Digging Into MPRP

7/11/2024

2 Comments

 
Picture
Get your hip waders, folks, it's going to get deep in here!

Last night I attended the MPRP "Open House" in Brunswick.  It made the guy from Assedo pretty nervous that we wouldn't sign in and give them our information, but he said we were welcome to look around.  So, I did.  I think maybe he changed his mind later when he spied us chatting with the reporter from Fox because he found it so intriguing he needed to document it with photographs.  I saw you, dude.  Somehow, I don't think PSEG is going to be using those photos for public relations purposes.

MPRP's "Open House" was right out of the utility playbook.  Free food and beverage, free tchotchkes, and plenty of free propaganda from subject matter "experts" that sometimes couldn't stay within their specialties.  Most of them were very nice, heck, they're just doing a job.  A couple were quite snotty when they realized I knew they were blowing smoke.  And I got so far under the PJM guy's skin that he started "m'am"-ing me.  The sickest part of these open house meetings to me is always the Indoctrination Station for the kiddos.
Picture
Don't leave your kids here coloring propaganda under the watchful eye of strangers.

The first stop was the table with the PJM guy.  Stu Widom had lots of helpful information, but didn't know much about the actual planning process, and it showed.  Got himself all tweaked when I mentioned the precedent PJM has recently set by changing the route of a different project so it doesn't affect wealthy and politically connected people in Virginia's wine and horse country.  Why don't you ask Stu about that tonight?  He likes to pretend that it was for "environmental reasons" but it was nothing of the sort!  The new route crosses the C&O Canal NHP TWICE.  Environmental my foot.  Of course, poking the rich and powerful might affect Stu's own personal environment as one of PJM's political schmoozers, so maybe that's what he meant?  He obviously wasn't there to talk with citizens, but to use his bee smoker on any angry legislators or government officials who showed up.

Next I talked to one of the land agent ladies, who pretended that's not what she was.  I asked her when they were going to release the land agents on the citizens impacted by this project and she acted all confused.  I asked her if land agents would be calling on people BEFORE or AFTER the Maryland Public Service Commission approves this project.  She assured me land agents would only contact you AFTER the MD PSC approves.  We both knew she was full of it, and my investigation of regulatory filings this morning confirms
The Project is a greenfield project for most of the project route, which poses uncertainty and risk. With an in-service date of June 1, 2027, the Project faces an aggressive timeline to execute and complete all construction activities. The Project must manage ROW permitting and land acquisition risks associated with the greenfield line routes in a compressed period of time. For instance, PSEG RT will need to obtain ROWs, rights-of-entry, easements, and temporary access agreements, and in these efforts, may encounter local opposition from landowners. 
Busted!  Those land agents will be on your doorstep as soon as the routing is completed in September.

Next was one of the routing guys who told me this project was needed to supply electricity to the local area.  I told him he was wrong, then he admitted that he wasn't the subject matter expert on that.  He suggested I go over to Stu's table to find the answer to that question.  I said I'd already been there and maybe HE should go talk to Stu.  He refused, so I suggested that he not lie to people about that anymore,

I talked with a delightful young lady at the structure/electrical engineering poster.  She showed me the selected H-frame structures and told me the poles were 40 feet apart and that it would be possible to drive farm equipment between them.  I asked her what happens if someone tried that and accidentally clipped one of the poles and it fell over.  Who would be liable?  She didn't know.  I didn't suggest that she volunteer for a farm machinery rodeo, where the power company person stands in a field with their arms outstretched and pretends to be a transmission tower while farmers see how close they can drive their gigantic pieces of equipment to the "tower" without knocking it over.

I talked with another routing lady who confirmed that paralleling existing transmission lines can actually be MORE destructive than cutting new greenfield lines.  We talked about how homes and other structures are often sited right outside transmission rights of way that have existed for decades.  Paralleling that corridor with a new 150-ft wide easement would destroy everything adjacent to the existing corridor.  She said MPRP would go around homes rather than over or through them, but had to minimize how many times its line crossed the existing line.  There was also a problem where a home stood on either side of the existing easement, preventing expansion on either side.  She didn't know what MPRP would do in that instance.  One of those homes would have to be sacrificed, that's what.  Whichever side of the existing easement has more homes wins.  However, when MPRP uses new easements, it can go around any home or other obstruction and won't have to destroy anyone's home.

