StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

PJM Continues Making Poor Choices About Transmission Line "Constructability"

6/22/2014

1 Comment

 
Nearly 10 years ago, PJM's management made a very poor choice approving Project Mountaineer, a scheme to build more than $3B worth of new transmission in order to increase the transfer of 5,000MW of coal-fired generation to the east coast.  Project Mountaineer caused PJM to approve four new high-voltage transmission projects and add them to its RTEP:  TrAIL, Susquehanna Roseland, PATH and MAPP.  Only two of these highly controversial projects were ever built, and at a very high cost.  The other two were abandoned without ever turning a shovel of dirt.

PATH was re-routed within months of being introduced to the public, because PJM's approved plan for it called for "twin" 500kV circuits through densely populated, high-growth areas of West Virginia's eastern panhandle, northern Virginia, and Maryland's Washington, D.C. suburbs.  It just wasn't physically and politically possible to construct the project.  PJM's determination of the "constructability" of PATH was wrong.  Even its second choice of a single 765kV line through the area failed.

And PJM hasn't gotten any smarter about constructability since.  Its first major transmission project since the PATH/MAPP failure is also destined to "constructability" failure.  PJM recently selected PSE&G's proposal for a new 500kV line to parallel an existing line in Salem County, New Jersey to solve its Artificial Island problem.  PJM claimed its decision was based on the "constructability" of PSE&G's project.

So, what standard did PJM use?  PJM hired a company that does work for the companies bidding on this project to do a "Constructability Study."

The study accounts for environmental permitting, historical commission review, federal environmental review, and a host of other "risks."  It gave little moment to state utility commission review and permitting, and paid absolutely no attention to possible public opposition and its impact on permits necessary from local government.

I guess PJM and GAI Consultants have already forgotten what killed the PATH project they both had a hand in.  GAI opines that paralleling existing transmission lines will dampen opposition because there's no need to involve "new" landowners.  Right... because transmission lines are like potato chips... one is never enough!

The routing study and mapping shows urban and residential areas being crossed, and at one point the line runs practically right over top of a school.  Although all projects needed to acquire new right of way adjacent to the current one, GAI and PJM reason that PSE&G has an advantage here because of some old agreement over ownership of transmission assets.  I just don't see this agreement being helpful convincing landowners to agree to expand the current right of way.  Maybe PJM has forgotten what happened when TrAILCo attempted to utilize old right of way in Pennsylvania?  In that instance, trying to force old agreements on new landowners using unscrupulous land agents blew up in TrAILCo's face and most likely contributed to its eventual denial by the PA PUC.  In the end, TrAILCo had to abandon that old right of way and give it back to the landowners. 

The selected project also proposes an overhead river crossing in a very busy shipping lane, instead of the submarine crossing proposed by other projects.

This is a public opposition bonfire in the making!

So, what else could PJM have done here?  What other projects were in the running?  Projects choosing a route through Delaware were evaluated for "constructability" by a different company that actually considered public opposition, and none of that was very encouraging.  All projects will garner public opposition, some more than others.  DUH.

Damned if you do, damned if you don't.

But, wait a tick here.  There's one project on PJM's bid list that doesn't seem to have been evaluated in either "constructability" report.  I guess PJM batted it aside instantly, like a distasteful mint.

Atlantic Grid (yes, the ones who have been patiently trying to construct an offshore backbone transmission line to gather offshore wind generation and funnel it to shore at strategic locations) submitted something called the Garden State Reliability Project.
  It looks like this project was going to do something entirely different than the rest of the contenders.

The Artificial Island-related challenges to grid reliability and operational flexibility that PJM describes in its Problem Statement can be solved with the Garden State Reliability Project (GSRP), a proposed voltage source converter (VSC) high voltage direct current (HVDC) transmission system that connects Artificial Island to the Cardiff AC Substation near Atlantic City, New Jersey. GSRP has the capacity to controllably transmit 1,000 MW of power on its approximately 60-mile underground circuit. GSRP also incorporates static VAR compensator (SVC) facilities. The project is estimated to cost $1,012 million and to be in service by December 31, 2018.
Not only was this project going to fix PJM's little Artificial Island problem, it was also going to tie into Atlantic Grid's New Jersey Energy Link to provide a way to move nuclear power into the congested northern New Jersey load zone.  It would also provide backup, baseload power to balance the eventual offshore wind generation's variability.

But, Atlantic Grid's GSRP was proposed to cost 4 times as much as PJM's favored project.  However, GSRP provided many other benefits the other project didn't, such as black start capability for Artificial Island, and it was designed to meet future needs, instead of simply fixing today's little problem.  Low cost may be the easy choice for today, but sometimes it's just not as efficient.

PJM's "low cost" choices presume that a select set of landowners must be forced to sacrifice their private property for the good of society.  When is the rest of society going to make a sacrifice for its own good?  Adequately compensating landowners and/or building higher cost projects that don't require as much sacrifice from host landowners should be a sacrifice society is willing to make for its own good!  Want cleaner power?  Want your lights to stay on?  You need to pay for it, not some other landowners miles away who are not benefiting from the project.

And you know what was really innovative about Atlantic Grid's project?  It was completely underground and routed along road rights of way!  Minimal sacrifice for host landowners, minimal public opposition, minimal risk, minimal time to complete.
Another key GSRP project objective was to demonstrate timely constructability with a practical right of way (ROW) approach and low construction and environmental impact. GSRP is distinguished from high voltage AC line solutions to the grid reliability and operating issues at Artificial Island because GSRP has a more predictable in-service date. GSRP’s HVDC cable system would be buried underground in state and local road ROW, rather than being constructed as an overhead transmission line. Accordingly, building GSRP requires simple rights of access to existing road ROW granted by public entities. In comparison, AC overhead transmission solutions will require new or expanded ROW acquisition involving tree and brush clearing, high towers, aesthetic and environmental impacts, public opposition and litigation. All of these challenges associated with overhead lines cause less predictability and greater cost.
Instead, PJM seems to prefer continuing its old status quo of selecting projects proposed by its incumbents that are environmental, permitting and public opposition nightmares.  And we all pay for PJM's mistakes.
1 Comment
Dr. Luis Contreras link
7/1/2014 06:13:41 am

Constructability for the SWEPCO 50 mile line to Kings River was "dropped" as a EIS criterion after the data for the six routes did not support the preferred route. The other five routes were simply a distraction to divide Arkansas an Missouri. Keryn, thank you for this post, the basis of one more objection to APSC today. No one from APSC Staff reads our objections, AEP does and they will be part of a permanent record to celebrate like PATH whenever the line is abandoned. Legal expenses are mounting and we are irate at AEP

Reply



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.