I don't have the orders yet, but here's FERC's summary of what they voted on at this morning's Commission meeting:
FERC grants in part, and dismisses in part, formal challenges; grants complaints, establishes hearing and settlement judge procedures
E-21, Potomac-Appalachian Transmission Highline, LLC, Docket No. ER09-1256-000, Alison Haverty v. Potomac-Appalachian Transmission Highline, LLC,
Docket No. EL12-79-000, Keryn Newman v. Potomac-Appalachian Transmission Highline, LLC, Docket No. EL12-85-000.
The order in Docket No. ER09-1256 sets for hearing challenges to PATH’s last two annual informational filings to update its transmission revenue requirement; the challenges are in accordance with special protocols that the Commission accepted as part of the formula rate in PATH’s tariff.
The order in Docket Nos. EL12-79-000 and EL12-85-000 grants the two complaints, each filed by a private citizen who wishes to participate as a party in PATH’s annual transmission revenue requirement review, due to their status as ratepayers.
Be sure to send in your RSVP for PATH's Oct. 16 open meeting, if you haven't yet, because FERC says you can attend.
Mood music!
Read a copy of FERC's Order here.