Community Participation in Urban Transmission Plans

9/21/2016

2 Comments

 
Building new transmission is hard.  Building new transmission in urban areas is really hard.  Building new transmission will always foment opposition of some kind.  When the proposal affects urban areas, opposition will be loud, widespread, and fierce simply due to the number of people affected and the lack of space to construct new infrastructure in an already crowded landscape.

I came across an article recently that provides an opportunity to compare and contrast the actions of two different utilities attempting to build new transmission capacity for short distances in urban areas.

Dominion needs to build new capacity in the City of Alexandria, Virginia.  In preparation, it convened a "resident-led work group" and involved city officials in coming up with a plan that was least objectionable to the city and residents.  By doing this, the affected individuals were allowed to "buy in" to a solution that they felt they had some control over.  By giving the affected community a (real or imagined) voice in selecting a solution, opposition was ameliorated.
“In my view, Dominion looked really hard at the input this community had and listened to us around the table. I’ve served on a lot of task groups in Alexandria, but this is probably the best I ever sat on.”
It probably bears mentioning that the Dominion proposals included underground options.
And Mayor Allison Silberberg touted Dominion’s proposal for the fact that both options keep power lines underground.

“The good news is Dominion put forward two alternatives that are, in the proposal, both shown to be underground in Alexandria,” Silberberg said. “That’s really good, because that has been a top concern. We are awaiting more info from Dominion with regard to the specifics, and then once we get that specific info from them, we will be reconvening the work group, which has been excellent, to go over these considerations and the two options.”
Underground proposals rarely gather the same kind of fierce opposition as overhead proposals.  So, good for you, Dominion, for being flexible enough to compromise in order to realize the goals of the project, and not stubbornly insisting on a configuration the community would reject.

Now, let's compare this to FirstEnergy's current kerfuffle in New Jersey.  FE affiliate Jersey Central Power & Light (JCP&L) wants to build a 10-mile transmission upgrade in urban Monmouth County, NJ.  And they want to do it overhead, along a commuter train right-of-way.  FirstEnergy has not consulted with the community, but is insisting on building the project to its own specifications.  Opposition has been huge, swift, and fierce.  Community opponents number in the thousands.  Legislators have gotten involved.  And opposition to this particular transmission proposal has leaked over into FirstEnergy's proposal for a transmission only utility spin-off in the state.  What a mess FirstEnergy has made of this project and its community goodwill.  There's no going back from this.

By refusing to take community suggestion, and insisting that it cannot bury the project along the train right-of-way (although Dominion seems to be able to do just that in Virginia), FirstEnergy has done nothing but encourage opposition to dig in its heels and spread like wildfire.  The MCRP will never be built as currently envisioned by JCP&L.  FirstEnergy cannot bully or buy its way to community support for MCRP.

It's time for some new thinking at FirstEnergy's transmission headquarters.  In days gone by, it was accepted practice for a transmission utility to simply buy enough community support to get a project approved despite community opposition.  A utility never had to compromise when it could buy enough support to fool regulators and provide "political cover" for elected officials to claim that the community at large supported the proposal.  A utility simply presented its planned project as a fait accompli and ignored any community opposition.  The times, they are a changing.

Dominion has accepted that there is a better way to get transmission built without widespread community opposition that delays projects and increases their cost unnecessarily.  FirstEnergy is still banging its corporate head against a brick wall, refusing to change, and causing delays and unnecessary costs for projects it does manage to get approved through third-party advocacy.

There is a better way.  And it works.  If FirstEnergy wasn't so mismanaged, it would clean house in its transmission department and restock it with folks from Dominion.
2 Comments
Tricia
2/14/2017 04:11:43 am

Thank you for this post. I live in one of the communities that MCRP wants to plow through with no regard for the residents. FE has consistently shown they do not have any regard for the communities or their ratepayers as they continue to spend big money buying ads and lobbyists.

Reply
Ratepayer
2/14/2017 06:03:54 am

...and whose money is FE spending buying persuasive advertising and political lobbyists? Is it yours? According to testimony filed at the Federal Energy Regulatory Commission, FE believes that it may spend your money to convince you its transmission projects are necessary because PJM has determined that FE's transmission projects are "necessary" and you will receive "benefits" from the transmission project, if constructed. Of course, FERC didn't buy that and actually opined that FE's advertising and lobbying was nothing more than an attempt to influence the decisions of public officials to approve its transmission projects.

FE consistently mismanages community engagement on its transmission proposals because it continues to utilize advocacy instead of true community engagement.

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.