StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

As The Dollar Turns

2/24/2024

3 Comments

 
Cost allocation for PJM's 2022 Window 3 projects has now officially turned into a long-running soap opera at FERC, and eventually through the courts.

Last year, PJM solicited new transmission to solve future issues with the retirement of 11,000 MW of existing generation in the eastern part of its region due to state "clean energy" policies, and the addition of 7,500 MW of new data center load concentrated in Northern Virginia.  In December, PJM selected and approved a huge portfolio of new transmission that looks like this.
Picture
You don't need to be a transmission engineer to notice that the majority of the new lines have a concentrated end point -- data center alley in Loudoun County, Virginia.  Power from southeast and southwest Pennsylvania (feeding from huge coal-fired plants in West Virginia) and power from central Virginia is being piped into data center alley on new transmission extension cords.  In the eastern portion of the map, power from southeastern Pennsylvania is being piped into the Baltimore area via new transmission extension cords.  The destinations for the new power is directly tied to PJM's statement of need -- new power for data centers and to replace closing coal-fired plants in the Baltimore area.  These are the causers of the new transmission.

In January, PJM made a filing at the Federal Energy Regulatory Commission (FERC) to allocate the more than $5B cost of this new transmission according to its regional cost allocation formula for big, regional lines.  Lines needed for regional reliability are allocated 50% to all load-serving utility zones across the region based on each zone's share of peak load for the preceding year.  The zones with the largest load receive a bigger share of this 50% of the cost of the lines.  The other 50% of the cost is allocated based on zones who will use the new lines.  Here's a map of PJM's utility zones.
Picture
PJM's territory is vast and stretches from the east coast as far west as Chicago, and as far south as North Carolina.  Under the 50% to load allocation, the ComEd zone around Chicago uses the most power so therefore it receives the largest share of these costs.  What benefit is Chicago getting from data centers in Virginia or "clean energy" in Maryland?  The correct answer is... zippety do dah!  However, the old thinking goes that since PJM is a connected region, any threat to reliability anywhere in the region could black out the entire region.  Therefore, everyone "needs" transmission to ensure reliability.

The old thinking also went that load increased incrementally around the entire region, with it being impossible to finger just one region for increased load, therefore everyone paid for regional increases in load.  It was too hard to measure exactly where load was increasing over time, and no new user created an outsized increase in load that could be isolated and allocated to the cost causer.  PJM cannot be changing its cost allocations constantly every time a new industrial plant asks for a connection, and these new users didn't cause a huge jump in power use when compared to the amount of power flowing across the region.

Toss that old thinking out the window!  PJM's latest portfolio of projects CAN be tied to just two things... closing baseload generators in eastern PJM and increased data center load concentrated in a tiny spot on PJM's vast map.  And what is causing that?  State "clean energy" policies that require the closing of existing fossil fuel baseload generators and prohibit their replacement with similar generators that can produce hundreds of megawatts of electricity when needed.  Replacement with renewables is a fairy tale.  Renewables take too much land for the amount of power they produce, and the power they produce is not reliable.  It takes many more megawatts of renewable power to equal one megawatt of fossil fuel power because renewables are such weak generators and they are intermittent and cannot be relied on to produce power when needed.  If we rely on renewables to keep the lights on, we're only kidding ourselves.  We cannot build enough renewables to take the place of all the fossil fuel generators in PJM that keep the lights on.  Here's a graph showing the source of PJM's power this morning that is powering this computer, and everything that's making your Saturday happy.
Picture
Without coal, gas and nuclear, we wouldn't have electricity.  This isn't a one-off, PJM's graph looks like this on a daily basis.  If we are ever going to get to zero carbon, we need to start building lots of nuclear power... yesterday.  Wind and solar and "other renewables" are not going to get there... EVER.  PJM has no control over power generation.  It only has control over transmission to get available power to load.  Generation is a state issue... except we deregulated it years ago so the states have no control over it either.  Generation is controlled by market, that is when it's profitable to build new generators, the market will inspire new builds.  However, PJM steps in long before the market can actually work and builds transmission to ensure reliability.  In certain states with "clean energy" policies, it is impossible to build new fossil fuel generators.  And it doesn't help that Big Green is putting pressure on existing generators to retire early with threats of lawsuits.  It's accelerating, and we are so screwed!  When The Sierra Club is in charge of your power supply you should be frightened.  They have but one goal... to shut down fossil fuels.  They have no responsibility to keep the lights on.

Now that I've set the table (or maybe it was just a rant), let's get back to PJM's cost allocation filing.  PJM makes numerous filings like this every year, and other regional grid operators do as well.  It's usually routine... filing is made and FERC rubber stamps it.  Sometimes a few entities will file objections, but they are rarely sustained.  Once, about 20 years ago, numerous states objected to PJM's cost allocation for its Project Mountaineer transmission projects.  These 500kV projects were for the purpose of increasing the use of coal-fired electricity in eastern PJM by 5,000 MW, and states in the other parts of PJM objected to paying for them.  That case (Illinois Commerce Commission v. FERC) ended up at the 7th Circuit Court of Appeals... twice... before PJM adopted its current cost allocation methodology.  The Court said that FERC had to demonstrate that the costs of those projects were allocated to the cost causers.  Since then, things have settled down.

