Double Jeopardy!

8/23/2025

2 Comments

 
PJM Interconnection, our regional grid operator and planner, is always planning something.  PJM regularly presents problem statements to transmission developers and solicits proposed solutions as part of a competitive transmission process.  Each RFP for transmission solutions is called a "window".  PJM presents its problem statement, and willing developers submit proposed solutions.  PJM's competitive transmission windows are what brought us the MARL, Gore-Doubs-Goose Creek, and Valley Link projects.

Once the open "window" closes, developers submissions are posted on PJM's website with a lot of "competitive" information redacted so that only a skeleton of the proposal is available to the public.  These bare bones proposals are turned into maps and tables that PJM's Transmission Expansion Advisory Committee (TEAC) discusses at its monthly meetings with the goal of selecting one of more of the proposals to address the problem PJM described.  The discussion and selection usually takes place over the course of several months, and once PJM's TEAC has selected a project or projects, it must read them into the record twice at committee meetings before submitting them to PJM's Board of Managers for approval.  If PJM's Board of Managers approves the new projects, they are added to PJM's Regional Transmission Expansion Plan (RTEP) and assigned to their transmission developer sponsors.  PJM signs what's called a Designated Entity Agreement (DEA) with the developer and the developer begins routing and engineering studies and eventual public information sessions that they call "Open House" meetings.  This is the exact process that MARL, GDGC and Valley Link have followed.

PJM opened a new competitive window in June of this year to solve a number of problems with the transmission system.  The main problem, as always, is that Northern Virginia demand is skyrocketing due to new data center proposals.  You can look at the factors PJM was considering by reviewing PJM's TEAC meeting slides from last month.  PJM said that some of the lines bringing power from the west would be overloaded in 2032.  Here's one of their maps.
Picture
I will share that PJM's meetings and information are high on the techno-speak level and may appear confusing to most people.

PJM's 2025 Window 1 closed on August 18.  PJM received many new transmission proposals.  Not all proposals submitted will ultimately be selected.  However, we have a first look at what has been proposed so that we can follow PJM's evaluation of these proposals and selection of the projects it wants to move forward.  Here's the full list of proposed projects (expand the 2025 RTEP Window 1 link).  They are simply referred to by number, and each number has a brief description of the project, with much of the specific information redacted to protect competitive information.  The name of the proposer is always redacted, however there's much we can garner out of the information that is not redacted that gives us clues about who may have proposed them.

One of the proposed projects is numbered 896.  This proposal, which may have been made by FirstEnergy or NextEra, calls for turning MARL into a double circuit 500kV transmission line, and adding a second 500kV line to the first segment of GDGC across Frederick County, Virginia.

