StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

ATC/ITC Jump Aboard the Ratepayer Funding Express

1/23/2019

0 Comments

 
Last week, the Federal Energy Regulatory Commission (FERC) approved an abandonment incentive for both companies to recover their investment in the Cardinal Hickory Creek transmission line across Wisconsin and Iowa.  FERC has been allowing incentive rate treatments for transmission investment since the mid-2000's.  As incentives go, this is one that doesn't have immediate rate impacts and may never actually be used... unless the Cardinal Hickory Creek project is abandoned before being completed.

What's abandonment and what does the incentive do?  Abandonment is just a fancy term for project cancellation.  In order to collect on this incentive, the utility must have no fault in the abandonment.  The project must be cancelled for reason.  A utility can't simply cancel a project without reason, and then collect its investment.  Like most projects granted this incentive, Cardinal Hickory Creek is the product of a regional planning process.  Once ordered to construct the project by the regional authority, the utility must proceed until ordered to stop by the authority.  Regional planning authorities sometimes cancel projects before they're built, usually because the case for "need" falters and the authority can no longer support building it.  Another reason to abandon a project is if it fails to receive all needed approvals, such as from a state regulator or agency, from a local government, or from a federal agency.  Is there ever a "sure thing" when it comes to transmission approvals?  There shouldn't be, since states have sole jurisdiction on transmission permitting and siting.  Many consider the abandonment incentive unnecessary, because every transmission project faces the risk that it may not be permitted.  Why are only some of them awarded the incentive, and not all of them?  Is the permitting risk so pervasively routine that incentives to lower the risk are unnecessary?  It all depends on what the utility asks for.  FERC doesn't award incentives that aren't requested.  So, is it indicative of a higher risk when a project applies for the abandonment incentive and is approved?  Perhaps... but maybe it's more a product of the amount of money that must be expended before approvals are secured.  The  more money the utility must put into the project before the approval risk is ameliorated, the greater the loss it may suffer if approvals are not received.  Having the abandonment incentive turns on the money spigot, allowing the utility to invest large sums in a transmission project with little to no risk that they won't be able to recover it later, plus interest (return on equity).  And it should be noted that FERC is guaranteeing that the utility can apply to recover this investment from ratepayers.  There is no special governmental fund behind this incentive, it's your money at risk here.

Now on to how it works...  if a project is abandoned, the utility must make a filing with FERC that demonstrates the abandonment wasn't their fault, and detailing the project costs it seeks to recover, as well as the suggested time period for recovery.  Other parties may intervene to protest any of these contentions, and eventually FERC makes a determination of whether the abandonment was through no fault of the utility, how much of the claimed expense may be recovered, and over what amount of time.  Also likely would be requests by the other parties to reduce the return on equity percentage.  On the matter of how much may be recovered, FERC allows "prudent" expenses to be recovered.  What's "prudent?"  It is defined as an action that would be taken by a similarly situated utility manager at that particular point in time.  And there is no Monday morning quarterbacking going on here... nothing that happens AFTER the expense matters because it could not be known to the utility at the time it made the expenditure.  As well, the burden of prudence gets shifted to the other parties.  All utility expenses are presumed prudent unless another party proves they are not.  It's a heavy burden to carry.

Because a utility's FERC formula rate segregates capital (or plant) expenses from Operations & Maintenance expense that is recovered dollar for dollar as it is spent, the abandonment incentive only applies to abandoned plant.  Plant expenses are capital expenses -- the cost of the infrastructure, or physical plant.  These expenses are not reimbursed through the formula rate until the plant goes in service (is completed and working).  Therefore, they're accumulating while the plant is in the approvals, engineering, and construction phases.  Once plant is put in service, it slowly depreciates during its useful life, and the utility is paid for its use over that period of time (plus return, or interest) on the remaining balance.  If FERC approves an abandonment filing, it would allow the utility to begin recouping its investment in plant, even though it never went in service.  Usually recovery times are shortened here to a period between 1 to 5 years, depending on the plant balance and its effect on ratepayers.

