FERC Stubbornly Clings to PJM Postage Stamp Rate Scheme

3/29/2013

0 Comments

 
FERC issued a whole bunch of interesting decisions at its meeting last week.  Unfortunately, I've been too busy over the last week writing FERCenese* to spend much time reading it.

Finally, here's your first FERCenese translation from last week about FERC's Order on Rehearing regarding postage stamp rates in PJM.

Not surprisingly, FERC reconfirmed it's original Order on Remand and brushed off all the arguments made by parties in their requests for rehearing.  The Commission continues to cling to its illogical presumption that “When a system is integrated, any system enhancements are presumed to benefit the entire system.”

Also not surprisingly, Commissioner LaFleur dissented (again).  However, joining her in dissenting this time around was the newest addition to the FERC stable, Commissioner Tony Clark.

Both dissenting Commissioners mentioned that FERC is reaching by assigning PJM "system wide benefits" to "Western PJM" entities like ComEd in exchange for bearing 14.7% of the costs.  These "system wide benefits" accrue from membership in PJM, and not from construction of the subject transmission projects.  Commissioner Clark also opined that FERC has fallen short of the 7th Circuit's directive in remanding the case back to FERC.

Although I usually encourage you all to read these filings yourself, this Order is a real deja vu snoozer that doesn't say anything new.  Everything you need to know is contained in the dissents.

Commissioner LaFleur's Dissent

Commissioner Clark's Dissent

The only thing different this time around is that a new cost allocation process for PJM transmission projects has been approved as part of PJM's Order No. 1000 compliance.  The new cost allocation method became effective February 1, 2013.  Therefore, this Order on Rehearing affects only a specific set of transmission projects approved between June 20, 2006 and February 1, 2013 (aka The Project Mountaineer Era).  These projects (TrAIL, Susquehanna Roseland and the dearly-departed, abandoned PATH and MAPP) will continue to be allocated and paid for by the postage stamp rate methodology that has been decided in this Order.

PJM's new cost allocation methodology will allocate 50% of the cost of transmission 345kV and over by postage stamp methods, with the remaining 50% allocated via a DFAX methodology, which more accurately assigns costs to those who cause them and to those who receive current benefits from the project.  (More on that in a future FERCenese translation).

So, while "Western PJM" will continue to pay an equal share of 500kV+ Project Mountaineer lines that are exclusive to the east coast, the current 345kV expansion going on in "Western PJM" (where they don't build 500kV lines) won't be allocated to "Eastern PJM" in the same proportions.  Sound fair to you?

FERC reasons that since this postage stamp business now applies only to a finite, historical set of projects that this decision will put the matter to rest.

Probably not.  The parties can now bump it back to the 7th Circuit.

And, curiously enough, the Illinois Attorney General intervened out of time in the PATH abandonment docket today.... because now Illinois is going to be stuck paying 14.7% of PATH's abandonment costs.  Coincidence?
*FERCenese:  [fur ken ees] noun 
Style of technical, legal prose utilized in filings and orders at the Federal Energy Regulatory Commission.  To the average layperson, the filings appear to be written in a language other than the familiar English.  The Scott Thorsen Dictionary, 2013.
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.