled through no fault of its owner.  How does this happen?  When a project is "ordered" by an RTO/ISO and later found not to be needed at all.  This should be a very rare occurrence, but it's not.  It's happening with more frequency, as RTOs stick their necks out ordering the unneeded projects proposed by their members.  What happens to unneeded projects?  They're opposed by affected communities.  And what happens if the opposition is successful (and this also is happening with more frequency)?  The project does not receive state siting and permitting approvals and is cancelled by the RTO, causing the transmission owner to abandon its project through no fault of its own.  Nobody's at fault, nothing to see, pay the money and let's move on.  What???  The only way to stop the proposal of bad projects is to make their owners responsible for their own failure.  Instead, FERC makes ratepayers responsible for the faults of transmission owners and RTOs, when the ratepayers have been the voice of reason all along.  This is truly absurd.

Q 77) Should the Commission grant the abandoned plant incentive automatically, rather than on a case-by-case basis? Under what circumstances might an automatic award of the abandoned plant incentive be appropriate?
Q 78) How, if at all, could the Commission grant the abandoned plant incentive without encouraging transmission developers to pursue unnecessarily risky transmission projects or take unnecessary risks in transmission development? Could such behavior be reduced if the developer shared some risk associated with the abandonment, e.g., 10 percent of abandonment costs? If so, what level of developer risk is appropriate?
Q 79) How should the Commission evaluate whether the costs of an abandoned facility were prudently incurred?

Accelerated depreciation -- Essentially, this allows the transmission owner to recover its costs quicker than the traditionally used "life of the project."  If a transmission line is supposed to last 40 years, then its total cost is broken down into re-payment over 40 years (plus interest).  Each component of a transmission project has a determined "life" of how long it's supposed to last before needing replacement.  This sets a transmission line's depreciation schedule, the rate at which principal is paid back.  But say a transmission owner wanted to recover the cost of a 40-year transmission line over a period of 20 years?  Sure, the transmission owner would get its money back faster, but it would earn a lot less interest.  This incentive has never been popular.  Can you guess why?

Q 80) Should the Commission continue to consider accelerated depreciation as an incentive?
Q 81) Does the accelerated deprecation incentive provide meaningful benefits to transmission developers?
Q 82) Should the Commission grant an accelerated depreciation incentive with a generic depreciation period or continue to determine such a period on a case-by-case basis?

For the last in this series, we'll tackle the dregs of FERC's inquiry -- the mechanics and implementation of incentives.  Coming soon....
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.