The original, Section 1221, designated the Secretary of Energy to conduct an electric transmission "congestion study" and designate "National Interest Electric Transmission Corridors" (NIETCs) every three years. Transmission proposed in these designated corridors was subject to "backstop" permitting by the Federal Energy Regulatory Commission (FERC) in the event a state withheld approval of an application for a permit for more than one year, or lacked the authority to permit the project.
Section 1221 was promptly deconstructed in two federal courts. When FERC proposed that "withholding approval" included a denial, and that meant it could override a state's denial of an application, the 4th Circuit determined that "withheld approval" excludes a state's denial of an application, preserving state authority. In addition, the 9th Circuit determined that DOE did not properly "consult with states" before designating NIETCs, and therefore it vacated the corridors DOE had set in 2009.
Last year, DOE made a half-hearted attempt to produce the 2012 "congestion study," but was resoundingly smacked down by a whole bunch of comments, and hasn't done a thing since.
In practice, Section 1221 has been an abject failure.
However, the new Section 216, carried to Congress by Sen. Martin Heinrich (D-NM), attempts to fix all that by giving FERC authority to overrule a state denial of a transmission permit and use federal eminent domain authority to take private property. It also tosses NIETCs out the window as a means to identify worthy transmission projects and replaces them with an RTO/ISO finding that the project is "needed."
Good news: The new Sec. 216 does not apply to Clean Line in its current form.
Bad news: The new Sec. 216 will encourage a whole bunch of new transmission projects of questionable necessity, and landowners along existing corridors and/or those owning "open farmland" are always the first targets identified on the ol' transmission routing Etch-A-Sketch.
So, let's look at what the new Sec. 216 says:
(B) FEDERAL AUTHORITY.—The Commission may authorize, in accordance with subsection (d), construction of a high-priority regional transmission project that the Commission finds to be required by the present or future public convenience and necessity and in accordance with this section if--
“(i) a State--
“(I) fails to approve construction and authorize routing of a high-priority regional transmission project not later than 1 year after the date the applicant submits a completed application for authorization to the State;
“(II) rejects or denies the application for a high-priority regional transmission project;
“(III) authorizes the high-priority regional transmission project subject to conditions that unreasonably interfere with the development of a high-priority regional transmission project contrary to the purposes of this section; or
“(IV) does not have authority to approve the siting of the high-priority regional transmission project; or
“(ii) the developer seeking a certificate for construction under subsection (d) does not qualify to apply for State authorization to construct a high-priority regional transmission project because the developer does not serve end-users in the State.
Tell ya what... if FERC ends up with authority to overrule state transmission permitting decisions, there's going to be a lot more "turn-offs" for Commissioner Norman Bay, because the protestors will have moved "from pipelines to Order 1000." *Insert laughter here*
Second problem - how these "special" high-priority regional transmission projects are determined:
(1) HIGH-PRIORITY REGIONAL TRANSMISSION PROJECT.—The term ‘high-priority regional transmission project’ means an overhead, submarine, or underground transmission facility, including conductors or cables, towers, manhole duct systems, reactors, capacitors, circuit breakers, static VAR compensators, static synchronous compensators, power converters, transformers, synchronous condensers, braking resistors, and any ancillary facilities and equipment necessary for the proper operation of the facility, that is selected in a regional transmission plan for the purposes of cost allocation under Order Number 1000 of the Commission (or any successor order), including an interregional project selected under that plan.
It's quite obvious that S.1017 intends to "fix" everything that went wrong with the original Sec. 216, including the flawed NIETCs and the ability of a state to deny an application for a transmission project that did not serve its citizens. But, let's ask ourselves, does it really need fixing? State approvals aren't the problem with new transmission, it's federal approvals and studies that muck up and delay transmission plans. In addition, Congress has resolutely refused to make electric transmission siting and permitting a federal responsibility, and will most likely continue to do so.
There seemed to be little love for controversial legislation like S.1017 at Thursday's Senate Energy and Natural Resources Committee hearing. But, you know how Congress is... they get up to all sorts of hijinks if you don't keep your eye on them, so this bears a bit of babysitting.
One more thing before I wrap this up... where did this legislation come from?
The original Sec. 216 got its purpose from:
(4) In determining whether to designate a national interest electric transmission corridor under paragraph (2), the Secretary may consider whether--
(A) the economic vitality and development of the corridor, or the end markets served by the corridor, may be constrained by lack of adequate or reasonably priced electricity;
(B)
(i) economic growth in the corridor, or the end markets served by the corridor, may be jeopardized by reliance on limited sources of energy; and
(ii) a diversification of supply is warranted;
(C) the energy independence of the United States would be served by the designation;
(D) the designation would be in the interest of national energy policy; and
(E) the designation would enhance national defense and homeland security.
Now take a look at the purpose of the new Sec. 216:
(a) Policy.—It is the policy of the United States that the national interstate transmission system should be guided by the goal of maximizing the net benefits of the electricity system, taking into consideration--
“(1) support for the development of new, cleaner power generation capacity, including renewable energy generation located distant from load centers;
“(2) opportunities for reduced emissions from regional power production;
“(3) transmission needs driven by public policy requirements established by State or Federal laws (including regulations);
“(4) cost savings resulting from--
“(A) reduced transmission congestion;
“(B) enhanced opportunities for intraregional and interregional electricity trades;
“(C) reduced line losses;
“(D) generation resource-sharing; and
“(E) enhanced fuel diversity;
“(5) reliability benefits, including satisfying reliability standards and guidelines for resource adequacy and system security;
“(6) diversification of risk relating to events affecting fuel supply or generating resources in a particular region;
“(7) the enhancement of competition in electricity markets and mitigation of market power;
“(8) the ability to collocate facilities on existing rights-of-way;
“(9) competing land use priorities, including land protected under Federal or State law;
“(10) the requirements of section 217(b)(4); and
“(11) the contribution of demand side management (including energy efficiency and demand response), energy storage, distributed generation resources, and smart grid investments.