Cheers and Jeers for DOE's Draft Congestion Study

10/25/2014

0 Comments

 
Section 1221 of the Energy Policy Act of 2005 directed the U.S. Department of Energy to complete a transmission "congestion study" every three years.  The congestion study is supposed to lead to designation of "National Interest Electric Transmission Corridors" (NIETCs).  A transmission project sited in a NIETC is subject to "backstop" permitting authority by FERC if a state fails to act on a permit application within one year, or lacks authority to issue a permit.  It's a three-step process to federal electric transmission siting and permitting that should NEVER be allowed to happen.

DOE's initial attempts ran into a buzzsaw of opposition that ended up in two separate federal court decisions that effectively castrated Sec. 1221.  But, hey, that Sec. 1221 mandate still exists, so DOE must still go through the motions.

And that's what they did, albeit 2 years past the 2012 due date. The DOE secretly opened their "draft" congestion study up for public comment (never mind the contradiction of a secret opportunity for public comment, we won't dwell there). 

The public commented -- nearly 100 comments panning the report and warning against designation of any new NIETCs were submitted by interested "stakeholders."

But, a handful of industry players also found out about the secret study and submitted comments.  So, let's take a look!

Utilities SDG&E, Southern Co., Duke, and Florida Municipal Power Agency filed self-serving comments about their own service territory, either pointing to "congestion" where they want to build lines, or cheering a DOE finding that there was no congestion in their region.

Regional transmission organizations Southwest Power Pool, NY-ISO and ISO-NE
also filed comments.  The general gist of their comments was that RTOs already have robust transmission planning processes and power markets that make DOE's congestion study a frivolous and unnecessary duplication of effort.  And then they resorted to redline editorial corrections.  I did get a kick out of ISO-NE's correction to add offshore wind to DOE's narrow resource focus:
Page 49:
The best onshore renewable wind resources (i.e., those with the highest potential
capacity factors) tend to be located far from load and sometimes in areas with less
transmission than desired for effective resource development. The best offshore renewable wind resources, however, are often located close to load centers, as is the case with New England.
Bravo, ISO-NE!

Edison Electric Institute (EEI), the investor-owned utility lobbyist organization, told DOE to forget all about that NIETC stuff and to spend its time finding ways to streamline transmission permits on federal land.  Yes... that's just what's missing from America's National Parks -- more and bigger transmission lines!  Just think how sweet the Grand Canyon would look with a couple of huge transmission lines spanning it at its widest points!  And wouldn't Old Faithful be much, much cooler if it erupted into an overhead transmission line and created even more steam and maybe an electric arc or two?
  Yeehaw.... idiots!

WIRES, the transmission developer's lobbying group just seems to want to get its paws on a whole bunch of congestion data.  If DOE can't find or easily gather this data for WIRES's use in proposing competitive transmission projects, then WIRES thinks the DOE should pursue new legislation to obtain it, no matter how much providing this information burdens other utilities.


The American Wind Energy Association and Next Era Energy want DOE to allow transmission developers to do their own "congestion studies" and apply to DOE for designation of narrow "corridors" just wide enough for projects they want to build.  That's just ridiculous!!  A version of this bastardization of Sec. 1221 was proposed several years ago, and was promptly disposed of by Congress.  Not a good idea!  DOE doing this study and designating corridors is bad enough without throwing wide the door to self-serving "studies" and corridor requests inspired, not by need for new transmission, but by corporate greed.

And speaking of corporate greed, I've saved the best for last.  As expected, our heroes at Clean Line Energy just couldn't be left out of a process where it may benefit by using the government as its own personal land agent to take what it isn't granted by individual states.

Clean Line makes a bunch of obsequious comments that really don't do much but promote its own projects and display their self-centered stupidity. 

Clean Line made much of this diagram:
All of Clean Line’s projects originate in a Type 1 Conditional Constraint Area, identified by DOE in the 2009 National Electric Transmission Congestion Study (“2009 Congestion Study”) and illustrated in Figure 2. The 2009 Congestion Study defined a Type I Conditional Constraint Area as, “an area where large quantities of renewable resources could be developed economically using existing technology with known cost and performance characteristics – if transmission were available to serve them.” The 2009 Congestion Study also noted, “Construction of major new transmission projects would enable development of thousands of MW of new renewable generation” within these areas.
Hey, guess what, Clean Line?  The 2009 Congestion Study is no longer in effect and, in fact, was one of the straws that broke the DOE's back in Federal court.  Issuing a new report filled with old data is probably not a good plan.  And, hey, look at Figure 2 -- wind in those Type II Conditional Constraint Areas is conveniently located near all the big load centers that YOU are trying to reach with YOUR Type I projects.  Thanks for bringing up and illustrating just how worthless your projects really are!

Clean Line tells a HUGE lie:
Clean Line has engaged with thousands of local stakeholders in eleven states, where its five projects are actively under development.
Sort of sounds like Clean Line is having a great time making new friends, right?  In fact, Clean Line has inspired record opposition in every state it's entered, where "thousands of stakeholders" have spoken out against the project and participated in opposing Clean Line applications in the state permitting process.  Landowners routinely complain that they were not engaged by Clean Line, but found out about the project from neighbors and friends.  Clean Line's "public participation" process has been one gigantic failure.  Failure to properly consult with all stakeholders was a problem in DOE's last NIETC designation, and it's also the reason Clean Line is facing record opposition.  Ignoring landowner stakeholders does NOT nullify them, it only enrages and engages them!

Clean Line rumbles on about demand for its projects from unbuilt wind generators.  Note, Clean Line doesn't mention any interest from load serving entities, most likely because there isn't any!  And Clean Line's price for "all in" delivery includes the production tax credit that expired LAST year. 

Clean Line even elects itself to speak as a champion for you struggling farmers!

These are real projects, many of which have land leased for wind turbines from
farmers seeking new sources of income, as drought has made traditional farming livelihoods uncertain. Wind power represents new hope for drought-resistant income and economic development in regions of the country otherwise struggling with diminishing populations.
Looks like you all should give up farming and sit on the porch, watching the turbines turn and counting your cash.  Where's our food supposed to come from?  Make sure Clean Line gets at the end of any buffet line...

The next step is for DOE to "review and consider" comments on the draft study, and to prepare and release a final version of the study.  Watch this website, because it's likely to be another secret public process from our taxpayer-funded U.S. DOE!
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.