StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Clean Line's Shifting Business Plan Passes Risk to Municipalities

3/1/2016

1 Comment

 
Clean Line has been "developing" its numerous transmission projects for 7 years now.  Seven years!  And not one of the projects is approved and ready for prime time.

As a "merchant" transmission company, Clean Line has no captive customers from which to collect its costs.  Clean Line must shoulder all financial risk of its own projects.  Unlike other transmission projects ordered by regional planning authorities that collect their costs from regional ratepayers, Clean Line may only collect its costs from customers who sign contracts to use its project capacity through negotiated rates.  This means that even if Clean Line gets a project approved, it still must find customers to financially support its construction and operation.

Initially, Clean Line's business plan depended on big utilities to sign contracts to use its capacity.  In the past, Clean Line made much of a Memorandum of Understanding it signed with government power marketing authority Tennessee Valley Authority.  Clean Line liked to pretend this MOU meant TVA was a confirmed customer.  However, the MOU simply indicated that TVA might be interested in using the project in the future.  It was not a contract.  But it was an indication that Clean Line was depending on large utilities in "states farther east" to buy huge chunks, or the entire amount, of its capacity. 
"We think we can provide green power at an attractive, fixed-rate price for TVA and other utilities in the region," said Jimmy Glotfelty, executive vice president for Clean Line Energy.
Clean Line's initial efforts to secure customers focused on big utilities.

But when TVA studied the Clean Line proposal in its Integrated Resource Plan, it found it did not need Clean Line's transmission capacity to provide its customers with the most economic and reliable energy in the immediate future.  And Clean Line stopped talking about the TVA.  In addition, no other big eastern utilities signed up or showed much interest in the capacity Clean Line is selling.

Next, Clean Line advertised two of its projects in an "Open Season" in order to find potential customers with which to negotiate rates.  All interest in its projects came from wind generation companies in Midwestern states at the source ends of the lines.

Clean Line's secondary efforts to secure customers focused on wind generators.

But none of these wind generators had customers to buy the power they generated, therefore, they could not sign contracts for Clean Line capacity.  The wind generators were speculative -- as yet unbuilt -- and the generators need customers to raise money to build their projects.  However, no user utilities showed interest in buying generation from non-existent generators.  How do you price something like that?  How do you set delivery amounts and dates?  It's a fungible commodity.  Depending on generators to buy its capacity, Clean Line stands at one end of a string of dominoes that may or may not topple in line.  Too much uncertainty and too much risk for utilities, who can instead purchase a known quantity of renewable generation, at a set price, with a set delivery date, from an existing generator and shipped via existing transmission lines.  The price just isn't that good to take on Clean Line's kind of risk, if it's even possible to sign a contract to purchase energy from a non-existent generator delivered via a non-existent transmission line that may or may not ever be built.

Clean Line is not an energy generator.  It can't sell energy.  It is only the extension cord proposed to bring future generation to customers at a set price.  It's an extension cord that isn't plugged into anything.  Buying capacity on Clean Line commits utilities to purchasing energy from future generators in a set geographic area at an unknown price.  If the generators aren't built, or their generation costs are higher than anticipated, the purchaser of Clean Line capacity would be locked into purchasing energy at whatever price is offered by the generators.  The generators would have market power over the captive customers to charge whatever they want.  If a captive utility customer chooses not to buy energy after all, it's still on the hook to pay for the capacity on Clean Line's extension cord, whether it uses it or not.

So, we've yet to see any contracts for Clean Line's capacity from wind generators.

Clean Line's latest quest for customers focuses on municipal public power entities that provide power at cost to their own cities and towns.  These are much smaller chunks of each Clean Line's 3500 MW capacity, coming in at 25 or 50 MW each.  It's going to take a whole lot of municipal customers to make a Clean Line financially feasible.

But not only is Clean Line trying to sell municipalities on future energy prices it cannot guarantee, it's also "offering" the municipalities the "opportunity" to invest municipally-astounding sums of money into its project and take on the risk of losing the municipality's investment in the project in its entirety if the project is never built.  Clean Line's proposals are being reviewed by municipal power employees that may not understand its merchant transmission business model and wrongly believe their investment would be "guaranteed" to produce a return, or be refunded if the project goes belly up.  It just can't happen -- Clean Line has no customer base from which to produce a return on equity, and no bond in place to guarantee a refund of investment if the project doesn't pan out.  In addition, the municipal contracts must be approved by city council or other elected officials who have no knowledge base about electricity or power purchases.  Whatever Clean Line tells the city about its proposal could be bought hook, line and sinker, without independent expert review.

So far, Clean Line has convinced the City of Tallahassee to "buy up to 50 MW of wind power from its wind transmission project."  I highly doubt that.  The only thing Clean Line can sell is capacity on its proposed transmission line, not energy.  If the City of Tallahassee thinks it's bought a certain amount of wind power from Clean Line, delivered on a certain date at a certain price, it needs to think again.  Who knows what Tallahassee committed to do -- the actual agreement hasn't been published, and the press release was obviously less than honest.

Clean Line has also attempted to sell the City of Hannibal energy at a quoted price, or an investment in its project.  The City has tabled the issue for the time being, but municipal power employees vow to come back with the plan at a later date.

Word is that Clean Line is courting numerous municipal power agencies to sign up for similar deals.

What Clean Line is doing is essentially transferring its project risk onto the backs of struggling municipalities by signing them up for capacity commitments or "investments" in its projects.  If the project is never approved and built, the cities end up holding the bag.

Clean Line's whole business plan is based on transferring its corporate risk of project failure onto the backs of potential customers.  First, it was big utilities.  The utilities, no strangers to the power purchase game, did not become customers.  Next, it was future wind generators, who would, in theory, sign up to purchase capacity which they would wrap into their delivered price of energy.  That didn't pan out because the generators had no customers upon whom to transfer the risk.  Now it's municipalities, who struggle to find economic and reliable energy sources for their citizens.  If the big utilities and the energy generators didn't want to shoulder Clean Line's brand of risk, why would a municipality want to carry the company's water?  I think it's because they don't know any better.  And that makes me sad.

So, in Clean Line's honor, I'm going out this afternoon to give $20 to the first panhandler I see.  Maybe he'll offer to sell me some energy at a mind blowing price! 
1 Comment
Anon
3/6/2016 04:31:31 am

So some of the same people "subsidizing" these lines against their will by sacrificing property value and future earnings on the land they're taking may ultimately be on the hook for construction costs (lost investment if they go belly up) and higher energy prices? Isn't there a regulatory agency that can pull the reins here? This really sounds predatory?

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.