The proposed MARL double circuit begins at FirstEnergy's Fort Martin power station in Morgantown, WV.
Convert the 500kV single circuit 502 Junction - Woodside 500kV project under development (PJM Baseline Upgrade ID b3800.102) to a double circuit configuration between Fort Martin and the NEETMA/APS interconnection point in Frederick County, VA, to accommodate Circuit 1 (b3800.102: 502 Junction – Black Oak – Woodside 500kV) and Circuit 2 (Fort Martin – Sandy Creek – Woodside 500kV).
The project calls for a new 138kV line from Ft. Martin to a new substation in Mon County that would be called Sandy Creek.  The proposed Sandy Creek substation will intersect with MARL and feed power directly from Ft. Martin to the new 500kV circuit proposed to be added to the MARL project.  The Sandy Creek substation is described:
AC Air Insulated Substation (AIS): New proposed 500-138kV Substation. New 500kV ring switchyard with three (3) line terminals, three (3) 500kV, 5000A, 63kAIC breakers, one (1) 500-138kV, 485 MVA transformer bank.
The new 500kV circuit will be added to MARL's proposed towers so that MARL would consist of TWO 500kV transmission lines, possibly hanging from the same new tower.  The proposer says this doesn't make any difference because MARL has not been constructed yet so they can change the towers and the circuits.
Approved 502 Junction - Woodside 500 kV project (PJM Baseline Upgrade ID b3800.102) has not been constructed so no existing hardware will be impacted.
​The entire circuit shall be upgraded to a double circuit from a single circuit from the point where the Fort Martin - Sandy Creek circuit joins the 502 Junction - Black Oak circuit until the point at which the Sandy Creek - Woodside circuit transitions to single circuit towers. 
This includes the entire portion of MARL from a point in Mon County to the place in Frederick County, Virginia where the MARL project ends and the Gore-Doubs-Goose Creek project begins.  It would impact Mon, Preston, Garrett, Allegany, Mineral and Hampshire Counties.  The proposer says it will use "existing right-of-way" but that right-of-way doesn't actually exist yet and will only exist if MARL is approved and built.  It only exists on paper right now because NextEra has not actually obtained any right-of-way for the MARL project in those counties yet.  Talk about counting your chickens before they hatch, right?
​Existing right-of-way to be used for upgrading the single circuit to a double circuit. ROW Adjustments may be required in specific locations to mitigate engineering and/or operational risks.
Once this new double circuit 500kV line gets to the demarcation point between MARL and GDGC in Frederick County, Virginia, it proposes to run on a new 200 foot right of way for 17 miles across Frederick County until it reaches the proposed Woodside substation owned by NextEra.
The approximately 17-mile route in Frederick County, Virginia travels eastward from the MARL NEET/FE handoff, paralleling the existing Mt. Storm to Doubs 500kV corridor where feasible. The route will have a 200 ft ROW width. The proposed ROW will be an expansion of existing transmission line corridors for approximately 20% of the route length, the remainder will be greenfield ROW.
They can't simply continue the double circuit on the same new towers when they get to Frederick County because that is the point where the Gore-Doubs-Goose Creek line is already planned to be constructed as a double circuit with the existing 138kV line.  The second 500kV circuit would need a whole new right-of-way parallel to the existing configuration.  And don't forget that Valley Link is coming along behind it and creating its own new 200 ft. right-of-way.  Frederick County is looking at not only the new 185 ft. tower for the first 500kV circuit, but the addition of two new lines on parallel rights-of-way that would add 400 feet to the existing 250 foot wide corridor.  Total if this is selected and completed:  650 feet wide right-of-way with three 500 kV lines, one 138kV line, and one 765kV line.  That's a whole lot of power and a whole lot of expansion for Frederick County!
Meanwhile, back in Mon County, Fort Martin's substation must expand for this plan.
Expand the existing 500kV double breaker double bus (DBDB) switchyard by adding (2) 500kV breakers to create (1) new bay with (1) new line position. Replace (9) existing 500kV breakers.
Assumes that fence line must be expanded to west to accommodate upgrades. 
Based on publicly available parcel data and imagery, upgrades are expected to fit on transmission-owner owned property.
The new line from Fort Martin to the new Sandy Creek substation will be constructed for approximately 1-mile and parallels the Hazelton to Lake Lynn 138 kV in Mon County on a proposed new 100 ft. right-of-way.  A second new 138kV line from a nearby substation will also parallel Hazelton to Lake Lynn for an additional 2 miles of new 100 ft. right-of-way.  That's three miles of new right of way in Mon County, and a new substation.

Seems like double jeopardy for impacted landowners, doesn't it?  As if it's not bad enough that MARL is proposed for your property, now the transmission companies want to double your pain with a second 500kV circuit and miles of new right-of-way, and a new substation, in Mon County and Frederick County.

For what?  To get power to data centers in Northern Virginia.

It really emphasizes the fact that these new transmission lines are NOT for West Virginia, and they are NOT needed to attract new data centers in the West Virginia counties they cross.  They are for Northern Virginia data centers, they are not for us!

PJM's TEAC meetings are open to all "stakeholders".  We are all stakeholders in this and anyone may attend the TEAC meetings where these projects are discussed to ask questions or make comments.  PJM TEAC meetings are held once a month, during the work day, and may be attended via Webex or over the telephone.  If you want to attend, you can sign up on PJM's website.  You must have a PJM account and pre-register for the meetings.  If that's not your cup of tea, you can simply get updates from citizens who regularly attend these meetings and save your written comments for PJM's Board of Managers if this proposal is ultimately selected by PJM's TEAC.

Remember, this is only a proposal right now and there is no guarantee it will be selected.  However, MARL and Valley Link were once only just proposals like this, so consider this a heads up on what PJM may be cooking up to invade your community in the future.

Transmission extension cords from West Virginia will never be enough for Virginia's insatiable appetite for electricity and it is expected that PJM's planners will keep adding more and more unless West Virginia stands up and says NO.  
2 Comments
Gary Bradfield
8/24/2025 08:18:28 am

I believe Northern Va. should build their own power supplies in Va. and NOT push costs, higher fees on Rural States!!!!!!

Reply
Mary Ann Emery
8/25/2025 02:27:13 pm

Exactly Where does it cut through Morgantown?

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.