What can a utility put in its plant accounts?  It's tricky and nuanced and comes with thousands of pages of instructions, known as FERC's Uniform System of Accounts.  But generally it includes physical assets, engineering costs, land costs, surveying costs, siting costs, regulatory and permitting costs, and labor.  It shall NOT include public relations or advertising costs.  (yay, precedent!)  So if you notice your utility spending a lot of money on advertising, public relations or lobbying, do not wait until abandonment happens to try to get those costs deemed imprudent.  Those costs may have been recovered as O&M in previous years.  It's unclear where ATC may try to fit these costs into its recovery (but they do recover them, according to a former executive testifying before a FERC ALJ).  FERC's Opinion No. 554 determined that advertising and public relations are not recoverable project cost in any account.  Keep this in mind going forward.

This article covers FERC's approval of ATC/ITC's abandonment incentive, but gets somewhat lost on process.  It claims:
In 2012, the developers of a proposed transmission line between West Virginia and Maryland sought to recover $121.5 million the company had spent before grid operators decided the $2.1 billion project was no longer needed.
FERC later told the utilities they were ineligible for at least $7 million of the $121.5 million requested, including $6.2 million in advocacy, advertising and lobbying expenses.

Of the $6.2M disallowed, only a very small portion was ever incorrectly recorded in plant accounts.  That disallowance flowed from a  number of formal challenge rate proceedings that had absolutely nothing to do with PATH's abandonment.  Unfortunately FERC consolidated the formal challenges with the abandonment for "consolidation" of two issues that were not at all similar.  I can see how the confusion happens.  It's a FERCenese problem.  (FERCenese |ferk in knees| noun:  The incomprehensible, acronym-laden gibberish spoken at FERC that is hard for common folks to understand.  Origin:  Electric ratepayer Scott Thorsen, standing in a field in Illinois.)
There are some who want to celebrate the fact that ATC/ITC believe they need the abandonment incentive because they believe it indicates a real chance at failure.  And there are some who are believe that the granting of the incentive makes the utilities more likely to persist instead of abandoning the project.  Let's take a look at what the utilities said to FERC to convince them to grant the incentive.

ITC says:
There is significant uncertainty and risk to the Project due to its scope, size and long lead times, and because the Project requires approval from Iowa, Wisconsin and multiple federal agencies. In particular, there is a risk that the federal agencies may select a different river crossing than that authorized by the IUB or the PSCW. If this occurs, there is a risk of additional delay that may threaten the ability of the Project to move forward.
The Project also involves multiple owners which requires coordination. In addition, the Project may face challenges and objections in the easement acquisition process in Iowa.
ATC says:
These approvals and permits are not guaranteed to be granted, and the Project could be delayed or terminated, or the final route changed, if ATC is unable to obtain any of these approvals or permits. In particular, the federal agencies may select a different Mississippi River crossing than that authorized by the IUB or the PSCW, which could delay or result in termination of the Project.

The scope, size, cost, long-lead times and participation by multiple owners pose  inherent risks for the Project. As my description of the Project makes clear, the size, scope and complexity of the Project – involving approximately 102- to 120-miles of new 345 kV transmission line and a new substation and related facilities, spanning multiple states and jurisdictions, crossing the Mississippi River, with multiple owners for a cost of approximately $492 Million to $543 Million – is significant. Further, the easement acquisition process may be contentious, resulting in delays or increased costs.
Both companies are concerned about the Mississippi River crossing.  Both companies are concerned about permitting.  Both companies are concerned about easement acquisition.  Aren't these all things that the utilities can seek to overcome by spending more money?

I think there's merit to both arguments.  First, the utilities have tipped their hand to reveal their greatest weaknesses.  Yay!  But they have also been encouraged by the incentive to spend whatever it takes to steamroll permitting agencies and resistant landowners and drag this project out as long as possible before abandoning it.  Boo!
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.