Armageddon in the PJM Region

5/15/2012

0 Comments

 
Grab your tin foil hat and crank up the generator, Armageddon is nearly upon us!  In a complaint filed yesterday, Primary Power LLC asks FERC to restore ownership of its SVC projects to Primary Power no later than July 13, and issue an immediate order preventing FirstEnergy and Dominion from beginning construction of the two projects that they stole from Primary Power by exerting their incumbent power over the PJM cartel.

"Primary Power respectfully submits that the actions of PJM and the Incumbent Transmission Owners addressed in this Complaint raise grave concerns for the future of new competitive transmission development in the United States. This is essentially the “Armageddon scenario” in which PJM and the Incumbent Transmission Owners have acted in a concerted, and unduly discriminatory, manner to prevent a potential new entrant from building new cost-of-service transmission facilities in PJM, despite the fact that there is a Commission order directly on point telling PJM to designate Primary Power if any of the projects that it sponsored were included in the RTEP. If Primary Power cannot be designated to build its SVCs in this well documented proceeding that already is the subject of a Commission order, then who can? If PJM’s actions are allowed to stand, it will provide a roadmap for incumbent transmission owners across the United States on how to block entry by competitors, and it will send a chilling signal to independent transmission developers and investors that the Commission is not willing to intervene to enforce its open access requirements. This Complaint thus represents a critical test case for the Commission’s commitment to opening up the market for transmission development to competition, which, as the Commission found in Order No. 1000, can result in more efficient and cost-effective solutions for ratepayers."

At issue here are two projects that will supply reactive power to the grid, without the building of new transmission lines.  Primary Power spent 5 years and $5M developing these projects and shared them with PJM and its "stakeholders" during the approval process.  PJM initially approved the projects and assigned them to their sponsor, Primary Power, for construction.  However, after all the work of design, development and approval was completed, PJM incumbent bullies and PIGS Dominion and FirstEnergy decided they wanted to build the projects instead.  So, what did PJM do?  They reassigned the projects to their favored incumbents, of course, and told Primary Power to go suck wind. 

I'm sure this doesn't come as any surprise to PATH opponents, who have had a front row seat to PJM's favoritism of its incumbent bullies  for the past 4 years.  PJM's bald favoritism of certain companies flies in the face of even the most basic logic, and it's way past time for FERC to rein them in.  Primary Power is but one more example of PJM's collusion with a handful of power conglomerates to increase their profits with the building of unnecessary infrastructure, and to prevent competitive markets.  Primary Power gets quite dramatic in their filing, however it's all true and well deserved.  The continued skewing of PJM's markets to favor certain incumbents keeps the prices consumers pay for electricity high and fails to provide the consumers with state-of-the-art, least cost options for electric service.  If PJM's arbitrary and capricious decision in Primary Power is allowed to stand, Primary Power will go belly-up and it's going to be a cold day in hell before another new company proposes an innovative (or cheaper) solution to identified transmission needs.  The incumbents will have exactly what they desire, a lock on all new transmission projects, similar to their current stranglehold on the development of new generation.  This does not serve electric consumers!

It's time to clean house at PJM.  The dirty dealing could be peeled off in layers at this point, and it's starting to stink up the place.  Once they've cleaned all the stink out of PJM, FERC should prohibit lobbying of any kind at PJM in order to prevent a recurrence.  Lobbying has no place in a competitive electric market that benefits consumers.  And while FERC is at it, they need to prohibit lobbying in their own house as well.  Regulation should never be subject to lobbying as lobbying does nothing to further just and reasonable, nondiscriminatory rates.
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.