AEP is Excited About Data Centers

10/31/2025

0 Comments

 
Picture
So, here I am again, analyzing IOU earnings calls and applying the bloviating the executives do to the reality facing landowners and ratepayers about how those profits materialize at their own pain and expense.

American Electric Power (partner in the proposed Valley Link 765kV transmission line) is just so gosh darned !EXCITED! about the uncontrolled growth of AI data centers.
David Keith Arcaro: I was wondering if you could maybe just give more of a sense of how the conversations are going with data centers and constraints on the system that you are seeing. So I guess I am curious, are you able to keep up with the transmission capacity needs for data centers to handle all of this load growth? You know, it is the wait time, you know, to connect that you are having to discuss with these customers? And is it fair to characterize a lot of this transmission CapEx that you are adding to the plan here? Is that opening up additional capacity to bring in these new customers? Wondering how that all kind of balances right now.
William J. Fehrman: Yes. Thanks for that question. Really excited about where we sit in this regard. As we have noted in here, the increased incremental load growth projected through 2030 is the 28 gigawatts up from the 24 that we talked about before. And that demand growth is roughly 80% tied to data centers in the commercial class and about 20% tied to the industrials. Breaking that up a little more, about 75% is related to transmission and distribution, while 25% is tied to the vertically integrated utilities. And so as I look out across the RTOs, roughly half ends up in ERCOT, 40% in PJM, and about 10% in the SPP.
And so as we look at where we sit to connect these customers, clearly we are working with them to site where we have available transmission today to help them with their ramp-ups in the manner in which they want to run their side of the business. And then in other cases, we are working with them to put in place behind-the-meter solutions. Obviously, 190 gigawatts. But in the meantime, as Trevor noted, we are very focused on reporting what we have signed. We are going to under-promise and over-deliver in this area, but I could not be more excited with where we sit across our service territory.
We are in, I would say, the catbird seat with regards to connecting data center load. The 765 kV transmission network that we have provides us with an extreme competitive advantage for where these folks are trying to site. And so I just see an amazing future ahead of us in this area.
Except for those 765kV transmission lines that are NOT YET built, and may never be.  Are the data centers dumb enough to believe AEP can get Valley Link built any time this century?  New transmission lines that take new property their entire length attract enormous opposition from landowners, ratepayers, and local and state governments.  The amount of opposition is directly related to the length of the line.  261 miles across West Virginia?  That's a lot.  Prepare for battle.

And what about West Virginia?  What are you doing there?
We continue to have conversations with state leaders regarding fair financial returns that they desire to attract more capital and make West Virginia an energy hub.

... we are fully engaged in West Virginia. We are working with all the stakeholders there, and that continues to be a major focus of mine. I am spending a significant amount of time in West Virginia to try and support a better outcome there.
Guess what?  West Virginians are tired of being the energy serfs who sacrifice for the economic development of other states.  We want to be more than just one gigantic power plant and a series of transmission lines.  There's a reason our kids grow up and move away, and West Virginia's population continues to decline.  There's nothing here for our young people anymore.

West Virginia has a remarkable opportunity right now, one it's been waiting for since the robber barons took control of our resources and our people more than 100 years ago.  There's an enormous amount of money behind data center growth, and the one thing data centers need most of all is abundant electric power.  West Virginia can attract that industry here because it is unique among Mid-Atlantic states as having an abundant supply of electricity.  In fact, West Virginia produces so much it exports it to other states.  Those other states use West Virginia's electricity to build their own economies with new data centers.

Stop exporting West Virginia's opportunities to other states on AEP's 765kV transmission system at West Virginians expense!  The only ones who benefit from  West Virginia being an "energy hub" are out-of-state corporations exploiting our people and our resources... the status quo for more than 100 years.
0 Comments



Leave a Reply.

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.