But have things changed over the past six years? Has the complete failure of GBE to get anything accomplished in that time taken the shine off the project? Is the KCC now once-bitten twice shy? Perhaps. At any rate, the honeymoon now appears to be over.
Last fall, Clean Line applied to have its permit extended for another 5 years (until 2023) like it was nothing. Like they expected KCC to simply fall at their feet and grant any request. After all, that had been the tone of their relationship with KCC. Whether it was a changing of the guard at the KCC to new folks not under Clean Line's spell, or the smart intervention of one of GBE's landowner opponents, the extension didn't happen. The KCC ordered Clean Line to provide answers. But instead of doing that, Clean Line revealed that it had contracted with a new owner to purchase the project, if only KCC would approve the sale and extend the permit expiration date. Landowner issues seemed once again lost in the shuffle as a new proceeding began to examine the potential sale to Invenergy.
The KCC surprised again when its staff filed testimony in the acquisition docket. Instead of the sycophantic support Invenergy expected, the Staff recommended new conditions to be placed on approval. Most surprising of all was a discussion of landowner impacts resulting from the stalled project, and a condition designed to protect them from continued uncertainty.
Condition No. 4: Invenergy shall make preliminary easement payments of [redacted percentage, most likely 30%] of the total eventual compensation to all Kansas landowners affected by the line siting within 12 months of a Commission decision to extend the 13-803 sunset provision or gaining approval for a new line siting.
And that was the basis for KCC Staff's recommended condition, to provide some certainty to landowners. Go or no go?
But, as expected, potential new owner Invenergy flipped its lid over the conditions, this one in particular. Earlier this week, Invenergy filed its Rebuttal with multiple reasons why this condition is unworkable in its entirety. First of all, Invenergy says the KCC can't legally impose this condition and that Invenergy is entitled to string landowners along for another 5 years, at its own discretion. Then it listed a whole bunch of self-interested reasons why it could not make initial easement payments within one year. It's a long list, are you ready?
Placing a firm deadline by which preliminary easement payments must be made to all Kansas landowners unnecessarily and improperly restricts the ability of GBE, and by extension Invenergy, to conduct Project development according to its proven best practices which have resulted in the successful delivery of over 20,220 MW of generation projects and 392 miles of transmission lines.
Invenergy says there are so many things it must get accomplished before or during easement acquisition that a year isn't enough time.
Importantly, this deadline, in a vacuum, does not account for the many other Project development activities that must be carefully sequenced prior to and in parallel with easement acquisition in order to ensure efficient scheduling and deployment of capital to minimize Project costs and facilitate timely delivery, including but not limited to:
Completing the regulatory processes in the various states;
Closing on the Membership Interest Purchase Agreement;
Completing environmental permitting requirements, including extensive consultation with state and federal agencies;
Advancing Project engineering, including detailed design of the route to conform with environmental permitting requirements and landowner considerations;
Conducting an open solicitation for Project capacity;
Negotiating transmission service agreements with customers; and
Obtaining financing for construction of the Project.
There are endless variables that could impact the timing of this process, such that placing a firm deadline on payments to all Kansas landowners restricts the ability of GBE and Invenergy to efficiently manage Project development, and thus severely inhibits the Project’s likelihood of success.
And besides, the siting of the line is still subject to modifications. Invenergy simply can't pay the wrong landowner for the pleasure of stringing them along another 5 years! And, get this... "...it would be premature and wasteful to be required to make capital expenditures for securing easements that may not be ultimately used." But it is incredibly wasteful to keep landowners in limbo for years and years when they might be able to use their property more effectively if they thought it wouldn't ultimately have a transmission easement running through it. Invenergy only cares for its own profits, not landowner well-being.
Oh, but no, Invenergy really, really cares for landowners! Honest!
GBE and Invenergy fully understand and respect the uncertainty surrounding landowner impact from the Project, which has been an unfortunate consequence of regulatory uncertainty in other states that has hindered Project progress. It is important to clarify that, despite Invenergy’s concerns with Proposed Condition No. 4, it is in no way discounting the importance of landowner participation in the GBE Project and reaffirms its commitment to working with host communities to foster mutually beneficial relationships; this commitment is reflected in Invenergy’s track record of successfully negotiating over 16,000 lease agreements with landowners, entirely on a voluntary basis, across its project portfolio. GBE and Invenergy are planning, upon approval of the Transaction, to reengage affected landowners to provide Project updates and to be a resource for interested parties. This effort to become a known commodity in host communities and to develop and foster local relationships is an important first step in the land acquisition process that must not be overlooked simply for the sake of quickly obtaining easements.
Invenergy needs to get to know you before it condemns your property. Maybe they're going to serve community ham dinners and let your grandkids play in a rented bouncy house? Then, when you're full and complacent, they're going to condemn an easement across your land. Yeah, this is a really workable plan. Not. Who thinks up this stuff? And more importantly, why do they think you're not going to read about their plans before they happen?
I don't think Invenergy's definition of "certainty" is the same as landowners. Invenergy seems to think that "certainty" means the project is certain to be built. Landowners just want to know, one way or the other, whether it will, so they can get on with their lives.
The best way to obtain certainty regarding the Project is to utilize available capital in an efficient and logical manner. Each of the development activities listed above will add incremental certainty to the Project. Inefficient use of capital will decrease certainty by putting unnecessary financial and logistical strain on the Project. Accordingly, while the intended result of Proposed Condition No. 4 is to increase certainty, it will actually have the opposite effect.
So how do we give the landowners certainty? Invenergy suggests it will add an item to those "confidential" reports it submits to the KCC that informs on the number of executed easement agreements. So, giving more information in secret to a KCC that nobody trusts is supposed to provide peace of mind to landowners? Surely you jest, Invenergy?
Why can't Invenergy make "good faith" payments to all landowners potentially affected by its project within one year of approval? Is it because Invenergy has no faith? If Invenergy doesn't have enough faith in this project to part with any cash, why should landowners, or more importantly, the KCC, believe in its promises? Put up, or shut up, Invenergy.
While no landowners have intervened in the acquisition proceeding at the KCC and may not participate in settlement negotiations or hearing, they are not prohibited from commenting. Maybe the KCC needs a little love and encouragement from landowners in order to hold firm on this condition? If you've got a few minutes, shoot them your thoughts (or file them electronically). Reference Docket No. 19-GBEE-253-ACQ. Perhaps it's also time for the KCC to put up or shut up, and restore public faith in its mission.