However, PJM's latest projects have lit another fire that is probably going to burn as bright as the last one.  Something extraordinary is happening in PJM's cost allocation FERC docket.  In addition to the comments filed by consumers, and the protest of the Maryland Office of People's Counsel that more of the cost should be allocated to Virginia than Maryland, last week the Virginia State Corporation Commission filed comments basically calling Maryland a hypocrite and stating that Maryland is equally to blame for these new transmission lines.  I tend to agree... that both Maryland and Virginia are hypocrites!  These are the two states causing all the "need" for new transmission lines that will be paid for by other states.

But it's not going to end there... a giant parade of entities have intervened in this case at FERC.  Being an intervenor means you are a party to the case.   Only parties have standing to request rehearing at FERC and eventually appeal the case in federal court.

Intervenors include:
  1. FirstEnergy (utility building some of the new lines)
  2. New Jersey Board of Public Utilities
  3. American Electric Power (utility building lines)
  4. Dominion (utility building lines)
  5. Exelon (parent company of utility building lines)
  6. Delaware Division of Public Advocate
  7. PPL (utility building lines)
  8. Calpine (generation company)
  9. Rockland Electric (utility in PJM assigned costs)
  10. Duquesne Light (utility assigned costs)
  11. New Jersey Division of Rate Counsel
  12. Old Dominion Electric Co-op (utility assigned cost)
  13. Organization of PJM States
  14. North Carolina Electric Membership Corp. (utility assigned cost)
  15. Pennsylvania Office of Consumer Advocatte
  16. Maryland Office of People's Counsel
  17. Maryland Public Service Commission
  18. PSEG (utility building lines)
  19. West Virginia Public Service Commission
  20. Southern Maryland Electric Co-op (utility assigned costs)
  21. Pennsylvania Public Utility Commission
  22. Dayton Power and Light (utility assigned costs)
  23. Ohio Consumer's Counsel
  24. American Municipal Power (utility assigned costs)
  25. Long Island Power Authority (utility assigned costs)
  26. Virginia State Corporation Commission
  27. Northern Va. Electric Co-op (utility assigned costs)
That's a lot of intervenors!  Many more than a normal FERC docket.  You may even be able to sort them into "camps" based on whether they are entities that will pay these costs, or whether they are entities that will benefit financially from building these projects.  It really sucks when they can be placed in BOTH camps, such as the utilities assigned costs that also benefit from building new projects.  Do you think these entities will side with their ratepayers against being assigned costs for these projects, or will they side on gladly accepting costs because their financial interests are greater than their public utility responsibilities to their customers?

So, what happens next?  There may be more intervenors and more comments, but eventually FERC will issue an order.  No matter what FERC decides, one "camp" or the other isn't going to like it.  That camp will file for rehearing.  FERC will reconsider the matter and issue another order.  One camp won't like that and will file an appeal in the federal circuit court(s) of appeal.  The Court will decide the matter and remand it to FERC with instructions to issue a new order that comports with the Court's instructions.  Once FERC issues the new order, it may be appealed again, and back to the courts it goes.  One camp may decide to appeal the federal court's order to SCOTUS.  It's going to drag on for years, like a bad soap opera.

Meanwhile, PJM will continue to pursue its projects.  If any cost allocation adjustment are made due to the appeals, that's a money issue that will be taken care of through rates.  The utilities assigned to build these projects will file applications for permits to construct with some of the intervening states.  Think about how that will go...  If a state denies a permit, permitting may be bumped up to FERC under new backstop permitting laws created by the Infrastructure Investment and Jobs Act in 2021.  The longer the permitting process for these projects, the higher their costs climb.

And what about those costs?  Will the possibility that zones in Virginia and Maryland are eventually assigned more of the costs become a risk factor that will impact the need for these projects in the first place?  Will data centers want to continue to build in Virginia and accept the risk that the cost of their electricity is going to skyrocket in the future when the legal cases are finally settled?  Or will they decamp to cheaper pastures without the risk?  (Don't let the door hit you in the ass on the way out!). And what about Maryland?  Will skyhigh electricity costs cause Maryland to re-think its clean energy policies that prohibit the building of new fossil fuel plants?  Will Maryland begin a nuclear generation renaissance that could be equally expensive?

Those are the only changes that will make a difference in PJM's load forecast, but getting there will be rough.  PJM never changes its mind, once it is made up.  FERC should require PJM to create a new cost allocation method for new transmission due to state "clean energy" policies that is involuntarily allocated to the states whose policies cause the new transmission.  PJM should also create a new cost allocation policy dealing specifically with data centers.  This relatively new electric user stands out as a huge load that must be separated from normal, incremental load increases.  Data centers use so much power, they are in a class by themselves.  While FERC cannot allocate costs directly to data centers, it can allocate costs to the zones in states where the building is causing need for new transmission.  It would then be up to the state whether to spread the costs of the transmission among all users, or allocate it to data centers directly.  Whatever happens, it won't be an easy decision, and someone isn't going to like it.

Probably you.  Your electric bill is going to skyrocket.

Be sure to tune in to our next episode when FERC issues an order on PJM's cost allocation filing... this is going to be the longest running soap opera in history!
3 Comments
Luke
2/26/2024 04:27:48 pm

Do they intend on eventually building lines to ComEdy and connecting lines like RICL would’ve been from Iowa with those lines going to the east or is that an impossibility?

Reply
Keryn
2/29/2024 08:52:46 am

I don't see anything like that in any plan, nor has it been mentioned.

Reply
Luke
3/4/2024 12:41:41 am

I was just wondering if it would be feasible, theoretically speaking. ComEdy, while in PJM, is geographically separated from and not continuous with the rest of PJM. Does that prevent that from ever being able to happen?




Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.