StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Feeding the Big Green Beast

10/19/2020

0 Comments

 
Picture
No, not him!  Although communities invaded by this big, green beast often feel like he's been rampaging in their neighborhood.  I'm talking about the "renewable energy" big, green beast.  The beast that's currently fat with tax credit cash paid for by you.  Ever heard the old saying about not feeding stray pests because they keep hanging around expecting a meal?  Well, that's just what renewable energy developers are doing now.  Because taxpayers have financed the construction of their wind farms through tax credits, now the developers want electric ratepayers to finance their costs to transmit their product as well.

What's the problem?  Traditionally, a new generator must pay its costs to interconnect to the existing transmission system.  This includes any new lines from the generator to an existing transmission line, plus any upgrades or new transmission caused by the new injection of additional power to the system.  Say the interconnection of 4,000 MW of wind from Guymon, OK to Indiana causes the need to build a brand new 765kV transmission line in Indiana in order to handle the additional load... the generator in Guymon would have to pay for the upgrade.  Does that sound fair to you?  Let's examine...

The generator at Guymon is producing power for export and expecting a huge profit because its cost to produce is extremely low and the price of power purchased in Indiana is extremely high.  But did anyone in Indiana contract to purchase this power, plus the cost of transmission?  No, they didn't, so the generator proposes that the cost of the transmission upgrades be paid for by electric customers in Indiana, who may or may not use the power transmitted over the new line.  Long-standing rules for transmission cost allocation -- beneficiary pays.  So, unless Guymon can prove that all the ratepayers receive a benefit, they cannot assign costs this way.

In addition, who says the Guymon generation is needed in Indiana or elsewhere?  It's the regional transmission organization that orders new transmission to be built and assigns costs to ratepayers.  The RTO can only order new transmission and assign costs for projects needed for reliability, economic, or public policy purposes.  If that need isn't there (and it's not... the PJM RTO has not ordered nor accepted costs for transmission for import) then it will not order a new project and assign costs.  Generators and renewable energy developers do not order projects, assign costs, and determine who must buy their power.  Claiming that the power they generate in Guymon is "desperately needed" in NYC and therefore ratepayers in Oklahoma City should pay for new transmission to get it there is a bridge too far.  Who decides where the power they buy comes from?  The purchaser, and to some extent the state.  State energy policy may call for wholesale purchasers (the company who supplies your power) to purchase a certain amount of renewable power.  That does not mean, however, that the state has demanded renewables from Guymon.  States are getting smart about energy and many who have set renewable mandates know exactly where the power should come from... and it's from new renewables in state or in the local region.  Not one state has set a target that it expects to have fulfilled by generators thousands of miles away.  Go on with your stupid "where it's needed" claims.  It's not up to renewable developers to determine where their power is "needed."

And let's not forget the logic of economics.  New generators are for-profit endeavors.  The cost to construct, connect, and operate must be less than the price the generator can charge for power.  If these costs are more than the value of the power produced, then the generator is not economic and won't be built because nobody builds a new business that it expects would lose money.  So, in this recent article, generators are whining that the cost of transmission interconnection and upgrade is too much and causes the cancellation of their projects because it makes them uneconomic.  But yet they want ratepayers to pick up their interconnection and upgrade costs so that their uneconomic generators suddenly become economic.  Let's not avoid the elephant in the room...

IF IT'S TOO EXPENSIVE FOR GENERATORS TO OPERATE ECONOMICALLY, IT'S TOO EXPENSIVE FOR RATEPAYERS TO PAY FOR ECONOMICALLY!

The ratepayers would pay for it either way, of course, whether wrapped into the cost of the power from Guymon, or secretly added to their bill in the form of higher transmission cost.  However, when it's presented as high-cost power from Guymon, wholesale buyers say "no."  But when it's slipped into everyone's electric bill without notice, they have no opportunity to say "no."

Perhaps this is also another Trojan Horse... by trying to foist their interconnection costs onto regional ratepayers who won't benefit from the new transmission, are renewable developers looking to have their merchant projects become RTO-ordered projects so they can be cost allocated?  Currently merchant projects are paid for by their owners.  So, what would happen to a merchant project that wanted to connect?  Should an RTO anticipate merchant projects and plan for them?  Get outta here... that's ridiculous! 

Energy decisions are made by elected officials, state utility commissions, and customers.  They aren't made by corporations who want to make money selling energy.
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.