And finally, I talked with PSEG's staff lawyer, who happened to be sitting at Stu's table.
Picture
Very nice person who pretty much told the truth and had the answers to my rather unique questions.  She admitted that perhaps some of the other "experts" at the meeting may be making crap up and she had asked them not to do that.  I grilled her on PSEG's federal regulatory filings and cost recovery system.  This morning I found the documents and they mostly confirmed what she told me. 

​PSEG has applied at the Federal Energy Regulatory Commission to be granted three transmission incentives.  The first is the Abandoned Plant Incentive.  If granted, PSEG would be able to recover all its prudent expenditures on MPRP in the event that it is abandoned before being built through no fault of PSEG.  This would include if cannot get the permits it needs, or if PJM's need for the project changes.  The second is to set a preliminary debt/equity ratio of 55/45%.  This isn't anything to get concerned about.  The third incentive is recovery of PSEG's expenses related to this project once the project has an approved formula rate.  PSEG's initial expenditures will be recovered over a 5-year period once it has a recovery method.  This means that all the money PSEG has spent preparing this project for PJM, ushering it through PJM's competitive process, it's legal costs to make those FERC filings, the cost of all its contractors (routing, engineering, land acquisition, public relations), the food, the coloring books, even those cute little hardhat flashlight keychains (be sure to get one!).  Everything PSEG has already spent will end up added to ratepayer bills once it has its formula rate established.  The one made up fib the lawyer told was that PSEG was paying for all the current costs of the project out of the goodness of their hearts.  I hope she knew as well as I did that those costs were being put in an account as a regulatory asset that would be recovered (with interest) at a later date.

First, PSEG is waiting for FERC to approve its incentives.  Afterwards, PSEG will file for approval of its formula rate and rate of return.  Bet your eyes glazed over just then, right?  Stick with me here...  A formula rate is a set of tables that calculate a yearly rate based on numbers that the transmission company plugs in from their ledger.  As things are paid for, the costs get added to certain accounts, and the account totals get transferred to the formula rate on a yearly basis.  The number that comes out the end of the formula is the amount that electric consumers pay for the transmission project on a yearly basis.  A rate of return is how much interest the company earns on its capital expenses.  That includes physical assets, like transmission lines, land they sit on, and it also includes the cost of building them in the first place.  It's heady stuff, but anyone with a little accounting experience can handle it just fine.

Once the formula rate and rate of return is set by FERC, you can help PSEG look over its costs every year to make sure they don't include any costs in their formula rate that shouldn't be charged to ratepayers.

To wrap up... I urge you to download and read PSEG's application for FERC incentives.  It may answer a bunch of the questions I have seen swirling around, such as where's the data proving need?  Why was this project selected instead of upgrading existing lines?  If you have questions, why not take them to the PSEG attorney at tonight's meeting?  She's fun to talk to.  Be nice. 

Another utility "dog and pony show" in the books.  Don't expect to accomplish much.  MPRP isn't going to be stopped at any of these meetings, but attending is your first step.  It's simply a networking opportunity.  Come hungry.  As one landowner remarked at one of these shows years ago... "We might as well eat.  It might be all we get."
Picture
2 Comments
Aunt Bea
7/15/2024 03:23:40 pm

Ya’ gotta get those pork sandwiches where ever you can!

Reply
Frank W MORRILL link
9/20/2024 02:20:40 pm

I've been to meetings. Have a sign, donate to STOPMPRP.
Route A goes through my paradise property on Harris Mill Rd.
We stand to lose 100s of thousands of dollars in asset value in addition to.our environmental habitat home to hundreds of animals.
I had read your piece months ago and it is equally.powerful today.
FERC recently gave PJM.its only failing grade of 6 similar entities.
We will keep up the good fight.
Whit & Robin Morrill
2001 Harris Mill Rd Parkton MD.

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.